  • 1

    Camber in gravel roads is provided to:

    Prevent water from stagnating on carriageway

  • 2

    Whose engineering judgment will prevail in overall field implementation of a project?

    Project Engineer

  • 3

    What is the single vertical datum to which elevation for all infrastructure projects should be referred to?

    Mean Sea Level

  • 4

    When a contract is mutually terminated, the contractor is:

    Allowed to submit bids

  • 5

    The most common hourly volume count used for roadway design is:

    30th Highest Hourly Volume

  • 6

    For testing reinforcing steel bars, the sample for every 10 tons should be:

    1.0m long

  • 7

    The depth of weakened plane joints should not be less than:

    50mm

  • 8

    Unless otherwise specified, all materials below subgrade level in earth should be cut to a depth of:

    150mm

  • 9

    Defective works in a project should be brought to the attention of the contractor by the resident engineer thru:

    Site Instruction

  • 10

    Which of the following is not a field test in road construction?

    California Bearing Ratio (CBR) test

  • 11

    Normally within how many hours can sawing joints commence given that concrete has hardened sufficiently?

    24

  • 12

    What is the required area of the trial section needed to check the suitability of the materials and efficiency of the equipment and the construction method the contractor will use?

    About 500 sqm

  • 13

    The inside face of a pothole, aside from squaring, must be made vertical before patching using cold or hot mix asphalt in order to:

    ensure bond between new mix and old surface

  • 14

    As practical as possible, concrete mix should not be placed where this can be subject to manual dropping by not more than _______ and whre no other special tools and means are used.

    1.5m

  • 15

    Cores taken from a concrete pavement are tested for:

    strength verification of concrete in-place that is considered adequate

  • 16

    Excavation of indurated rocks can be undertaken by:

    Ripper

  • 17

    The minimum flexural strength requirement of concrete for Item 311 (Portland Cement Concrete Pavement) is:

    550psi

  • 18

    The minimum testing requirement of concrete for Item 405 is the compressive strength test on concrete cylinder samples consisting of a set of 3 concrete cylinder samples to represent not more than:

    75cu.m.

  • 19

    In laying stone components of Item 505 (Riprap and Grouted Riprap), each stone should be:

    Laid with its longest axis perpendicular to the slope

  • 20

    What is the required minimum field density for embankment materials?

    95%

  • 21

    Who supervises the work and tests employed in project implementation?

    Project Engineer

  • 22

    Which of the following is not considered a Variation Order?

    Resume Order

  • 23

    On sloping surface, concrete should be places starting at:

    bottom of slope

  • 24

    Resurfacing of unpaved shoulder that was settled or been eroded by traffic and water is an activity under:

    periodic maintainance

  • 25

    The primary quality control mechanism for the production of asphalt mixtures which will have a high degree of uniformity that will satisfy job requirements is called:

    Job-Mix Formula

  • 26

    When considating concrete during pouring operations, vibrator should not be be operated in any one location longer than:

    15 seconds

  • 27

    Which of the following financial controls should be imposed of the project is delayed?

    Liquidated damages

  • 28

    What is the allowable minimum thickness of bedding material beneath a concrete pipe?

    100mm

  • 29

    The best aid in locating and identifying areas of discussion in an inspection report are:

    Photographs

  • 30

    The process of maintaining sufficient moisture and favorable temperature in concrete is called:

    curing

  • 31

    The rate of application of emulsified asphalt used as tack coat, should be within the range of:

    0.2 - 0.7 L/m2

  • 32

    The system of protecting land area from ocean waves is called:

    coastal protection works

  • 33

    In no case, however, shall the total sum of liquidated damage exceed of ____ of the contract price, in which event the contract shall automatically be taken over by the procuring entity concerned or can be awarded to same qualified contractor through negotiated contract.

    10%

  • 34

    Which of the following is not an agent for repairing concrete cracks?

    Sulfur Injection

  • 35

    What type of cement is allowed by the DPWH as a substitute in the absence of Portland Cement Type I?

    Portland Pozzolan Type IP

  • 36

    What kind of joint is established by an interrupted or delayed placing of concrete on partially placed concrete wherin initial setting had already taken place?

    Cold joint

  • 37

    During pouring operations of concrete pavements, what kind of samples should be taken for testing

    Beam samples

  • 38

    Who has the authority to reject questionable materials or suspend the work until it is referred and decided upon by the Project Engineer?

    Materials Engineer

  • 39

    Who assist the Project Engineer in the overall direction and supervision of field operations?

    Project Inspector

  • 40

    What do you call the strengthening of an old existing asphalt or concrete pavement by providing additional adequate thickness over it?

    overlaying

  • 41

    What do you call a record or book compiled to contain data information and history in the implementation of a project from start to completion?

