Question
Polymer-based chemical soil additive shall be less than ___ by weight of soil
Question
The unsoaked CBR value of treated soil material with Olymer-based chemical soil additive shall be ________ the unsoaked CBR value of untreated same soil material
Question
Existing road subbase/base materials shall be scarified by use of grader to a depth of _____ to _____ and shall be stockpiled on both sides of the road.
Question
If further needed, polymer-based chemical soil additive shall be applied on the subbase/base after it was exposed for ____, provided that after applying the said chemical additive, the first layer of road subbase/base materials which is thoroughly mixed shall be spread immediately.
Question
The dilution rate for the subbase/base shall be ___ part of polymer-based chemical soil additive and ___ parts of water depending on type of soil and application method
Question
After the preparation of subbase/base material, it shall be mixed thoroughly and spread by a grader in approximately ___ equal layers.
Question
Rate of dilution in each layer
Question
Steel roller shall be used to crush aggregates larger than ____ on the surface of the laid/treated subbase/base course while rubber roller shall follow to smoothen the surface.
Question
After _____ of curing, polymer-based chemical soil additive shall be sprayed on the compacted road subbase/base with required dilution in each layer.
Question
Trial sections of the stabilized subbase/base shall be constructed by the contractor at least ____ before the actual subbase/base construction
Item 206 Chemically Stabilized Road Mix Subbase/Base Course
Score
0 / 10
Correct rate
0%
Correct: 0
Incorrect: 0
Unanswered: 10
Question list
1
Polymer-based chemical soil additive shall be less than ___ by weight of soil2%
2
The unsoaked CBR value of treated soil material with Olymer-based chemical soil additive shall be ________ the unsoaked CBR value of untreated same soil materialgreater than
3
Existing road subbase/base materials shall be scarified by use of grader to a depth of _____ to _____ and shall be stockpiled on both sides of the road.150mm, 200mm
4
If further needed, polymer-based chemical soil additive shall be applied on the subbase/base after it was exposed for ____, provided that after applying the said chemical additive, the first layer of road subbase/base materials which is thoroughly mixed shall be spread immediately.24hrs
5
The dilution rate for the subbase/base shall be ___ part of polymer-based chemical soil additive and ___ parts of water depending on type of soil and application method1, 5-9
6
After the preparation of subbase/base material, it shall be mixed thoroughly and spread by a grader in approximately ___ equal layers.2
7
Rate of dilution in each layer1:5 to 1:9
8
Steel roller shall be used to crush aggregates larger than ____ on the surface of the laid/treated subbase/base course while rubber roller shall follow to smoothen the surface.1/2" or 13mm
9
After _____ of curing, polymer-based chemical soil additive shall be sprayed on the compacted road subbase/base with required dilution in each layer.48hrs
10
Trial sections of the stabilized subbase/base shall be constructed by the contractor at least ____ before the actual subbase/base construction2 weeks
11
Polymer-based chemical soil additive shall be measured by:liter