Item 303 Bituminous Seal Coat

Item 303 Bituminous Seal Coat
20問 • 1年前
  • Vaantoote
  • 通報

    問題一覧

  • 1

    Quantity for bituminous material (L/m2) for seal coat, Type 1

    0.20 to 0.50

  • 2

    Quantity for bituminous material (L/m2) for seal coat, Type 2

    0.51 to 1.00

  • 3

    Quantity for bituminous material (L/m2) for seal coat, Type 3

    1.01 to 1.50

  • 4

    Quantity of cover aggregate (kg/sq.m) for seal coat, Type 1

    None

  • 5

    Quantity of cover aggregate (kg/sq.m) for seal coat, Type 2

    5.00 to 10.00

  • 6

    Quantity of cover aggregate (kg/sq.m) for seal coat, Type 3

    10.01 to 14.00

  • 7

    The cover aggregate for _____ seal coat shall consist of sand and fine screenings, reasonably free from dirt or other organic matter.

    Type 2

  • 8

    Aggregate for ____ seal coat shall be crushed stone, crushed slag, or crushed gravel.

    Type 3

  • 9

    Cover aggregate shall have a mass percent of wear not exceeding _____ according to Los Angeles Abrasion Test.

    40

  • 10

    In cover aggregate, when crushed slag is used, it shall be of uniform density and quality and shall have a density of not less than ____.

    960 kg/cu.m

  • 11

    In no event seal coat shall be placed on a newly constructed or reconditioned surfaces in less than ____ after such surface is laid and opened to traffic, unless ordered in written by the engineer.

    10 days

  • 12

    For asphalt cement, bituminous material shall be applied by means of pressure distributor at the rate of approximately

    0.9 to 1.8 liters

  • 13

    For cutback asphalt, bituminous material shall be applied by means of pressure distributor at the rate of approximately ____ per square meter of surface, in a uniform unbroken spread over the section to be treated.

    1.5 to 3.0 liters

  • 14

    The pressure distributor shall be equipped with a _______ registering the speed and so located as to be visible to the truck driver.

    fifth wheel tacometer

  • 15

    The distributor pump shall be equipped with a gauge registering ______ passing through the nozzles and readily visible to the operator.

    liters per minute

  • 16

    The application of bituminous material at the junction of spreads is not in excess of the specified quantities, any excess shall be removed from the surface by a:

    squeegee

  • 17

    If necessary, to obtain proper junction of spreads, a strip of manila paper approximately ____ wide and at least as long as the spray bar shall be used at the beginning and end of each spread.

    1m

  • 18

    Immediately after the application of asphalt, the cover aggregate shall be evenly spread over the surface at the rate of approximately _________ per sq.m

    0.004 to 0.007 cu.m

  • 19

    As soon as the cover aggregate has been spread, the spread shall be broomed lightly with an approved push or drag broom to insure an even distribution, and shall then be rolled with an approved power roller weighing not less than ____, nor more than ____ to a uniform surface.

    5 tonnes, 6 tonnes

  • 20

    The quantities of bituminous material and cover aggregate shall be measured by _____, calculated by the actual size of application approved by the engineer.