    Logbook

  • 42

    Measurement of concrete materials for concrete structures shall be by:

    volume

  • 43

    Before an asphalt pavement or asphalt surface treatment is placed on a granular base, what liquid asphalt is applied?

    Prime Coat

  • 44

    What is allowable minimum penetration of piles in firm material

    3.0m

  • 45

    If designed thickness of aggregate subbase course is 200mm, in how many layers may the material be spread and compacted?

    1

  • 46

    To check the suitablility of the materials and the efficiency of the equipment and construction method in the construction of embankments and base course, trial sections should be spread and compacted, and corresponding field density test should be undertaken. Said trial section shall be about:

    500 sqm

  • 47

    In field project monitoring using old, approved plans of a river system, which of the following would immediately identify the sheets if pages were already erased?

    Stationings and Matching Lines

  • 48

    For Item 311 (Portland Cement Concrete Pavement) the minimum cement factor in bags of cement per cubic meter of concrete based on a 40kg per bag of cement is:

    9.1

  • 49

    How many years for periodic maintainance for Asphalt Pavement?

    5

  • 50

    It is the graphical representation of monthly cash flow, monitoring of equipment and manpower.

    S Curve

  • 51

    When concrete pilenare lifted oroved, they should be supported at what point?

    Quarter point

  • 52

    For buildings, what is the maximum number of bore hole fornevery 200sq.m. of structure?

    1

  • 53

    In no case, shall the total liquidated damages exceed ____ of the contract price, in which event the contract shall be automatically taken over by the procuring entity concerned or can be awarded to same qualified contractor through negotiated contract?

    10%

  • 54

    For a 2-lane bridge 7.3m in width, what is the minimum no. of girder required?

    4 (urban and rural)

  • 55

    Advance payment of the contractor is an amount not to exceed ___ of the total original contract amount.

    15%

  • 56

    At least 1 set consisting of ___ concrete beam test specimens shall be taken from each 330sq.m. of pavement, 0.23cm thick or fraction thereof placed each day.

    3

  • 57

    Persuant to the RA 9184, what is the applicable rate of liquidated damages?

    1/10 of 1 percent

  • 58

    What do you call the method of determining stream discharge by measuring the cross sectional area of the stream and its velocity with a current meter?

    Velocity Area Method

  • 59

    What is the most used pile driver in the country?

    Diesel Hammer

  • 60

    Initial rolling in bituminous mixes shall be performed with a ____ roller?

    Pneumatic Tire Roller

  • 61

    What is the Project Scheduling technique in DPWH Project?

    PDM (Precedence Diagram Method)

  • 62

    Process of rolling/compaction of bituminous pavement?

    It should begin from the sides and proceed longitudinally parallel toward the road center line, each trip overlapping one half of the roller's width.

