    問題一覧

  • 1

    In construction scheduling, one of the most efficient method to use is ______

    critical path method

  • 2

    It is a three-phase procedure consisting of planning, scheduling, and time monitoring or controlling

    cpm

  • 3

    It involves the determination of what must be done, how it is performed, and the sequential order in which it will be carried out

    planning construction operations

  • 4

    It determines calendar dates for the start and completion of project components

    scheduling

  • 5

    It is the process of comparing actual job progress with the schedule

    time monitoring

  • 6

    The management techniques of CPM are based on graphical project model called a ______ This ______ presents in diagrammatic form those job activities that must be carried out and their mutual time dependencies

    network

  • 7

    Types of schedule compression:

    fast tracking , crashing

  • 8

    Shortening by working activities simultaneously with increased risk

    fast tracking

  • 9

    Shortening by adding resources for the least cost possible

    crashing

  • 10

    It is used to compute the duration of the project and estimating the needed manpower and materials

    cpm

  • EM Waves and Spectrum

    EM Waves and Spectrum

    John Marabiles · 73問 · 1年前

    EM Waves and Spectrum

    EM Waves and Spectrum

    73問 • 1年前
    John Marabiles

    Polarization

    Polarization

    John Marabiles · 25問 · 1年前

    Polarization

    Polarization

    25問 • 1年前
    John Marabiles

    Lesson 1

    Lesson 1

    John Marabiles · 9問 · 1年前

    Lesson 1

    Lesson 1

    9問 • 1年前
    John Marabiles

    Lesson 2

    Lesson 2

    John Marabiles · 8問 · 1年前

    Lesson 2

    Lesson 2

    8問 • 1年前
    John Marabiles

    Lesson 3

    Lesson 3

    John Marabiles · 7問 · 1年前

    Lesson 3

    Lesson 3

    7問 • 1年前
    John Marabiles

    Chapter 10

    Chapter 10

    John Marabiles · 43問 · 1年前

    Chapter 10

    Chapter 10

    43問 • 1年前
    John Marabiles

    Evidence Of Evolution

    Evidence Of Evolution

    John Marabiles · 46問 · 1年前

    Evidence Of Evolution

    Evidence Of Evolution

    46問 • 1年前
    John Marabiles

    Traditional Materials

    Traditional Materials

    John Marabiles · 20問 · 1年前

    Traditional Materials

    Traditional Materials

    20問 • 1年前
    John Marabiles

    Crushing Strength Of Common Building Stones

    Crushing Strength Of Common Building Stones

    John Marabiles · 8問 · 1年前

    Crushing Strength Of Common Building Stones

    Crushing Strength Of Common Building Stones

    8問 • 1年前
    John Marabiles

    Properties Of Stones

    Properties Of Stones

    John Marabiles · 16問 · 1年前

    Properties Of Stones

    Properties Of Stones

    16問 • 1年前
    John Marabiles

    Requirements Of Good Building Stones:

    Requirements Of Good Building Stones:

    John Marabiles · 11問 · 1年前

    Requirements Of Good Building Stones:

    Requirements Of Good Building Stones:

    11問 • 1年前
    John Marabiles

    Tests On Stones

    Tests On Stones

    John Marabiles · 5問 · 1年前

    Tests On Stones

    Tests On Stones

    5問 • 1年前
    John Marabiles

    Structural Reading

    Structural Reading

    John Marabiles · 22問 · 1年前

    Structural Reading

    Structural Reading

    22問 • 1年前
    John Marabiles

    General Chemistry

    General Chemistry

    John Marabiles · 50問 · 1年前

    General Chemistry

    General Chemistry

    50問 • 1年前
    John Marabiles

    Lesson 1: Construction Sector

    Lesson 1: Construction Sector

    John Marabiles · 10問 · 1年前

    Lesson 1: Construction Sector

    Lesson 1: Construction Sector

    10問 • 1年前
    John Marabiles

    Lesson 2: Participating in Workplace Communication and Collaboration

    Lesson 2: Participating in Workplace Communication and Collaboration

    John Marabiles · 11問 · 1年前

    Lesson 2: Participating in Workplace Communication and Collaboration

    Lesson 2: Participating in Workplace Communication and Collaboration

    11問 • 1年前
    John Marabiles

    問題一覧

  • 1

    In construction scheduling, one of the most efficient method to use is ______

    critical path method

  • 2

    It is a three-phase procedure consisting of planning, scheduling, and time monitoring or controlling

    cpm

  • 3

    It involves the determination of what must be done, how it is performed, and the sequential order in which it will be carried out

    planning construction operations

  • 4

    It determines calendar dates for the start and completion of project components

    scheduling

  • 5

    It is the process of comparing actual job progress with the schedule

    time monitoring

  • 6

    The management techniques of CPM are based on graphical project model called a ______ This ______ presents in diagrammatic form those job activities that must be carried out and their mutual time dependencies

    network

  • 7

    Types of schedule compression:

    fast tracking , crashing

  • 8

    Shortening by working activities simultaneously with increased risk

    fast tracking

  • 9

    Shortening by adding resources for the least cost possible

    crashing

  • 10

    It is used to compute the duration of the project and estimating the needed manpower and materials

    cpm