Item 206 Chemically Stabilized Road Mix Subbase/Base Course
11問 • 1年前
  • Vaantoote
  • 通報

    問題一覧

  • 1

    Polymer-based chemical soil additive shall be less than ___ by weight of soil

    2%

  • 2

    The unsoaked CBR value of treated soil material with Olymer-based chemical soil additive shall be ________ the unsoaked CBR value of untreated same soil material

    greater than

  • 3

    Existing road subbase/base materials shall be scarified by use of grader to a depth of _____ to _____ and shall be stockpiled on both sides of the road.

    150mm, 200mm

  • 4

    If further needed, polymer-based chemical soil additive shall be applied on the subbase/base after it was exposed for ____, provided that after applying the said chemical additive, the first layer of road subbase/base materials which is thoroughly mixed shall be spread immediately.

    24hrs

  • 5

    The dilution rate for the subbase/base shall be ___ part of polymer-based chemical soil additive and ___ parts of water depending on type of soil and application method

    1, 5-9

  • 6

    After the preparation of subbase/base material, it shall be mixed thoroughly and spread by a grader in approximately ___ equal layers.

    2

  • 7

    Rate of dilution in each layer

    1:5 to 1:9

  • 8

    Steel roller shall be used to crush aggregates larger than ____ on the surface of the laid/treated subbase/base course while rubber roller shall follow to smoothen the surface.

    1/2" or 13mm

  • 9

    After _____ of curing, polymer-based chemical soil additive shall be sprayed on the compacted road subbase/base with required dilution in each layer.

    48hrs

  • 10

    Trial sections of the stabilized subbase/base shall be constructed by the contractor at least ____ before the actual subbase/base construction

    2 weeks

  • 11

    Polymer-based chemical soil additive shall be measured by:

    liter

  • Project Engineer EXAM

    Project Engineer EXAM

    Vaantoote · 62問 · 2年前

    Project Engineer EXAM

    Project Engineer EXAM

    62問 • 2年前
    Vaantoote

    YT1 Materials Engineer EXAM

    YT1 Materials Engineer EXAM

    Vaantoote · 100問 · 1年前

    YT1 Materials Engineer EXAM

    YT1 Materials Engineer EXAM

    100問 • 1年前
    Vaantoote

    YT2 Materials Engineer EXAM

    YT2 Materials Engineer EXAM

    Vaantoote · 100問 · 1年前

    YT2 Materials Engineer EXAM

    YT2 Materials Engineer EXAM

    100問 • 1年前
    Vaantoote

    Project Engineer YT 1

    Project Engineer YT 1

    Vaantoote · 100問 · 1年前

    Project Engineer YT 1

    Project Engineer YT 1

    100問 • 1年前
    Vaantoote

    Project Engineer EXAM 68

    Project Engineer EXAM 68

    Vaantoote · 100問 · 1年前

    Project Engineer EXAM 68

    Project Engineer EXAM 68

    100問 • 1年前
    Vaantoote

    Project Engineer EXAM 82

    Project Engineer EXAM 82

    Vaantoote · 100問 · 1年前

    Project Engineer EXAM 82

    Project Engineer EXAM 82

    100問 • 1年前
    Vaantoote

    July 2023 PE Refresher

    July 2023 PE Refresher

    Vaantoote · 70問 · 1年前

    July 2023 PE Refresher

    July 2023 PE Refresher

    70問 • 1年前
    Vaantoote

    August 2019 Special PE Exam

    August 2019 Special PE Exam

    Vaantoote · 93問 · 1年前

    August 2019 Special PE Exam

    August 2019 Special PE Exam

    93問 • 1年前
    Vaantoote

    RNPCP Chapter 1 to 5

    RNPCP Chapter 1 to 5

    Vaantoote · 86問 · 1年前

    RNPCP Chapter 1 to 5

    RNPCP Chapter 1 to 5

    86問 • 1年前
    Vaantoote

    Plumbing Code 1

    Plumbing Code 1

    Vaantoote · 100問 · 1年前

    Plumbing Code 1

    Plumbing Code 1

    100問 • 1年前
    Vaantoote

    Plumbing Code 2

    Plumbing Code 2

    Vaantoote · 100問 · 1年前

    Plumbing Code 2

    Plumbing Code 2

    100問 • 1年前
    Vaantoote

    Plumbing Code 4

    Plumbing Code 4

    Vaantoote · 100問 · 1年前

    Plumbing Code 4

    Plumbing Code 4

    100問 • 1年前
    Vaantoote

    Plumbing Code 5

    Plumbing Code 5

    Vaantoote · 100問 · 1年前

    Plumbing Code 5

    Plumbing Code 5

    100問 • 1年前
    Vaantoote

    Plumbing Code 6

    Plumbing Code 6

    Vaantoote · 100問 · 1年前

    Plumbing Code 6

    Plumbing Code 6

    100問 • 1年前
    Vaantoote

    Plumbing Code 7

    Plumbing Code 7

    Vaantoote · 100問 · 1年前

    Plumbing Code 7

    Plumbing Code 7

    100問 • 1年前
    Vaantoote

    Plumbing Code 8

    Plumbing Code 8

    Vaantoote · 100問 · 1年前

    Plumbing Code 8

    Plumbing Code 8

    100問 • 1年前
    Vaantoote

    Plumbing Code 3

    Plumbing Code 3

    Vaantoote · 100問 · 1年前

    Plumbing Code 3

    Plumbing Code 3

    100問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 2

    Sanitation, Plumbing Design, and Installation 2

    Vaantoote · 97問 · 1年前

    Sanitation, Plumbing Design, and Installation 2

    Sanitation, Plumbing Design, and Installation 2

    97問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 1

    Sanitation, Plumbing Design, and Installation 1

    Vaantoote · 99問 · 1年前

    Sanitation, Plumbing Design, and Installation 1

    Sanitation, Plumbing Design, and Installation 1

    99問 • 1年前
    Vaantoote

    Sanitation, Plumbing Design, and Installation 3

    Sanitation, Plumbing Design, and Installation 3

    Vaantoote · 96問 · 1年前

    Sanitation, Plumbing Design, and Installation 3

    Sanitation, Plumbing Design, and Installation 3

    96問 • 1年前
    Vaantoote

    問題一覧

  • 1

    Polymer-based chemical soil additive shall be less than ___ by weight of soil

    2%

  • 2

    The unsoaked CBR value of treated soil material with Olymer-based chemical soil additive shall be ________ the unsoaked CBR value of untreated same soil material

    greater than

  • 3

    Existing road subbase/base materials shall be scarified by use of grader to a depth of _____ to _____ and shall be stockpiled on both sides of the road.

    150mm, 200mm

  • 4

    If further needed, polymer-based chemical soil additive shall be applied on the subbase/base after it was exposed for ____, provided that after applying the said chemical additive, the first layer of road subbase/base materials which is thoroughly mixed shall be spread immediately.

    24hrs

  • 5

    The dilution rate for the subbase/base shall be ___ part of polymer-based chemical soil additive and ___ parts of water depending on type of soil and application method

    1, 5-9

  • 6

    After the preparation of subbase/base material, it shall be mixed thoroughly and spread by a grader in approximately ___ equal layers.

    2

  • 7

    Rate of dilution in each layer

    1:5 to 1:9

  • 8

    Steel roller shall be used to crush aggregates larger than ____ on the surface of the laid/treated subbase/base course while rubber roller shall follow to smoothen the surface.

    1/2" or 13mm

  • 9

    After _____ of curing, polymer-based chemical soil additive shall be sprayed on the compacted road subbase/base with required dilution in each layer.

    48hrs

  • 10

    Trial sections of the stabilized subbase/base shall be constructed by the contractor at least ____ before the actual subbase/base construction

    2 weeks

  • 11

    Polymer-based chemical soil additive shall be measured by:

    liter