  • YT1 Materials Engineer EXAM

    YT1 Materials Engineer EXAM

    Anonymous · 100 questions · 2 mo ago

    YT1 Materials Engineer EXAM

    YT1 Materials Engineer EXAM

    100 questions • 2 mo ago
    Anonymous

    YT2 Materials Engineer EXAM

    YT2 Materials Engineer EXAM

    Anonymous · 100 questions · 2 mo ago

    YT2 Materials Engineer EXAM

    YT2 Materials Engineer EXAM

    100 questions • 2 mo ago
    Anonymous

    Project Engineer YT 1

    Project Engineer YT 1

    Anonymous · 100 questions · 2 mo ago

    Project Engineer YT 1

    Project Engineer YT 1

    100 questions • 2 mo ago
    Anonymous

    Project Engineer EXAM 68

    Project Engineer EXAM 68

    Anonymous · 100 questions · 2 mo ago

    Project Engineer EXAM 68

    Project Engineer EXAM 68

    100 questions • 2 mo ago
    Anonymous

    Project Engineer EXAM 82

    Project Engineer EXAM 82

    Anonymous · 100 questions · 2 mo ago

    Project Engineer EXAM 82

    Project Engineer EXAM 82

    100 questions • 2 mo ago
    Anonymous

    July 2023 PE Refresher

    July 2023 PE Refresher

    Anonymous · 70 questions · 2 mo ago

    July 2023 PE Refresher

    July 2023 PE Refresher

    70 questions • 2 mo ago
    Anonymous

    August 2019 Special PE Exam

    August 2019 Special PE Exam

    Anonymous · 93 questions · 2 mo ago

    August 2019 Special PE Exam

    August 2019 Special PE Exam

    93 questions • 2 mo ago
    Anonymous

    RNPCP Chapter 1 to 5

    RNPCP Chapter 1 to 5

    Anonymous · 86 questions · 2 mo ago

    RNPCP Chapter 1 to 5

    RNPCP Chapter 1 to 5

    86 questions • 2 mo ago
    Anonymous

    Plumbing Code 4

    Plumbing Code 4

    Anonymous · 100 questions · 2 mo ago

    Plumbing Code 4

    Plumbing Code 4

    100 questions • 2 mo ago
    Anonymous

    Plumbing Code 5

    Plumbing Code 5

    Anonymous · 100 questions · 2 mo ago

    Plumbing Code 5

    Plumbing Code 5

    100 questions • 2 mo ago
    Anonymous

    Plumbing Code 6

    Plumbing Code 6

    Anonymous · 100 questions · 2 mo ago

    Plumbing Code 6

    Plumbing Code 6

    100 questions • 2 mo ago
    Anonymous

    Plumbing Code 7

    Plumbing Code 7

    Anonymous · 100 questions · 2 mo ago

    Plumbing Code 7

    Plumbing Code 7

    100 questions • 2 mo ago
    Anonymous

    Plumbing Code 8

    Plumbing Code 8

    Anonymous · 100 questions · 2 mo ago

    Plumbing Code 8

    Plumbing Code 8

    100 questions • 2 mo ago
    Anonymous

    Plumbing Code 3

    Plumbing Code 3

    Anonymous · 100 questions · 2 mo ago

    Plumbing Code 3

    Plumbing Code 3

    100 questions • 2 mo ago
    Anonymous

    Sanitation, Plumbing Design, and Installation 2

    Sanitation, Plumbing Design, and Installation 2

    Anonymous · 97 questions · 2 mo ago

    Sanitation, Plumbing Design, and Installation 2

    Sanitation, Plumbing Design, and Installation 2

    97 questions • 2 mo ago
    Anonymous

    Sanitation, Plumbing Design, and Installation 1

    Sanitation, Plumbing Design, and Installation 1

    Anonymous · 99 questions · 2 mo ago

    Sanitation, Plumbing Design, and Installation 1

    Sanitation, Plumbing Design, and Installation 1

    99 questions • 2 mo ago
    Anonymous

    Sanitation, Plumbing Design, and Installation 3

    Sanitation, Plumbing Design, and Installation 3

    Anonymous · 96 questions · 2 mo ago

    Sanitation, Plumbing Design, and Installation 3

    Sanitation, Plumbing Design, and Installation 3

    96 questions • 2 mo ago
    Anonymous

    Sanitation, Plumbing Design, and Installation 4

    Sanitation, Plumbing Design, and Installation 4

    Anonymous · 95 questions · 2 mo ago

    Sanitation, Plumbing Design, and Installation 4

    Sanitation, Plumbing Design, and Installation 4

    95 questions • 2 mo ago
    Anonymous

    Sanitation, Plumbing Design, and Installation 5

    Sanitation, Plumbing Design, and Installation 5

    Anonymous · 97 questions · 2 mo ago

    Sanitation, Plumbing Design, and Installation 5

    Sanitation, Plumbing Design, and Installation 5

    97 questions • 2 mo ago
    Anonymous

    Sanitation, Plumbing Design, and Installation 7

    Sanitation, Plumbing Design, and Installation 7

    Anonymous · 100 questions · 2 mo ago

    Sanitation, Plumbing Design, and Installation 7

    Sanitation, Plumbing Design, and Installation 7

    100 questions • 2 mo ago
    Anonymous

    Sanitation, Plumbing Design, and Installation 8

    Sanitation, Plumbing Design, and Installation 8

    Anonymous · 98 questions · 2 mo ago

    Sanitation, Plumbing Design, and Installation 8

    Sanitation, Plumbing Design, and Installation 8

    98 questions • 2 mo ago
    Anonymous

    Plumbing Tools 1

    Plumbing Tools 1

    Anonymous · 87 questions · 2 mo ago

    Plumbing Tools 1

    Plumbing Tools 1

    87 questions • 2 mo ago
    Anonymous

    Plumbing Tools 2

    Plumbing Tools 2

