Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

13 questions • 2026-01-10
Anonymous
Report

Question

Amount of cement to be added

  • 3-12% mass of dry soil aggregate

  • 4-7% mass of dry soil aggregate

  • 6-10% mass of dry soil aggregate

  • Skip

Question

For Soil Aggregates For every ____ or fraction thereof - 1 Grading Test - 1 Plasticity Test (LL, PL, PI) For every ____ or fraction thereof - 1 Quality Test (Grading, Plasticity, and Abrasion)

Answer

Question

For Portland Cement For every _____ bags or fraction thereof - 1 Quality test

Answer

Question

For the mix For every ___ or fraction thereof - 1 Laboratory Compaction Test - 1 Unconfined Compaction Test

Answer

Question

Quality Test on water requires:

  • Materials Engineer's Certificate

  • Project Engineer's Certificate

  • Skip

Question

For compacted base course For every layer of ____ compacted depth of base course requires - FDT for every ____ or fraction thereof - Thickness Determination for every ____ or fraction thereof

Answer

Question

The salvaged or new soil aggregate shall be pulverized until at least ____ of all material other than stone or gravel will pass No. 4 sieve (4.75mm)

  • 50%

  • 80%

  • Skip

Question

Any material retained on a ____ sieve and other suitable material shall be removed.

  • 25mm

  • 50mm

  • Skip

Question

In mixing, a maximum time of _____ shall be permitted for wet mixing, laydown, and finishing

  • 2 hrs

  • 60 minutes

  • Skip

Question

Not more than _____ shall elapse betwedn the start of mixing and the time of starting compaction of the spread structure

  • 2 hrs

  • 60 minutes

  • Skip

Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

TestMaker

Score

0 / 10

Correct rate

0%

Correct: 0

Incorrect: 0

Unanswered: 10

 
ankimaker.com

Question list

  • 1

    Amount of cement to be added

    6-10% mass of dry soil aggregate

  • 2

    For Soil Aggregates For every ____ or fraction thereof - 1 Grading Test - 1 Plasticity Test (LL, PL, PI) For every ____ or fraction thereof - 1 Quality Test (Grading, Plasticity, and Abrasion)

    300cu.m, 1500cu.m

  • 3

    For Portland Cement For every _____ bags or fraction thereof - 1 Quality test

    2000

  • 4

    For the mix For every ___ or fraction thereof - 1 Laboratory Compaction Test - 1 Unconfined Compaction Test

    300cu.m

  • 5

    Quality Test on water requires:

    Project Engineer's Certificate

  • 6

    For compacted base course For every layer of ____ compacted depth of base course requires - FDT for every ____ or fraction thereof - Thickness Determination for every ____ or fraction thereof

    150mm, 150m, 150m

  • 7

    The salvaged or new soil aggregate shall be pulverized until at least ____ of all material other than stone or gravel will pass No. 4 sieve (4.75mm)

    80%

  • 8

    Any material retained on a ____ sieve and other suitable material shall be removed.

    50mm

  • 9

    In mixing, a maximum time of _____ shall be permitted for wet mixing, laydown, and finishing

    2 hrs

  • 10

    Not more than _____ shall elapse betwedn the start of mixing and the time of starting compaction of the spread structure

    60 minutes

  • 11

    The compaction and finishing shall be completed within _____ of the time water is added to the mixture

    2 hrs

  • 12

    The rate of application of curing seal shall be between ________ of surface

    0.5 to 1 L/sq.m

  • 13

    Applied in sufficient quantity to provide a continuous film over the base.

    curing seal