Question
RA 1378
Question
Set/s of plumbing plans, drawings, diagrams, and other documents to be submitted for the application of permit.
Question
Set/s of approved plans, specifications, and data to be retained by the Administrative Authority.
Question
Set/s of entire plans and specifications to be returned to the applicant.
Question
Set/s of entire plans and specifications to be returned to the Owner.
Question
Set/s of entire plans and specifications to be kept at job site
Question
Expiration of plumbing permit if work is not commenced from the date of issuance
Question
Expiration of plumbing permit if the work has been suspended or abandoned.
Question
Percentage of original fee to be paid for the renewal of permit.
Question
Request for inspection for the replacement of an existing equipment shall be filed not more than ______ after such replacement work is completed.
RNPCP Chapter 1 to 5
Score
0 / 10
Correct rate
0%
Correct: 0
Incorrect: 0
Unanswered: 10
Question list
1
RA 1378Plumbing Law
2
Set/s of plumbing plans, drawings, diagrams, and other documents to be submitted for the application of permit.6 sets
3
Set/s of approved plans, specifications, and data to be retained by the Administrative Authority.1 set
4
Set/s of entire plans and specifications to be returned to the applicant.2 sets
5
Set/s of entire plans and specifications to be returned to the Owner.2 sets
6
Set/s of entire plans and specifications to be kept at job site1 set
7
Expiration of plumbing permit if work is not commenced from the date of issuance1 year
8
Expiration of plumbing permit if the work has been suspended or abandoned.120 days
9
Percentage of original fee to be paid for the renewal of permit.50%
10
Request for inspection for the replacement of an existing equipment shall be filed not more than ______ after such replacement work is completed.72 hrs
11
Request for inspection shall be filed with the Administrative Authority at least _____ before such inspection is intended.3 working days
12
Alley means any public space, public or park ______ on width.2m to 3m
13
Court is bounded by ______ by the walls of building2 or more sides
14
Yards are open, unoccupied, _____ from ground to sky.unobstructed
15
Group vent is a branch vent that performs its functions for ___ or more traps2
16
Branch interval which corresponds to a storey height shall be not less than _____.2.43m
17
Brazed joints are obtained by joining of metal parts with alloys which melt at temperatures higher than _____, but lower than the melting temperature of the parts to be joined.449°C
18
Soldered joints are obtained by joining of metal parts with alloys which melt at temperatures above ___ and below ___.149°C, 427°C
19
Distance of the building sewer from the outer face of any building foundation or wall.0.60m
20
Mobile Home Park Sewer measures _____ downstream from the last mobile home.0.60m
21
Horizontal pipe forms an angle of not more than ___ with the horizontal line.45°C
22
Vertical pipe forms an angle of not more than ___ with the vertical line.45°C
23
Combustible construction is any structure with structural framework which ignites and burns at temperature of ___ or less.756°C
24
Confined space is a room or space having a volume less than _____ with 250kg calorie of the aggregate input rating of all fuel burning applicances installed in that space.1.4cu.m.
25
Equivalent of 1 fixture unit to liters per minute28.3
26
Equivalent to 1 fixture unit to gallons per minute7.48
27
Equivalent of one fixture unit to quartz per minute30
28
Equivalent of one fixture unit to cubic foot per minute1
29
Minimum capacity of a grease interceptor3 cu.m.
30
No of traps served by a unit vent2
31
Return bend is usually made of two ___ bends90°
32
Recommended slope for horizontal drainage pipes2%
33
Recommended slope for 102mm and 152.4mm diameter when impractical; and must be approved by Administrative Authority1%
34
Recommended slope for 203mm and larger diameter when impractical; and must be approved by Administrative Authority0.5%
35
Vertical installation of double sanitary tees maybe used when the barrel of the fitting is at least ___ pipe size larger than the largest side inlet2
36
The bottom of all pipe trenches deeper than the footing of any adjacent building or structure and parallel to it must be at least ___45°
37
Minimum depth of building sewer below the finish ground level0.30m
38
Maximum depth of building sewer below the finish ground level0.60m
39
Clear height of tunnels above the pipe laid in a trench0.60m
40
Maximum length of tunnels is 1/2 the depth of trench or ____.2.4m
41
Trenches shall be backfilled in thin layers of ____ above the top of the pipe with clean earth.0.30m
42
Minimum thickness of restaurant kitchen and other special use sink, bonderized and galvanized sheet steel.GA 16 B&S (1.6mm)
43
Minimum thickness of continuous waste and fixture tailpiece made of seamless drawn brass.GA 20 B&S (0.8mm)
44
Least dimension of access panel or utility for fixtures with concealed slip joint connections, provided for inspection and repair.0.30m
45
Minimum diameter of tailpiece, continuous waste or waste and overflow for sinks, dishwaters, laundry tubs, bathtubs, urinals and similar fixtures.1 1/2" or 38mm O.D.