    Anonymous · 53 questions · 2 mo ago

    Plumbing Tools 2

    Plumbing Tools 2

    53 questions • 2 mo ago
    Anonymous

    Practical Problems and Experiences 1

    Practical Problems and Experiences 1

    Anonymous · 100 questions · 2 mo ago

    Practical Problems and Experiences 1

    Practical Problems and Experiences 1

    100 questions • 2 mo ago
    Anonymous

    Practical Problems and Experiences 2

    Practical Problems and Experiences 2

    Anonymous · 100 questions · 2 mo ago

    Practical Problems and Experiences 2

    Practical Problems and Experiences 2

    100 questions • 2 mo ago
    Anonymous

    Practical Problems and Experiences 3

    Practical Problems and Experiences 3

    Anonymous · 99 questions · 2 mo ago

    Practical Problems and Experiences 3

    Practical Problems and Experiences 3

    99 questions • 2 mo ago
    Anonymous

    Practical Problems and Experiences 4

    Practical Problems and Experiences 4

    Anonymous · 100 questions · 2 mo ago

    Practical Problems and Experiences 4

    Practical Problems and Experiences 4

    100 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic Terms 1

    Plumbing Arithmetic Terms 1

    Anonymous · 49 questions · 2 mo ago

    Plumbing Arithmetic Terms 1

    Plumbing Arithmetic Terms 1

    49 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic Terms 2

    Plumbing Arithmetic Terms 2

    Anonymous · 47 questions · 2 mo ago

    Plumbing Arithmetic Terms 2

    Plumbing Arithmetic Terms 2

    47 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic Terms 3

    Plumbing Arithmetic Terms 3

    Anonymous · 49 questions · 2 mo ago

    Plumbing Arithmetic Terms 3

    Plumbing Arithmetic Terms 3

    49 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic Terms 4

    Plumbing Arithmetic Terms 4

    Anonymous · 27 questions · 2 mo ago

    Plumbing Arithmetic Terms 4

    Plumbing Arithmetic Terms 4

    27 questions • 2 mo ago
    Anonymous

    Plumbing Code WSFU

    Plumbing Code WSFU

    Anonymous · 58 questions · 2 mo ago

    Plumbing Code WSFU

    Plumbing Code WSFU

    58 questions • 2 mo ago
    Anonymous

    Practical Problems and Experiences REFRESHER 1

    Practical Problems and Experiences REFRESHER 1

    Anonymous · 100 questions · 2 mo ago

    Practical Problems and Experiences REFRESHER 1

    Practical Problems and Experiences REFRESHER 1

    100 questions • 2 mo ago
    Anonymous

    Practical Problems and Experiences REFRESHER 2

    Practical Problems and Experiences REFRESHER 2

    Anonymous · 70 questions · 2 mo ago

    Practical Problems and Experiences REFRESHER 2

    Practical Problems and Experiences REFRESHER 2

    70 questions • 2 mo ago
    Anonymous

    Item # and Descriptions

    Item # and Descriptions

    Anonymous · 24 questions · 2 mo ago

    Item # and Descriptions

    Item # and Descriptions

    24 questions • 2 mo ago
    Anonymous

    Item 200 Aggregate Subbase Course

    Item 200 Aggregate Subbase Course

    Anonymous · 16 questions · 2 mo ago

    Item 200 Aggregate Subbase Course

    Item 200 Aggregate Subbase Course

    16 questions • 2 mo ago
    Anonymous

    Item 201 Aggregate Base Course

    Item 201 Aggregate Base Course

    Anonymous · 16 questions · 2 mo ago

    Item 201 Aggregate Base Course

    Item 201 Aggregate Base Course

    16 questions • 2 mo ago
    Anonymous

    Item 202 Crushed Aggregate Base Course

    Item 202 Crushed Aggregate Base Course

    Anonymous · 18 questions · 2 mo ago

    Item 202 Crushed Aggregate Base Course

    Item 202 Crushed Aggregate Base Course

    18 questions • 2 mo ago
    Anonymous

    Item 203 Lime Stabilized Road Mix Base Course

    Item 203 Lime Stabilized Road Mix Base Course

    Anonymous · 27 questions · 2 mo ago

    Item 203 Lime Stabilized Road Mix Base Course

    Item 203 Lime Stabilized Road Mix Base Course

    27 questions • 2 mo ago
    Anonymous

    Item 204 Portland Cement Stabilized Road Mix Base Course

    Item 204 Portland Cement Stabilized Road Mix Base Course

    Anonymous · 7 questions · 2 mo ago

    Item 204 Portland Cement Stabilized Road Mix Base Course

    Item 204 Portland Cement Stabilized Road Mix Base Course

    7 questions • 2 mo ago
    Anonymous

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    Anonymous · 13 questions · 2 mo ago

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    13 questions • 2 mo ago
    Anonymous

    Item 205 Asphalt Stabilized Road Mix Base Course

    Item 205 Asphalt Stabilized Road Mix Base Course

    Anonymous · 7 questions · 2 mo ago

    Item 205 Asphalt Stabilized Road Mix Base Course

    Item 205 Asphalt Stabilized Road Mix Base Course

    7 questions • 2 mo ago
    Anonymous

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    Anonymous · 11 questions · 2 mo ago

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    11 questions • 2 mo ago
    Anonymous

