    The construction of large open cuttings or excavations involving both cutting and filling of material other than rock

    earthwork

  • 2

    The process of loosening and removing earth or rock from its original position in a cut and transporting it to a fill or to a waste deposit

    excavation / cut

  • 3

    The soil or rock materials added above the low points along the roadway to raise the level to the bottom of the pavement structure material for embankment commonly comes from roadway cuts or designated borrow areas

    embankment / fill

  • 4

    It is the product of volume of earth excavated and the distance transported to form an embarkment or to be disposed of as waste

    haul

  • 5

    A fixed distance in which the ha—— (hauled) materials is not paid but is assumed ro be nearly included in the cost of excavation, it is usually ______ long

    free haul distance (FHD) , 200 meters

  • 6

    It means that a certain distance will not have an additional cost to excavate and embank earth soil

    free haul distance

  • 7

    It is the proposed road slope

    grade line

  • 8

    When rod readings are taken at each slope stake, in addition to readings taken at the center as will normally be done where the ground is sloping, the cross-section is called a ______

    three — level section

  • EM Waves and Spectrum

    EM Waves and Spectrum

    John Marabiles · 73問 · 1年前

    EM Waves and Spectrum

    EM Waves and Spectrum

    73問 • 1年前
    John Marabiles

    Polarization

    Polarization

    John Marabiles · 25問 · 1年前

    Polarization

    Polarization

    25問 • 1年前
    John Marabiles

    Lesson 1

    Lesson 1

    John Marabiles · 9問 · 1年前

    Lesson 1

    Lesson 1

    9問 • 1年前
    John Marabiles

    Lesson 2

    Lesson 2

    John Marabiles · 8問 · 1年前

    Lesson 2

    Lesson 2

    8問 • 1年前
    John Marabiles

    Lesson 3

    Lesson 3

    John Marabiles · 7問 · 1年前

    Lesson 3

    Lesson 3

    7問 • 1年前
    John Marabiles

    Chapter 10

    Chapter 10

    John Marabiles · 43問 · 1年前

    Chapter 10

    Chapter 10

    43問 • 1年前
    John Marabiles

    Evidence Of Evolution

    Evidence Of Evolution

    John Marabiles · 46問 · 1年前

    Evidence Of Evolution

    Evidence Of Evolution

    46問 • 1年前
    John Marabiles

    Traditional Materials

    Traditional Materials

    John Marabiles · 20問 · 1年前

    Traditional Materials

    Traditional Materials

    20問 • 1年前
    John Marabiles

    Crushing Strength Of Common Building Stones

    Crushing Strength Of Common Building Stones

    John Marabiles · 8問 · 1年前

    Crushing Strength Of Common Building Stones

    Crushing Strength Of Common Building Stones

    8問 • 1年前
    John Marabiles

    Properties Of Stones

    Properties Of Stones

    John Marabiles · 16問 · 1年前

    Properties Of Stones

    Properties Of Stones

    16問 • 1年前
    John Marabiles

    Requirements Of Good Building Stones:

    Requirements Of Good Building Stones:

    John Marabiles · 11問 · 1年前

    Requirements Of Good Building Stones:

    Requirements Of Good Building Stones:

    11問 • 1年前
    John Marabiles

    Tests On Stones

    Tests On Stones

    John Marabiles · 5問 · 1年前

    Tests On Stones

    Tests On Stones

    5問 • 1年前
    John Marabiles

    Structural Reading

    Structural Reading

    John Marabiles · 22問 · 1年前

    Structural Reading

    Structural Reading

    22問 • 1年前
    John Marabiles

    General Chemistry

    General Chemistry

    John Marabiles · 50問 · 1年前

    General Chemistry

    General Chemistry

    50問 • 1年前
    John Marabiles

    Lesson 1: Construction Sector

    Lesson 1: Construction Sector

    John Marabiles · 10問 · 1年前

    Lesson 1: Construction Sector

    Lesson 1: Construction Sector

    10問 • 1年前
    John Marabiles

    Lesson 2: Participating in Workplace Communication and Collaboration

    Lesson 2: Participating in Workplace Communication and Collaboration

    John Marabiles · 11問 · 1年前

    Lesson 2: Participating in Workplace Communication and Collaboration

    Lesson 2: Participating in Workplace Communication and Collaboration

    11問 • 1年前
    John Marabiles

    問題一覧

  • 1

    The construction of large open cuttings or excavations involving both cutting and filling of material other than rock

    earthwork

  • 2

    The process of loosening and removing earth or rock from its original position in a cut and transporting it to a fill or to a waste deposit

    excavation / cut

  • 3

    The soil or rock materials added above the low points along the roadway to raise the level to the bottom of the pavement structure material for embankment commonly comes from roadway cuts or designated borrow areas

    embankment / fill

  • 4

    It is the product of volume of earth excavated and the distance transported to form an embarkment or to be disposed of as waste

    haul

  • 5

    A fixed distance in which the ha—— (hauled) materials is not paid but is assumed ro be nearly included in the cost of excavation, it is usually ______ long

    free haul distance (FHD) , 200 meters

  • 6

    It means that a certain distance will not have an additional cost to excavate and embank earth soil

    free haul distance

  • 7

    It is the proposed road slope

    grade line

  • 8

    When rod readings are taken at each slope stake, in addition to readings taken at the center as will normally be done where the ground is sloping, the cross-section is called a ______

    three — level section