    tonne

  • Project Engineer EXAM

    Project Engineer EXAM

    Vaantoote · 62問 · 2年前

    Project Engineer EXAM

    Project Engineer EXAM

    62問 • 2年前
    Vaantoote

    YT1 Materials Engineer EXAM

    YT1 Materials Engineer EXAM

    Vaantoote · 100問 · 2年前

    YT1 Materials Engineer EXAM

    YT1 Materials Engineer EXAM

    100問 • 2年前
    Vaantoote

    YT2 Materials Engineer EXAM

    YT2 Materials Engineer EXAM

    Vaantoote · 100問 · 2年前

    YT2 Materials Engineer EXAM

    YT2 Materials Engineer EXAM

    100問 • 2年前
    Vaantoote

    Project Engineer YT 1

    Project Engineer YT 1

    Vaantoote · 100問 · 1年前

    Project Engineer YT 1

    Project Engineer YT 1

    100問 • 1年前
    Vaantoote

    Project Engineer EXAM 68

    Project Engineer EXAM 68

    Vaantoote · 100問 · 1年前

    Project Engineer EXAM 68

    Project Engineer EXAM 68

    100問 • 1年前
    Vaantoote

    Project Engineer EXAM 82

    Project Engineer EXAM 82

    Vaantoote · 100問 · 1年前

    Project Engineer EXAM 82

    Project Engineer EXAM 82

    100問 • 1年前
    Vaantoote

    July 2023 PE Refresher

    July 2023 PE Refresher

    Vaantoote · 70問 · 1年前

    July 2023 PE Refresher

    July 2023 PE Refresher

    70問 • 1年前
    Vaantoote

    August 2019 Special PE Exam

    August 2019 Special PE Exam

    Vaantoote · 93問 · 1年前

    August 2019 Special PE Exam

    August 2019 Special PE Exam

    93問 • 1年前
    Vaantoote

    RNPCP Chapter 1 to 5

    RNPCP Chapter 1 to 5

    Vaantoote · 86問 · 1年前

    RNPCP Chapter 1 to 5

    RNPCP Chapter 1 to 5

    86問 • 1年前
    Vaantoote

    Plumbing Code 1

    Plumbing Code 1

    Vaantoote · 100問 · 1年前

    Plumbing Code 1

    Plumbing Code 1

    100問 • 1年前
    Vaantoote

    Plumbing Code 2

    Plumbing Code 2

    Vaantoote · 100問 · 1年前

    Plumbing Code 2

    Plumbing Code 2

    100問 • 1年前
    Vaantoote

    Plumbing Code 4

    Plumbing Code 4

    Vaantoote · 100問 · 1年前

    Plumbing Code 4

    Plumbing Code 4

    100問 • 1年前
    Vaantoote

    Plumbing Code 5

    Plumbing Code 5

    Vaantoote · 100問 · 1年前

    Plumbing Code 5

    Plumbing Code 5

    100問 • 1年前
    Vaantoote

    Plumbing Code 6

    Plumbing Code 6

    Vaantoote · 100問 · 1年前

    Plumbing Code 6

    Plumbing Code 6

    100問 • 1年前
    Vaantoote

    Plumbing Code 7

    Plumbing Code 7

    Vaantoote · 100問 · 1年前

    Plumbing Code 7

    Plumbing Code 7

    100問 • 1年前
    Vaantoote

    Plumbing Code 8

    Plumbing Code 8

    Vaantoote · 100問 · 1年前

    Plumbing Code 8

    Plumbing Code 8

    100問 • 1年前
    Vaantoote

    Plumbing Code 3

    Plumbing Code 3

    Vaantoote · 100問 · 1年前

    Plumbing Code 3

    Plumbing Code 3

    100問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 2

    Sanitation, Plumbing Design, and Installation 2

    Vaantoote · 97問 · 1年前

    Sanitation, Plumbing Design, and Installation 2

    Sanitation, Plumbing Design, and Installation 2

    97問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 1

    Sanitation, Plumbing Design, and Installation 1

    Vaantoote · 99問 · 1年前

    Sanitation, Plumbing Design, and Installation 1

    Sanitation, Plumbing Design, and Installation 1

    99問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 3

    Sanitation, Plumbing Design, and Installation 3

    Vaantoote · 96問 · 1年前

    Sanitation, Plumbing Design, and Installation 3

    Sanitation, Plumbing Design, and Installation 3

    96問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 4

    Sanitation, Plumbing Design, and Installation 4

    Vaantoote · 95問 · 1年前

    Sanitation, Plumbing Design, and Installation 4

    Sanitation, Plumbing Design, and Installation 4

    95問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 5

    Sanitation, Plumbing Design, and Installation 5

    Vaantoote · 97問 · 1年前