    Item 300 Aggregate Surface Course

    Item 300 Aggregate Surface Course

    Anonymous · 11 questions · 2 mo ago

    Item 300 Aggregate Surface Course

    Item 300 Aggregate Surface Course

    11 questions • 2 mo ago
    Anonymous

    Item 301 Bituminous Prime Coat

    Item 301 Bituminous Prime Coat

    Anonymous · 10 questions · 2 mo ago

    Item 301 Bituminous Prime Coat

    Item 301 Bituminous Prime Coat

    10 questions • 2 mo ago
    Anonymous

    Item 303 Bituminous Seal Coat

    Item 303 Bituminous Seal Coat

    Anonymous · 20 questions · 2 mo ago

    Item 303 Bituminous Seal Coat

    Item 303 Bituminous Seal Coat

    20 questions • 2 mo ago
    Anonymous

    RNPCP Chapter 6 to 9

    RNPCP Chapter 6 to 9

    Anonymous · 94 questions · 2 mo ago

    RNPCP Chapter 6 to 9

    RNPCP Chapter 6 to 9

    94 questions • 2 mo ago
    Anonymous

    RNPCP Chapter 10 to 13

    RNPCP Chapter 10 to 13

    Anonymous · 93 questions · 2 mo ago

    RNPCP Chapter 10 to 13

    RNPCP Chapter 10 to 13

    93 questions • 2 mo ago
    Anonymous

    RNPCP Appendix A and B

    RNPCP Appendix A and B

    Anonymous · 79 questions · 2 mo ago

    RNPCP Appendix A and B

    RNPCP Appendix A and B

    79 questions • 2 mo ago
    Anonymous

    Republic Acts

    Republic Acts

    Anonymous · 9 questions · 2 mo ago

    Republic Acts

    Republic Acts

    9 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic Terms 5

    Plumbing Arithmetic Terms 5

    Anonymous · 68 questions · 2 mo ago

    Plumbing Arithmetic Terms 5

    Plumbing Arithmetic Terms 5

    68 questions • 2 mo ago
    Anonymous

    Principles and Code of Ethics

    Principles and Code of Ethics

    Anonymous · 29 questions · 2 mo ago

    Principles and Code of Ethics

    Principles and Code of Ethics

    29 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic Problems 1

    Plumbing Arithmetic Problems 1

    Anonymous · 75 questions · 2 mo ago

    Plumbing Arithmetic Problems 1

    Plumbing Arithmetic Problems 1

    75 questions • 2 mo ago
    Anonymous

    Item 406 Prestressed Concrete Structures

    Item 406 Prestressed Concrete Structures

    Anonymous · 36 questions · 2 mo ago

    Item 406 Prestressed Concrete Structures

    Item 406 Prestressed Concrete Structures

    36 questions • 2 mo ago
    Anonymous

    Item 405 Structural Concrete

    Item 405 Structural Concrete

    Anonymous · 41 questions · 2 mo ago

    Item 405 Structural Concrete

    Item 405 Structural Concrete

    41 questions • 2 mo ago
    Anonymous

    Item 400 Piling

    Item 400 Piling

    Anonymous · 80 questions · 2 mo ago

    Item 400 Piling

    Item 400 Piling

    80 questions • 2 mo ago
    Anonymous

    Item 311 Portland Cement Concrete Pavement (PART 2)

    Item 311 Portland Cement Concrete Pavement (PART 2)

    Anonymous · 61 questions · 2 mo ago

    Item 311 Portland Cement Concrete Pavement (PART 2)

    Item 311 Portland Cement Concrete Pavement (PART 2)

    61 questions • 2 mo ago
    Anonymous

    Item 311 Portland Cement Concrete Pavement (PART 1)

    Item 311 Portland Cement Concrete Pavement (PART 1)

    Anonymous · 78 questions · 2 mo ago

    Item 311 Portland Cement Concrete Pavement (PART 1)

    Item 311 Portland Cement Concrete Pavement (PART 1)