46
Minimum diameter of tailpiece, continuous waste or waste and overflow for lavatories, drinking fountains, and similar small fixtures.1 1/4" or 32mm O.D.
47
Distance of water closet or bidet from its center to any side wall.0.375m
48
Distance of water closet or bidet center to center0.75m
49
Distance of urinal from its center to any side wall0.30m
50
Distance of urinal center to center0.60m
51
Minimum depth of finished shower dam, curb or threshold from the outside door.25.4mm
52
Min depth of shower dam or threshold measure from the top of the dam or threshold to the top of the drain51mm to 228mm
53
Slope of a finished floor of a shower receptor2% to 4%
54
Minimum width of a shower door a threshold should accommodate559mm (22")
55
Minimum distance between the door or entry to the drain opening1.2m
56
Minimum finished interior area of a shower compartment0.6sqm
57
Minimum diameter of a circle capable of encompassing a shower compartment762mm
58
Minimum area and dimensions of a shower compartment shall be maintained from a point above the shower drain outlet to a height of ________.1.78m
59
For shower receptors built above the ground, at least ______ above the top of the finished dam or threshold shall be first lined with sheet lead or copper or with other durable and watertight materials76mm
60
Minimum extension of all lining materials upward on the rough jambs of the shower opening above the top of the finished dam or threshold.76mm
61
Standard grade of asphalt-impregnated roofing felt for metaling shower sub-pans or linings.6.8kg
62
Extension of folds, laps and reinforcing webbing for shower lining or sub-pans in all directions from the corner of the webbing.101mm
63
Minimum tensile strength of mesh/webbing for lining or sub-pan0.9kg/mm
64
Linings above the finished dam or threshold shall not be nailed or perforated25.4mm
65
Minimum weight of lead pans or liners19.6kg/m2
66
Minimum thickness of copper pans or linersGA 24 B&S (0.5mm)
67
Slope of gutters in public or gang shower rooms2%
68
Maximum spacing of gutter drains in public or gang shower rooms4.9m
69
Maximum temperature of limit stops for the delivery of hot water (human consumption)48.88°C
70
Width of wash sink, when provided with water outlets, shall be considered equivalent to 1 lavatory608.6mm (24")
71
Diameter of circular basin, when provided with water outlets, shall be considered equal to 1 lavatory457.2mm (18")
72
Ratio of lavatory to number of persons in occupancy where there is exposure to skin contamination with poisonous, infectious, or irritating materials1:5
73
Ratio of laundry tray to number of persons1:50
74
Ratio of slope sink tray to number of persons1:100
75
Ratio of water closet and urinal to number of persons for temporary workingmen1:30
76
Distance on each side of the urinal to be lined with non-absorbent materials0.6m
77
Height above the floor of the urinal to be lined with non-absorbent materials1.2m
78
Ratio of drinking fountain to number of persons in public buildings1:75
79
On top of first 75 persons, provide 1 additional drinking fountain for each _____ persons thereafter150
80
Notice to Administrative Authority that the work is ready for inspection3 days
81
Head of water to be filled on each section of piping under water test3m
82
Duration that water shall be kept before start of inspection15min
83
Gauge pressure for air test, equivalent to 254mm Mercury in height34.5kPa
84
Duration that air pressure shall be held during air test without introduction of additional air15min
85
Water piping shall be tested under a water pressure not less than the working pressure under which is to be used plus ____50%
86
Air pressure which may be substituted for the water test344.5kPa