    Sanitation, Plumbing Design, and Installation 5

    Sanitation, Plumbing Design, and Installation 5

    97問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 7

    Sanitation, Plumbing Design, and Installation 7

    Vaantoote · 100問 · 1年前

    Sanitation, Plumbing Design, and Installation 7

    Sanitation, Plumbing Design, and Installation 7

    100問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 8

    Sanitation, Plumbing Design, and Installation 8

    Vaantoote · 98問 · 1年前

    Sanitation, Plumbing Design, and Installation 8

    Sanitation, Plumbing Design, and Installation 8

    98問 • 1年前
    Vaantoote

    Plumbing Tools 1

    Plumbing Tools 1

    Vaantoote · 87問 · 1年前

    Plumbing Tools 1

    Plumbing Tools 1

    87問 • 1年前
    Vaantoote

    Plumbing Tools 2

    Plumbing Tools 2

    Vaantoote · 53問 · 1年前

    Plumbing Tools 2

    Plumbing Tools 2

    53問 • 1年前
    Vaantoote

    Practical Problems and Experiences 1

    Practical Problems and Experiences 1

    Vaantoote · 100問 · 1年前

    Practical Problems and Experiences 1

    Practical Problems and Experiences 1

    100問 • 1年前
    Vaantoote

    Practical Problems and Experiences 2

    Practical Problems and Experiences 2

    Vaantoote · 100問 · 1年前

    Practical Problems and Experiences 2

    Practical Problems and Experiences 2

    100問 • 1年前
    Vaantoote

    Practical Problems and Experiences 3

    Practical Problems and Experiences 3

    Vaantoote · 99問 · 1年前

    Practical Problems and Experiences 3

    Practical Problems and Experiences 3

    99問 • 1年前
    Vaantoote

    Practical Problems and Experiences 4

    Practical Problems and Experiences 4

    Vaantoote · 100問 · 1年前

    Practical Problems and Experiences 4

    Practical Problems and Experiences 4

    100問 • 1年前
    Vaantoote

    PART A - Facilities for the Engineer

    PART A - Facilities for the Engineer

    Vaantoote · 9問 · 1年前

    PART A - Facilities for the Engineer

    PART A - Facilities for the Engineer

    9問 • 1年前
    Vaantoote

    PART B - Other General Requirements

    PART B - Other General Requirements

    Vaantoote · 13問 · 1年前

    PART B - Other General Requirements

    PART B - Other General Requirements

    13問 • 1年前
    Vaantoote

    Practical Problems and Experiences 5

    Practical Problems and Experiences 5

    Vaantoote · 100問 · 1年前

    Practical Problems and Experiences 5

    Practical Problems and Experiences 5

    100問 • 1年前
    Vaantoote

    Practical Problems and Experiences 6

    Practical Problems and Experiences 6

    Vaantoote · 100問 · 1年前

    Practical Problems and Experiences 6

    Practical Problems and Experiences 6

    100問 • 1年前
    Vaantoote

    Plumbing Arithmetic Terms 1

    Plumbing Arithmetic Terms 1

    Vaantoote · 49問 · 1年前

    Plumbing Arithmetic Terms 1

    Plumbing Arithmetic Terms 1

    49問 • 1年前
    Vaantoote

    Plumbing Arithmetic Terms 2

    Plumbing Arithmetic Terms 2

    Vaantoote · 47問 · 1年前

    Plumbing Arithmetic Terms 2

    Plumbing Arithmetic Terms 2

    47問 • 1年前
    Vaantoote

    Plumbing Arithmetic Terms 3

    Plumbing Arithmetic Terms 3

    Vaantoote · 49問 · 1年前

    Plumbing Arithmetic Terms 3

    Plumbing Arithmetic Terms 3

    49問 • 1年前
    Vaantoote

    Plumbing Arithmetic Terms 4

    Plumbing Arithmetic Terms 4

    Vaantoote · 27問 · 1年前

    Plumbing Arithmetic Terms 4

    Plumbing Arithmetic Terms 4

    27問 • 1年前
    Vaantoote

    Plumbing Code WSFU

    Plumbing Code WSFU

    Vaantoote · 58問 · 1年前

    Plumbing Code WSFU

    Plumbing Code WSFU

    58問 • 1年前
    Vaantoote

    Practical Problems and Experiences REFRESHER 1

    Practical Problems and Experiences REFRESHER 1

    Vaantoote · 100問 · 1年前

    Practical Problems and Experiences REFRESHER 1

    Practical Problems and Experiences REFRESHER 1