    78 questions • 2 mo ago
    Anonymous

    Standpipe Requirements

    Standpipe Requirements

    Anonymous · 29 questions · 2 mo ago

    Standpipe Requirements

    Standpipe Requirements

    29 questions • 2 mo ago
    Anonymous

    Spdi 1

    Spdi 1

    Anonymous · 100 questions · 2 mo ago

    Spdi 1

    Spdi 1

    100 questions • 2 mo ago
    Anonymous

    Spdi 2

    Spdi 2

    Anonymous · 98 questions · 2 mo ago

    Spdi 2

    Spdi 2

    98 questions • 2 mo ago
    Anonymous

    SPI version D pt 2

    SPI version D pt 2

    Anonymous · 61 questions · 2 mo ago

    SPI version D pt 2

    SPI version D pt 2

    61 questions • 2 mo ago
    Anonymous

    plumbing code

    plumbing code

    Anonymous · 100 questions · 2 mo ago

    plumbing code

    plumbing code

    100 questions • 2 mo ago
    Anonymous

    plumbing code 2

    plumbing code 2

    Anonymous · 100 questions · 2 mo ago

    plumbing code 2

    plumbing code 2

    100 questions • 2 mo ago
    Anonymous

    plumbing code 3

    plumbing code 3

    Anonymous · 56 questions · 2 mo ago

    plumbing code 3

    plumbing code 3

    56 questions • 2 mo ago
    Anonymous

    Practice Problem

    Practice Problem

    Anonymous · 70 questions · 2 mo ago

    Practice Problem

    Practice Problem

    70 questions • 2 mo ago
    Anonymous

    PP pre

    PP pre

    Anonymous · 100 questions · 2 mo ago

    PP pre

    PP pre

    100 questions • 2 mo ago
    Anonymous

    PP Pre 2

    PP Pre 2

    Anonymous · 100 questions · 2 mo ago

    PP Pre 2

    PP Pre 2

    100 questions • 2 mo ago
    Anonymous

    PP pre 3

    PP pre 3

    Anonymous · 44 questions · 2 mo ago

    PP pre 3

    PP pre 3

    44 questions • 2 mo ago
    Anonymous

    WT 1

    WT 1

    Anonymous · 50 questions · 2 mo ago

    WT 1

    WT 1

    50 questions • 2 mo ago
    Anonymous

    WT 2

    WT 2

    Anonymous · 48 questions · 2 mo ago

    WT 2

    WT 2

    48 questions • 2 mo ago
    Anonymous

    WT 3

    WT 3

    Anonymous · 50 questions · 2 mo ago

    WT 3

    WT 3

    50 questions • 2 mo ago
    Anonymous

    WT 6

    WT 6

    Anonymous · 50 questions · 2 mo ago

    WT 6

    WT 6

    50 questions • 2 mo ago
    Anonymous

    Definition of Terms 1

    Definition of Terms 1

    Anonymous · 90 questions · 2 mo ago

    Definition of Terms 1

    Definition of Terms 1

    90 questions • 2 mo ago
    Anonymous

    Definition of Terms 2

    Definition of Terms 2

    Anonymous · 90 questions · 2 mo ago

    Definition of Terms 2

    Definition of Terms 2

    90 questions • 2 mo ago
    Anonymous

    Definition of Terms 3

    Definition of Terms 3

    Anonymous · 90 questions · 2 mo ago

    Definition of Terms 3

    Definition of Terms 3

    90 questions • 2 mo ago
    Anonymous

    Refresher SPDI 1

    Refresher SPDI 1

    Anonymous · 100 questions · 2 mo ago

    Refresher SPDI 1

    Refresher SPDI 1

    100 questions • 2 mo ago
    Anonymous

    Refresher SPDI 1

    Refresher SPDI 1

    Anonymous · 9 questions · 2 mo ago

    Refresher SPDI 1

    Refresher SPDI 1

    9 questions • 2 mo ago
    Anonymous

    Weekly Test 1

    Weekly Test 1

    Anonymous · 50 questions · 2 mo ago

    Weekly Test 1

    Weekly Test 1

    50 questions • 2 mo ago
    Anonymous

    Weekly Test 2

    Weekly Test 2

    Anonymous · 50 questions · 2 mo ago

    Weekly Test 2

    Weekly Test 2

    50 questions • 2 mo ago
    Anonymous

    Weekly Test 3

    Weekly Test 3

    Anonymous · 50 questions · 2 mo ago

    Weekly Test 3

    Weekly Test 3

    50 questions • 2 mo ago
    Anonymous

    MPLE

    MPLE

    Anonymous · 41 questions · 2 mo ago

    MPLE

    MPLE

    41 questions • 2 mo ago
    Anonymous

    CDG- Plumbing Code 1

    CDG- Plumbing Code 1

    Anonymous · 48 questions · 2 mo ago

    CDG- Plumbing Code 1

    CDG- Plumbing Code 1

    48 questions • 2 mo ago
    Anonymous

    CDG- Plumbing Code 1.1

    CDG- Plumbing Code 1.1

    Anonymous · 50 questions · 2 mo ago

    CDG- Plumbing Code 1.1

    CDG- Plumbing Code 1.1

    50 questions • 2 mo ago
    Anonymous

    CDG- Plumbing Code 1.4

    CDG- Plumbing Code 1.4

    Anonymous · 23 questions · 2 mo ago

    CDG- Plumbing Code 1.4

    CDG- Plumbing Code 1.4

    23 questions • 2 mo ago
    Anonymous

    CDG- Plumbing Code 1.2

    CDG- Plumbing Code 1.2

    Anonymous · 50 questions · 2 mo ago

    CDG- Plumbing Code 1.2

    CDG- Plumbing Code 1.2

    50 questions • 2 mo ago
    Anonymous

    CGD- Plumbing Code 1.3

    CGD- Plumbing Code 1.3

    Anonymous · 50 questions · 2 mo ago

    CGD- Plumbing Code 1.3

    CGD- Plumbing Code 1.3

    50 questions • 2 mo ago
    Anonymous

    Plumbing Code 1

    Plumbing Code 1

    Anonymous · 50 questions · 2 mo ago

    Plumbing Code 1

