記憶度
33問
78問
0問
0問
0問
アカウント登録して、解答結果を保存しよう
問題一覧
1
1057. What is the usual measure undertaken to stop a river for charging its path?
River training works
2
993. Is the most commonly used method in the design and evaluation of bituminous mixture.
Marshall Stability Method
3
1042. If the surface is sloping, where should the asphalt application start?
Low
4
933. Splicing for bottom bar of continuously reinforced concrete beam?
At the Support or Near at Support
5
192. Consist of the excavation of river, bottom of creeks or esteros and other bodies of Water.
Dredging
6
795. One of the controlling factors in the design of vertical alignment of road
Drainage System
7
794. Profile along the centerline of the bridges shall be extended beyond both ends of the bridge.
100 m
8
983. This will show work activities in accomplishing a project or a project component.
Pert/CPM and PDM Network
9
1055. Which of the following is not included in the exploration of foundation strata?
Nuclear Density Test
10
852. Longitudinal suface depression, in the wheel paths
Rutting
11
966. Time allocation for Mobilization and Demobilization for up to 5M estimated direct cost of project.
10 C.D
12
1032. The _______________ lateral safety buffer beside the work area that increase protection and safety for workers
Adjacent Clearance Area
13
772. Consist of furnishing, placing and finishing çoncrete in all structures accept pavements conforming to the lines, grade and dimension?
Structural Concrete
14
893. In absence of Beam Sample, what is the compressive strength if cylinder sample is used?
3500 psi
15
909. What is the maximum distance of the building main entrance to the elevator?
30 m
16
809. Tension induce the steel tendons by means of pulling, by hydraulic jack. The amount of tension is measured by the elongation of the steel tendons from a pre-determine point and is checked by a pressure gauge.
Tensioning of Tendons
17
959.______________prior to production, the contractor shall submit in writing a "job-mix formula".
3 weeks
18
977.What are true about Contraction Joint/Weakened Plane Joint, except?
Relieve Compression Stresses
19
815. Minimum thickness and covering for rubble concrete is
30 cm (12") and 5 cm (2") respectively
20
883. 4005 bags of cement supplied to your project, how many samples will you make?
3
21
804. Steel tendons should be grouted with an approved grout mixture after the completion of the stressing operation within
48hrs.
22
1034. In dredging works, what is the preferred side slope (vertical to horizontal ) between original bottom and the indicated dredging level of a clay materials.
1 to 4
23
978. What are true about Construction Joint/Cold Joint, except?
Use dowel bars (Deformed Bars)
24
950. In Removal of Structures and Obstructions - Pavement, Sidewalks, Curbs, etc. Shall be broken into pieces, the size of which shall not exceed_______in any dimension.
300 mm
25
830. Maximum spacing weep holes and their diameter
2 meters on center @ 2 inches dia
26
915. What is the minimum Doorway width under BP 344?
0.80 m
27
984.Use time lines and other symbols to illustrate scheduled completion of aproject.、
Bar Chart
28
898. How many meters is the Free Haul Distance?
600 m
29
857. Thickness determination for concrete and asphalt pavement.
D.0. No.55 Series of 1992
30
801. This increases the shearing strength of aggregates of any size, shape & gradation
Compaction
31
895. What DPWH Team evaluates the contractors rating?
CPES
32
1043. Responsible for logbooks, S -Curves'
Project Engineer
33
987. It is predicted/projected/correlated from cumulative monthly target accomplishment in percent along the duration of the project.
Cash Flow
34
812. National Building Code of the Philippines
P. D. 1096
35
779. An event oriented network analysis?
PERT
36
1056. What is the technical term for a bridge abutment that sits high up on the river bank?
Wing wall
37
848. Bowl shaped holes of various sizes in the pavement surface.
Potholes
38
939. What is the minimum RROW and Width of travel way (2 Lane) in Provincial Road?
15 m & 6.10 m
39
851. A form of plastic movement resulting in localized bulging of the pavement.
Shoving
40
777. Designed to spread the load from the bearing evenly over an area of ground
Base Plate
41
876. All doors for PWD shall have a minimum clear width of
0.90 meter
42
981. How much is the maximum Advance Payment?
15%
43
951. In Clearing and Grubbing, Clearing shall extend beyond the toe of the fill slopes or beyond rounding of cut slopes for the entire length and provided it is within the right of way limits of the project.
1.0 m
44
882. Bridge Span for Pre-cast?
13-30 m
45
845. An important consideration in sewer design.
Velocity of Flow
46
843. A purposeful control of all cost in every possible way, incurred on project arises from manpower, equipment, materials, contract cost overhead.
