Question
Amount of cement to be added
Question
For Soil Aggregates For every ____ or fraction thereof - 1 Grading Test - 1 Plasticity Test (LL, PL, PI) For every ____ or fraction thereof - 1 Quality Test (Grading, Plasticity, and Abrasion)
Question
For Portland Cement For every _____ bags or fraction thereof - 1 Quality test
Question
For the mix For every ___ or fraction thereof - 1 Laboratory Compaction Test - 1 Unconfined Compaction Test
Question
Quality Test on water requires:
Question
For compacted base course For every layer of ____ compacted depth of base course requires - FDT for every ____ or fraction thereof - Thickness Determination for every ____ or fraction thereof
Question
The salvaged or new soil aggregate shall be pulverized until at least ____ of all material other than stone or gravel will pass No. 4 sieve (4.75mm)
Question
Any material retained on a ____ sieve and other suitable material shall be removed.
Question
In mixing, a maximum time of _____ shall be permitted for wet mixing, laydown, and finishing
Question
Not more than _____ shall elapse betwedn the start of mixing and the time of starting compaction of the spread structure
Item 207 Portland Cement Stabilized Treated Plant Mix Base Course
Score
0 / 10
Correct rate
0%
Correct: 0
Incorrect: 0
Unanswered: 10
Question list
1
Amount of cement to be added6-10% mass of dry soil aggregate
2
For Soil Aggregates For every ____ or fraction thereof - 1 Grading Test - 1 Plasticity Test (LL, PL, PI) For every ____ or fraction thereof - 1 Quality Test (Grading, Plasticity, and Abrasion)300cu.m, 1500cu.m
3
For Portland Cement For every _____ bags or fraction thereof - 1 Quality test2000
4
For the mix For every ___ or fraction thereof - 1 Laboratory Compaction Test - 1 Unconfined Compaction Test300cu.m
5
Quality Test on water requires:Project Engineer's Certificate
6
For compacted base course For every layer of ____ compacted depth of base course requires - FDT for every ____ or fraction thereof - Thickness Determination for every ____ or fraction thereof150mm, 150m, 150m
7
The salvaged or new soil aggregate shall be pulverized until at least ____ of all material other than stone or gravel will pass No. 4 sieve (4.75mm)80%
8
Any material retained on a ____ sieve and other suitable material shall be removed.50mm
9
In mixing, a maximum time of _____ shall be permitted for wet mixing, laydown, and finishing2 hrs
10
Not more than _____ shall elapse betwedn the start of mixing and the time of starting compaction of the spread structure60 minutes
11
The compaction and finishing shall be completed within _____ of the time water is added to the mixture2 hrs
12
The rate of application of curing seal shall be between ________ of surface0.5 to 1 L/sq.m
13
Applied in sufficient quantity to provide a continuous film over the base.curing seal