    Plumbing Code 1

    50 questions • 2 mo ago
    Anonymous

    Plumbing Code 1.1

    Plumbing Code 1.1

    Anonymous · 22 questions · 2 mo ago

    Plumbing Code 1.1

    Plumbing Code 1.1

    22 questions • 2 mo ago
    Anonymous

    CGD - Sanitary Design

    CGD - Sanitary Design

    Anonymous · 19 questions · 2 mo ago

    CGD - Sanitary Design

    CGD - Sanitary Design

    19 questions • 2 mo ago
    Anonymous

    Practical Problems 1

    Practical Problems 1

    Anonymous · 50 questions · 2 mo ago

    Practical Problems 1

    Practical Problems 1

    50 questions • 2 mo ago
    Anonymous

    Practical Problems 1.1

    Practical Problems 1.1

    Anonymous · 47 questions · 2 mo ago

    Practical Problems 1.1

    Practical Problems 1.1

    47 questions • 2 mo ago
    Anonymous

    Practical Problems 2

    Practical Problems 2

    Anonymous · 50 questions · 2 mo ago

    Practical Problems 2

    Practical Problems 2

    50 questions • 2 mo ago
    Anonymous

    Practical Problems 2.1

    Practical Problems 2.1

    Anonymous · 50 questions · 2 mo ago

    Practical Problems 2.1

    Practical Problems 2.1

    50 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic 1

    Plumbing Arithmetic 1

    Anonymous · 50 questions · 2 mo ago

    Plumbing Arithmetic 1

    Plumbing Arithmetic 1

    50 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic 1.1

    Plumbing Arithmetic 1.1

    Anonymous · 50 questions · 2 mo ago

    Plumbing Arithmetic 1.1

    Plumbing Arithmetic 1.1

    50 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic 2

    Plumbing Arithmetic 2

    Anonymous · 50 questions · 2 mo ago

    Plumbing Arithmetic 2

    Plumbing Arithmetic 2

    50 questions • 2 mo ago
    Anonymous

    Plumbing Arithmetic 2.1

    Plumbing Arithmetic 2.1

    Anonymous · 50 questions · 2 mo ago

    Plumbing Arithmetic 2.1

    Plumbing Arithmetic 2.1

    50 questions • 2 mo ago
    Anonymous

    Question list

  • 1

    Camber in gravel roads is provided to:

    Prevent water from stagnating on carriageway

  • 2

    Whose engineering judgment will prevail in overall field implementation of a project?

    Project Engineer

  • 3

    What is the single vertical datum to which elevation for all infrastructure projects should be referred to?

    Mean Sea Level

  • 4

    When a contract is mutually terminated, the contractor is:

    Allowed to submit bids

  • 5

    The most common hourly volume count used for roadway design is:

    30th Highest Hourly Volume

  • 6

    For testing reinforcing steel bars, the sample for every 10 tons should be:

    1.0m long

  • 7

    The depth of weakened plane joints should not be less than:

    50mm

  • 8

    Unless otherwise specified, all materials below subgrade level in earth should be cut to a depth of:

    150mm

  • 9

    Defective works in a project should be brought to the attention of the contractor by the resident engineer thru:

    Site Instruction

  • 10

    Which of the following is not a field test in road construction?

    California Bearing Ratio (CBR) test

  • 11

    Normally within how many hours can sawing joints commence given that concrete has hardened sufficiently?

    24

  • 12

    What is the required area of the trial section needed to check the suitability of the materials and efficiency of the equipment and the construction method the contractor will use?

    About 500 sqm

  • 13

    The inside face of a pothole, aside from squaring, must be made vertical before patching using cold or hot mix asphalt in order to:

    ensure bond between new mix and old surface

  • 14

    As practical as possible, concrete mix should not be placed where this can be subject to manual dropping by not more than _______ and whre no other special tools and means are used.

    1.5m

  • 15

    Cores taken from a concrete pavement are tested for:

    strength verification of concrete in-place that is considered adequate

  • 16

    Excavation of indurated rocks can be undertaken by:

    Ripper

  • 17

    The minimum flexural strength requirement of concrete for Item 311 (Portland Cement Concrete Pavement) is:

    550psi

  • 18

    The minimum testing requirement of concrete for Item 405 is the compressive strength test on concrete cylinder samples consisting of a set of 3 concrete cylinder samples to represent not more than:

    75cu.m.

  • 19

    In laying stone components of Item 505 (Riprap and Grouted Riprap), each stone should be:

    Laid with its longest axis perpendicular to the slope

  • 20

    What is the required minimum field density for embankment materials?

    95%

  • 21

    Who supervises the work and tests employed in project implementation?

    Project Engineer

  • 22

    Which of the following is not considered a Variation Order?

