Question
For pre-tensioning work-samples, at least a ____ long shall be furnished of each size of wire or strand proposed
Question
For post-tensioning work-samples, a ____ long shall be furnished for wire requiring heading
Question
For wires not requiring heading, sufficient length to make up one parallel-lay cable of ____ long consisting of the same number of wires as the cable to be furnished
Question
For strand to be furnished with fittings, _____ long shall be between near ends of fittings
Question
If anchorage assemblies are not attached to reinforcement samples, _____ anchorage assemblies shall be furnished, completed with distribution plates of each size and type to be used
Question
The pressure gauge, if used, shall have an accurate reading dial at least _____ in diameter
Question
The range of the load cell shall be such that the lower ____ of the manufacturer's rated capacity will not be used in determining the jacking stress
Question
Vents shall be _____ minimum diameter standard pipe
Question
Ends of vents shall be removed _____ below the roadway surface after grouting has been completed
Question
When acceptable prestressing steel for post-tensioning is installed in ducts after completion of concrete curing, and if stressing and grouting are completed within ___ calendar days after the installation of the prestressing steel
Item 406 Prestressed Concrete Structures
Score
0 / 10
Correct rate
0%
Correct: 0
Incorrect: 0
Unanswered: 10
Question list
1
For pre-tensioning work-samples, at least a ____ long shall be furnished of each size of wire or strand proposed2m
2
For post-tensioning work-samples, a ____ long shall be furnished for wire requiring heading2m
3
For wires not requiring heading, sufficient length to make up one parallel-lay cable of ____ long consisting of the same number of wires as the cable to be furnished1.5m
4
For strand to be furnished with fittings, _____ long shall be between near ends of fittings1.5m
5
If anchorage assemblies are not attached to reinforcement samples, _____ anchorage assemblies shall be furnished, completed with distribution plates of each size and type to be used2
6
The pressure gauge, if used, shall have an accurate reading dial at least _____ in diameter154mm
7
The range of the load cell shall be such that the lower ____ of the manufacturer's rated capacity will not be used in determining the jacking stress10%
8
Vents shall be _____ minimum diameter standard pipe12.7mm
9
Ends of vents shall be removed _____ below the roadway surface after grouting has been completed25.4mm
10
When acceptable prestressing steel for post-tensioning is installed in ducts after completion of concrete curing, and if stressing and grouting are completed within ___ calendar days after the installation of the prestressing steel10
11
Prestressing steel, installed, tensioned and grouted in this manner, all within ___ calendar days shall be subject to all the requirements in this Item pertaining to corrosion protection and rejection because of rust10
12
No bond stress shall be transferred to the concrete, nor end anchorages released until the concrete has attained a compressive strength, as shown by cylinder tests, of at least _____ unless otherwise specified28 MPa
13
_______ after placing concrete and after the concrete has undergone initial set, the first application of steam or radiant heat shall be made unless retarders are used2-4 hours
14
The waiting period before application of steam or radiant heat shall be increased to between ________4-6 hours
15
During the waiting period, the temperature within the curing chamber shall not be less than _____ and live steam or radiant heat may be used to maintain the curing chamber at the proper minimum temperature10°C
16
The steam shall be at ____ relative humidity to prevent loss of moisture and to provide moisture for proper hydration of the cement100%
17
During application of the steam, or of radiant heat, the ambient air temperature shall increase at a rate not to exceed _____ per hour until the curing temperature is reached4.41°C
18
The maximum curing temperature within the enclosure shall not exceed _____71.1°C
19
Tensioning of the prestressing reinforcement shall not be commenced until tests on concrete cylinders, manufactured of the same concrete and cured under the same conditions, indicate that the concrete of the particular member to be prestressed has attained compressive strength of at least ______ unless otherwise specified28 MPa
20
Cast-in-place concrete shall not be post-tensioned until at least _____ after the last concrete has been placed in the member to be post-tensioned and until the compressive strength of said placed concrete has reached the strength specified for the concrete at the time of stressing10 days
21
The falsework under the bottom slab supporting the superstructure shall not be released until a minimum of _____ have elapsed after grouting of the post-tension tendons nor until all other conditions of the Specifications have been met48 hours
22
The water content shall be not more than _____ per sack of cement19L
23
Grouting equipment shall be capable of grouting at a pressure of at least _______0.6894 MPa
24
Grouting equipment shall be furnished with a pressure gauge having a full-scale reading of not more than _______2.07 MPa
25
Standby flushing equipment capable of developing a pumping pressure of ______ and of sufficient capacity to flush out any partially grouted ducts shall be provided1.72 MPa
26
All grout shall pass through a screen with a ______ maximum clear opening prior to being introduced into the grout pump2mm
27
Approximately _______ after the concrete pour, the metal conduits shall be flushed out with water and then blown out with compressed oil free air24 hours
28
Grout shall be pumped through the duct and continuously wasted at the outlet until no visible slugs of water or air are ejected and the efflux time of ejected grout is not less than _______11 seconds
29
After all vents and openings shall then be closed and the grouting pressure at the injection end shall be raised to a minimum of _______ and held for a minimum of ______0.6894 MPa, 10 seconds
30
From 2 to 4 grams of the unpolished variety, about __________ of each sack of cement used in the grout1 to 2 teaspoons
31
The aluminum powder shall be blended with pumicite or other inert powder in the proportion of _____ powder to _______ pumicite (or other inert powder) by weight1 part, 50 parts
32
After all ingredients are added, the batch shall be mixed for ________3 minutes
33
Batches of grout shall be placed within _______ after mixing45 minutes
34
Prestressed concrete girders shall not be shipped until indicate that the concrete of the particular girder has attained a compressive strength equal to the specified design compressive strength of the concrete in the girder and has attained a minimum age of ______14 days
35
The width of the deci soffit shall be within _____± 25mm
36
The width of gap between individual beams shall not exceed ______ the nominal gaptwice