    100問 • 1年前
    Vaantoote

    Practical Problems and Experiences REFRESHER 2

    Practical Problems and Experiences REFRESHER 2

    Vaantoote · 70問 · 1年前

    Practical Problems and Experiences REFRESHER 2

    Practical Problems and Experiences REFRESHER 2

    70問 • 1年前
    Vaantoote

    Item # and Descriptions

    Item # and Descriptions

    Vaantoote · 24問 · 1年前

    Item # and Descriptions

    Item # and Descriptions

    24問 • 1年前
    Vaantoote

    Item 200 Aggregate Subbase Course

    Item 200 Aggregate Subbase Course

    Vaantoote · 16問 · 1年前

    Item 200 Aggregate Subbase Course

    Item 200 Aggregate Subbase Course

    16問 • 1年前
    Vaantoote

    Item 201 Aggregate Base Course

    Item 201 Aggregate Base Course

    Vaantoote · 16問 · 1年前

    Item 201 Aggregate Base Course

    Item 201 Aggregate Base Course

    16問 • 1年前
    Vaantoote

    Item 202 Crushed Aggregate Base Course

    Item 202 Crushed Aggregate Base Course

    Vaantoote · 18問 · 1年前

    Item 202 Crushed Aggregate Base Course

    Item 202 Crushed Aggregate Base Course

    18問 • 1年前
    Vaantoote

    Item 203 Lime Stabilized Road Mix Base Course

    Item 203 Lime Stabilized Road Mix Base Course

    Vaantoote · 27問 · 1年前

    Item 203 Lime Stabilized Road Mix Base Course

    Item 203 Lime Stabilized Road Mix Base Course

    27問 • 1年前
    Vaantoote

    Item 204 Portland Cement Stabilized Road Mix Base Course

    Item 204 Portland Cement Stabilized Road Mix Base Course

    Vaantoote · 7問 · 1年前

    Item 204 Portland Cement Stabilized Road Mix Base Course

    Item 204 Portland Cement Stabilized Road Mix Base Course

    7問 • 1年前
    Vaantoote

    Item 205 Asphalt Stabilized Road Mix Base Course

    Item 205 Asphalt Stabilized Road Mix Base Course

    Vaantoote · 7問 · 1年前

    Item 205 Asphalt Stabilized Road Mix Base Course

    Item 205 Asphalt Stabilized Road Mix Base Course

    7問 • 1年前
    Vaantoote

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    Vaantoote · 13問 · 1年前

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    Item 207 Portland Cement Stabilized Treated Plant Mix Base Course

    13問 • 1年前
    Vaantoote

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    Vaantoote · 11問 · 1年前

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    Item 206 Chemically Stabilized Road Mix Subbase/Base Course

    11問 • 1年前
    Vaantoote

    Item 300 Aggregate Surface Course

    Item 300 Aggregate Surface Course

    Vaantoote · 11問 · 1年前

    Item 300 Aggregate Surface Course

    Item 300 Aggregate Surface Course

    11問 • 1年前
    Vaantoote

    Item 301 Bituminous Prime Coat

    Item 301 Bituminous Prime Coat

    Vaantoote · 10問 · 1年前

    Item 301 Bituminous Prime Coat

    Item 301 Bituminous Prime Coat

    10問 • 1年前
    Vaantoote

    RNPCP Chapter 6 to 9

    RNPCP Chapter 6 to 9

    Vaantoote · 94問 · 1年前

    RNPCP Chapter 6 to 9

    RNPCP Chapter 6 to 9

    94問 • 1年前
    Vaantoote

    RNPCP Chapter 10 to 13

    RNPCP Chapter 10 to 13

    Vaantoote · 93問 · 1年前

    RNPCP Chapter 10 to 13

    RNPCP Chapter 10 to 13

    93問 • 1年前
    Vaantoote

    RNPCP Appendix A and B

    RNPCP Appendix A and B

    Vaantoote · 79問 · 1年前

    RNPCP Appendix A and B

    RNPCP Appendix A and B

    79問 • 1年前
    Vaantoote

    Item 311 Portland Cement Concrete Pavement (PART 1)

    Item 311 Portland Cement Concrete Pavement (PART 1)

    Vaantoote · 78問 · 1年前

    Item 311 Portland Cement Concrete Pavement (PART 1)

    Item 311 Portland Cement Concrete Pavement (PART 1)

    78問 • 1年前
    Vaantoote

    Item 311 Portland Cement Concrete Pavement (PART 2)

    Item 311 Portland Cement Concrete Pavement (PART 2)

    Vaantoote · 61問 · 1年前

    Item 311 Portland Cement Concrete Pavement (PART 2)

    Item 311 Portland Cement Concrete Pavement (PART 2)