    Resume Order

  • 23

    On sloping surface, concrete should be places starting at:

    bottom of slope

  • 24

    Resurfacing of unpaved shoulder that was settled or been eroded by traffic and water is an activity under:

    periodic maintainance

  • 25

    The primary quality control mechanism for the production of asphalt mixtures which will have a high degree of uniformity that will satisfy job requirements is called:

    Job-Mix Formula

  • 26

    When considating concrete during pouring operations, vibrator should not be be operated in any one location longer than:

    15 seconds

  • 27

    Which of the following financial controls should be imposed of the project is delayed?

    Liquidated damages

  • 28

    What is the allowable minimum thickness of bedding material beneath a concrete pipe?

    100mm

  • 29

    The best aid in locating and identifying areas of discussion in an inspection report are:

    Photographs

  • 30

    The process of maintaining sufficient moisture and favorable temperature in concrete is called:

    curing

  • 31

    The rate of application of emulsified asphalt used as tack coat, should be within the range of:

    0.2 - 0.7 L/m2

  • 32

    The system of protecting land area from ocean waves is called:

    coastal protection works

  • 33

    In no case, however, shall the total sum of liquidated damage exceed of ____ of the contract price, in which event the contract shall automatically be taken over by the procuring entity concerned or can be awarded to same qualified contractor through negotiated contract.

    10%

  • 34

    Which of the following is not an agent for repairing concrete cracks?

    Sulfur Injection

  • 35

    What type of cement is allowed by the DPWH as a substitute in the absence of Portland Cement Type I?

    Portland Pozzolan Type IP

  • 36

    What kind of joint is established by an interrupted or delayed placing of concrete on partially placed concrete wherin initial setting had already taken place?

    Cold joint

  • 37

    During pouring operations of concrete pavements, what kind of samples should be taken for testing

    Beam samples

  • 38

    Who has the authority to reject questionable materials or suspend the work until it is referred and decided upon by the Project Engineer?

    Materials Engineer

  • 39

    Who assist the Project Engineer in the overall direction and supervision of field operations?

    Project Inspector

  • 40

    What do you call the strengthening of an old existing asphalt or concrete pavement by providing additional adequate thickness over it?

    overlaying

  • 41

    What do you call a record or book compiled to contain data information and history in the implementation of a project from start to completion?

    Logbook

  • 42

    Measurement of concrete materials for concrete structures shall be by:

    volume

  • 43

    Before an asphalt pavement or asphalt surface treatment is placed on a granular base, what liquid asphalt is applied?

    Prime Coat

  • 44

    What is allowable minimum penetration of piles in firm material

    3.0m

  • 45

    If designed thickness of aggregate subbase course is 200mm, in how many layers may the material be spread and compacted?

    1

  • 46

    To check the suitablility of the materials and the efficiency of the equipment and construction method in the construction of embankments and base course, trial sections should be spread and compacted, and corresponding field density test should be undertaken. Said trial section shall be about:

    500 sqm

  • 47

    In field project monitoring using old, approved plans of a river system, which of the following would immediately identify the sheets if pages were already erased?

    Stationings and Matching Lines

  • 48

    For Item 311 (Portland Cement Concrete Pavement) the minimum cement factor in bags of cement per cubic meter of concrete based on a 40kg per bag of cement is:

    9.1

  • 49

    How many years for periodic maintainance for Asphalt Pavement?

    5

  • 50

    It is the graphical representation of monthly cash flow, monitoring of equipment and manpower.

    S Curve

  • 51

    When concrete pilenare lifted oroved, they should be supported at what point?

    Quarter point

  • 52

    For buildings, what is the maximum number of bore hole fornevery 200sq.m. of structure?

    1

  • 53

    In no case, shall the total liquidated damages exceed ____ of the contract price, in which event the contract shall be automatically taken over by the procuring entity concerned or can be awarded to same qualified contractor through negotiated contract?

    10%

  • 54

    For a 2-lane bridge 7.3m in width, what is the minimum no. of girder required?

    4 (urban and rural)

  • 55

    Advance payment of the contractor is an amount not to exceed ___ of the total original contract amount.

    15%

  • 56

    At least 1 set consisting of ___ concrete beam test specimens shall be taken from each 330sq.m. of pavement, 0.23cm thick or fraction thereof placed each day.

    3

  • 57

    Persuant to the RA 9184, what is the applicable rate of liquidated damages?

    1/10 of 1 percent

  • 58

    What do you call the method of determining stream discharge by measuring the cross sectional area of the stream and its velocity with a current meter?

    Velocity Area Method

  • 59

    What is the most used pile driver in the country?

    Diesel Hammer

  • 60

    Initial rolling in bituminous mixes shall be performed with a ____ roller?

    Pneumatic Tire Roller

  • 61

    What is the Project Scheduling technique in DPWH Project?

    PDM (Precedence Diagram Method)

  • 62

    Process of rolling/compaction of bituminous pavement?

    It should begin from the sides and proceed longitudinally parallel toward the road center line, each trip overlapping one half of the roller's width.