Question
2.31ft of head
Question
Minimum pressure for a group containing flushometer valves
Question
Minimum pressure for a group containing flush tanks
Question
Multiplier to the elevation above the water main to determine loss in static pressure
Question
Multiplier to the total demand for fixtures with combined hot and cold water to arrive in maximum separate demands
Question
Maximum velocity of water for sizing supply piping
Question
Minimum area of trench bottom for disposal field
Question
Sidewall area below the leach line may be added to the trench bottom absorption area
Question
Where leaching beds are permitted in lieu of trenches, the area of each bed shall be at least ____ greater than the tubular requirements for trenches
Question
Separation distance of leach bed excavation from the water table
RNPCP Appendix A and B
Score
0 / 10
Correct rate
0%
Correct: 0
Incorrect: 0
Unanswered: 10
Question list
1
2.31ft of head1 psi
2
Minimum pressure for a group containing flushometer valves103kPa or 15psi
3
Minimum pressure for a group containing flush tanks55.16kPa or 8psi
4
Multiplier to the elevation above the water main to determine loss in static pressure9.79
5
Multiplier to the total demand for fixtures with combined hot and cold water to arrive in maximum separate demands75%
6
Maximum velocity of water for sizing supply piping3m/s
7
Minimum area of trench bottom for disposal field14sq.m
8
Sidewall area below the leach line may be added to the trench bottom absorption area305mm to 914mm (1' to 3')
9
Where leaching beds are permitted in lieu of trenches, the area of each bed shall be at least ____ greater than the tubular requirements for trenches50%
10
Separation distance of leach bed excavation from the water table1.5m
11
Separation distance of seepage pit excavation from the water table3m
12
Minimum number of compartments of a septic tank (as per plumbing code)2
13
Minimum number of compartments of a septic tank (as per new ordinance)3
14
Minimum capacity of inlet compartment2/3 of tank capacity
15
Minimum liquid capacity of inlet compartment2cu.m
16
Minimum length of inlet compartment1.5m
17
Minimum width of inlet compartment0.9m
18
Minimum capacity of secondary compartment1/3 of tank capacity
19
Minimum capacity of secondary compartment1cu.m
20
Minimum length capacity of secondary compartment if tank has over 6cu.m capacity1.5m
21
Length of inlet compartment to be provided with additional manholemore than 3.7m
22
Minimum number of manholes for septic tank2
23
Minimum dimension of a manhole508mm or 20"
24
Minimum size of the vertical leg of the inlet and outlet fitting104.6mm
25
Minimum horizontal dimension of baffle type fitting when measured at the inlet and outlet pipe inverts106.6mm
26
Minimum extension of inlet and outlet pipe or baffle above the water surface101.6mm or 4"
27
Minimum extension of inlet and outlet pipe or baffle below the water surface304.8mm or 12"
28
Minimum vertical clearance of the inlet pipe invert above the outlet pipe invert50.8mm or 2"
29
Minimum extension of sidewalls above the liquid depth228.6mm or 9"
30
Minimum vertical clearance of septic tank cover above the back vent openings50.8mm
31
Minimum extension of partitions or baffles above the liquid level101.6mm or 4"
32
Minimum size of an inverted fitting, installed in the inlet compartment side of the baffle with the bottom placed midway the liquid depth104.6mm
33
Minimum earth load support capacity of septic tank covers, when the maximum coverage does not exceed 9m14.4 kPa
34
Minimum extension of bituminous coating below the water line of concrete septic tanks and shall cover all of the internal area above that point101.6mm
35
Minimum wall thickness of steel septic tank, internally and externally protected from corrosionGA 12 (2.8mm)
36
Ranking depth to remove loose materials from trenches before placing filter material25.4mm or 1"
37
Varying sizes of clean stone, gravel, slag or similar filter material to be placed on the trench19.1mm to 63.5mm (3/4" to 2 1/2")
38
Termination of filter material from the seepage pit excavation when used in combination with disposal fields1.5m
39
In distribution box, minimum vertical clearance of the invert of inlet above the inverts of outlets. Length of each line where dosing tank is required25.4mm
40
Length of each line where dosing tank is required> 152.4mm
41
Intervals of sewage discharge from the dosing tank through automatic siphon or pump3-4 hrs
42
Number of siphons or pumps to be provided when total length of pipe exceeds 304.8 linear meters2
43
Minimum number of drain lines per field1
44
Maximum length of each line in a disposal field305m
45
Minimum bottom width of trench457.2mm or 1.5'
46
Maximum bottom width of trench914.4mm or 3'
47
Minimum depth of earth cover of drain lines304.8mm or 1'
48
Recommended depth of earth cover of drain lines457.2mm or 1.5'
49
Minimum thickness of filter material under drain lines304.8mm or 1'
50
Minimum thickness of filter material over drain lines50.8mm or 2"
51
Minimum spacing between leaching beds1.2m
52
Horizontal spacing of distribution drain lines center-to-center1.8m
53
Distance of the perimeter of leaching bed from a distribution line0.9m
54
A cesspool without septic tanks may be installed when a public sewer will be available in less than:2 years
55
Minimum sidewall of cesspool below inlet; nit more than 3.1 meters in depth when 1.2 m thick pervious strata is found6.1m
56
Minimum sidewall of cesspool below inlet, when 1.2 m thick pervious strata is found3.1
57
In cesspool, the minimum extension of vented leg downward into an existing pit304.8mm or 1'
58
In cesspool, the minimum vertical clearance of the outlet flow line below the inlet, when overflow pits are added to existing installations152.4mm or 6"
59
Minimum number of compartments for interceptors2
60
Minimum horizontal distance of tree from septic tanks, seepage pits or cesspools3m
61
When disposal fields and/or seepage pits are installed in sloping ground, the minimum horizontal distance between any part of the leaching system and ground surface4.6m
62
In seepage pit, minimum extension of vented leg fitting below the inlet fitting304.8mm or 12"
63
Minimum diameter of seepage pit2.2m
64
Minimum thickness of seepage pit concrete wall101.6mm or 4"
65
Thickness of concrete block in seepage pits to be chamfered304.8mm or 12"
66
In seepage pit, minimum thickness of clean 19.1 mm gravel or rock in excavation voids behind the brick, block or concrete liner152.4mm or 6"
67
Minimum compressive strength of brick or block in seepage pit construction17225 kPa
68
Minimum sidewall of seepage pit below the inlet3m or 10'
69
Minimum thickness of cement mortar covering for seepage pit arch or dome50.8mm or 2"
70
Minimum extension mortar covering beyond the sidewalls of the seepage pit152.4mm or 6"
71
Minimum thickness of reinforced concrete slab cover of seepage pit127mm or 5"
72
Minimum earth load support capacity of slab cover for seepage pit19.2 kPa
73
Minimum dimension of inspection hole for seepage pit228.6mm or 9"
74
Depth of top of seepage pit arch or cover below the surface of the ground457.2mm to 1.2m (1.5' to 4')
75
Maximum Absorption capacity for Coarse Sand or Gravel203.7 L/sq.m
76
Maximum Absorption capacity for Fine Sand162.9 L/sq.m
77
Maximum Absorption capacity for Sand Loam or Sand Clay101.9 L/sq.m
78
Maximum Absorption capacity for Clay with considerable sand or gravel44.8 L/sq.m
79
Maximum Absorption capacity for Clay with small amount of sand or gravel33.8 L/sq.m