    61問 • 1年前
    Vaantoote

    Republic Acts

    Republic Acts

    Vaantoote · 9問 · 1年前

    Republic Acts

    Republic Acts

    9問 • 1年前
    Vaantoote

    Plumbing Arithmetic Terms 5

    Plumbing Arithmetic Terms 5

    Vaantoote · 68問 · 1年前

    Plumbing Arithmetic Terms 5

    Plumbing Arithmetic Terms 5

    68問 • 1年前
    Vaantoote

    Item 400 Piling

    Item 400 Piling

    Vaantoote · 80問 · 1年前

    Item 400 Piling

    Item 400 Piling

    80問 • 1年前
    Vaantoote

    Item 405 Structural Concrete

    Item 405 Structural Concrete

    Vaantoote · 41問 · 1年前

    Item 405 Structural Concrete

    Item 405 Structural Concrete

    41問 • 1年前
    Vaantoote

    Item 406 Prestressed Concrete Structures

    Item 406 Prestressed Concrete Structures

    Vaantoote · 36問 · 1年前

    Item 406 Prestressed Concrete Structures

    Item 406 Prestressed Concrete Structures

    36問 • 1年前
    Vaantoote

    Item 407 Concrete Structures

    Item 407 Concrete Structures

    Vaantoote · 31問 · 1年前

    Item 407 Concrete Structures

    Item 407 Concrete Structures

    31問 • 1年前
    Vaantoote

    Plumbing Design and Estimate (by Max Fajardo)

    Plumbing Design and Estimate (by Max Fajardo)

    Vaantoote · 22問 · 1年前

    Plumbing Design and Estimate (by Max Fajardo)

    Plumbing Design and Estimate (by Max Fajardo)

    22問 • 1年前
    Vaantoote

    Principles and Code of Ethics

    Principles and Code of Ethics

    Vaantoote · 29問 · 1年前

    Principles and Code of Ethics

    Principles and Code of Ethics

    29問 • 1年前
    Vaantoote

    Plumbing Arithmetic Problems 1

    Plumbing Arithmetic Problems 1

    Vaantoote · 75問 · 1年前

    Plumbing Arithmetic Problems 1

    Plumbing Arithmetic Problems 1

    75問 • 1年前
    Vaantoote

    問題一覧

  • 1

    Quantity for bituminous material (L/m2) for seal coat, Type 1

    0.20 to 0.50

  • 2

    Quantity for bituminous material (L/m2) for seal coat, Type 2

    0.51 to 1.00

  • 3

    Quantity for bituminous material (L/m2) for seal coat, Type 3

    1.01 to 1.50

  • 4

    Quantity of cover aggregate (kg/sq.m) for seal coat, Type 1

    None

  • 5

    Quantity of cover aggregate (kg/sq.m) for seal coat, Type 2

    5.00 to 10.00

  • 6

    Quantity of cover aggregate (kg/sq.m) for seal coat, Type 3

    10.01 to 14.00

  • 7

    The cover aggregate for _____ seal coat shall consist of sand and fine screenings, reasonably free from dirt or other organic matter.

    Type 2

  • 8

    Aggregate for ____ seal coat shall be crushed stone, crushed slag, or crushed gravel.

    Type 3

  • 9

    Cover aggregate shall have a mass percent of wear not exceeding _____ according to Los Angeles Abrasion Test.

    40

  • 10

    In cover aggregate, when crushed slag is used, it shall be of uniform density and quality and shall have a density of not less than ____.

    960 kg/cu.m

  • 11

    In no event seal coat shall be placed on a newly constructed or reconditioned surfaces in less than ____ after such surface is laid and opened to traffic, unless ordered in written by the engineer.

    10 days

  • 12

    For asphalt cement, bituminous material shall be applied by means of pressure distributor at the rate of approximately

    0.9 to 1.8 liters

  • 13

    For cutback asphalt, bituminous material shall be applied by means of pressure distributor at the rate of approximately ____ per square meter of surface, in a uniform unbroken spread over the section to be treated.

    1.5 to 3.0 liters

  • 14

    The pressure distributor shall be equipped with a _______ registering the speed and so located as to be visible to the truck driver.

    fifth wheel tacometer

  • 15

    The distributor pump shall be equipped with a gauge registering ______ passing through the nozzles and readily visible to the operator.

    liters per minute

  • 16

    The application of bituminous material at the junction of spreads is not in excess of the specified quantities, any excess shall be removed from the surface by a:

    squeegee

  • 17

    If necessary, to obtain proper junction of spreads, a strip of manila paper approximately ____ wide and at least as long as the spray bar shall be used at the beginning and end of each spread.

    1m

  • 18

    Immediately after the application of asphalt, the cover aggregate shall be evenly spread over the surface at the rate of approximately _________ per sq.m

    0.004 to 0.007 cu.m

  • 19

    As soon as the cover aggregate has been spread, the spread shall be broomed lightly with an approved push or drag broom to insure an even distribution, and shall then be rolled with an approved power roller weighing not less than ____, nor more than ____ to a uniform surface.

    5 tonnes, 6 tonnes

  • 20

    The quantities of bituminous material and cover aggregate shall be measured by _____, calculated by the actual size of application approved by the engineer.

    tonne