Cost Control
47
932. What is the Cement/Sand ratio to achieve 1000 psi of a concrete spacer use in foundation?
1:4
48
967. For DPWH projects Mobilization and Demobilization shall not exceed of the Estimated Direct Cost (EDC) of civil works items (as per D.0. 197, S. of 2016) with time duration as prescribed in D.0. 44, Series of 2012.
1%
49
838. Super plasticizers can reduce the water content by ______% ?
25 to 35%
50
816. Paint used for concrete pavement.
Thermoplastic Paint
51
891. S-Curve ahead of Schedule?
February 28
52
949. Trees that are selected for presevation must be protected, while trees that are needed to be cut/ball shall be identified by the
Project Engineer
53
872. Conduits and Pipes, with their fittings, embedded within a column shall not displaced more than_________ percent of the area of cross section.
4
54
975. The services of a certified first-aider when total number of workers is________or less.
50
55
992. In Item 310, the minimum dry compressive strength of mixture is ?
200 psi
56
957. Posts shall be set vertically and where embedded in a concrete foundation block, shall remain undisturbed for a minimum of
48 hrs.
57
776. Is a day work by one person?
Man-day
58
789. A road sign used to direct traffic along the road or towards a destination
Guide Sign
59
783. This represent periodic payment made by the owner to the contractor to commensurate the work accomplishment
Progress Payment
60
855. Cracks in asphalt concrete overlay surface that occur over joints in PCCP
Reflection Cracking
61
928. School building construction beside of the cliff, has minimum distance of
6 m
62
785. When reasons for project delays are clearly and solely attributed to the contractor
Rescind the Contract
63
784. This is the increase/decrease in quantities due to verification survey/as staked plans against the construction plans, not more than 25% of the original contract price
Change Order
64
854. The upward movements in an asphalt pavement resulting in the formation of a film of asphalt on the surface.
Bleeding
65
860. New standard worksheet and test procedure in conducting FDT
D.M.C. No. 46 Series of 1997
66
829. Minimum thickness for asphalt overlay is:
1 inch
67
1067. In the Memorandum Circular No. 38 dated 12 November 1981,. a certificate of Quality Control Assurance ( COCA ) should be accomplished.
Weekiy
68
924. What is the minimum width of a stair under BP 344?
0.70 m
69
802. The recommended thickness of Hot Mix Asphalt Overlay depending on the expected traffic and the modulus of the Cracked and Sealed pavement section
3" to 5"
70
808. A float used to smooth freshly placed concrete.
Bull Float
71
910. What is the minimum dimension of an elevator door width?
0.80 m
72
994. In Item 310, after final rolling, the degree of compaction should be checked. The compacted pavement shall have a density equal to, or greater than________of the laboratory composed density.
97
73
827. Flexural Strength requirement of concrete.
550 psi.
74
817. Paint used for asphalt pavement.
Reflectorized Paint
75
799. This shall be made of steel wire triple to form a uniform hexagonal mesh pattern
Gabions
76
790. What is the minimum sized of conduit in any system?
12.5 mm dia
77
900. Test for RSB, except?
Axial Stress
78
866. What is the minimum width of PWD ramp?
1.20m
79
814. Min imum number of days to remove forms in column
2 days
80
902. Repainting of steel bridge is an activity under:
Periodic Maintenance
81
961. Tiles shall have been laid in place for at least
24 hrs.
82
901. Sampling of the freshly mixed concrete should be taken on the _____________batch discharge of the transit mixer?
Middle
83
997. In conducting Slump Test, how many stroke per layer?
25
84
911. What is the minimum size of an elevator car?
1.10 mx1.40 m
85
943. It is constructed along the side of the roadway to stabilize the slopes either above or below the elevation of the roadway.
Slope Protection Structures
86
822. The system of pre-stressing wherein the steel tendons are tensioned after the concrete has been placed and has attained a specific strength.
Post Tensioning
87
798. The minimum depth of CHB wall footing or other minor structures on the ground
700 mm
88
906. What is the minimum dimension of a PWD Toilet?
1.70 m
89
929. School building construction beside of the power lines, has minimum distance of
20 m
90
1033. Termination area is the area where traffic resumes normal operations after the worksite. The following are the signs that would be located in this area, as applicable, except:
Prepare to stop (T1-18 )
91
968. Time allocation for Mobilization and Demobilization for 100 M to 150M estimated direct cost of project.
30 C.D
92
908. What is the minimum width for a hallway?
1.20 m
93
941. Refer to roads linking the agriculture and fisheries production sites, coastal landing points and post-harvest facilities to the market and arterial roads and highways.
Farm to Market Road
94
877. Soil Poisoning shall be applied_________laying the beddings or lean concrete.
Before
95
913. Minimum door opening for elevators for a single door?
0.80 m
96
1051.To attain a uniform consistency of concrete during the pouring operation of a concrete pavement, the slump should not be more than
40mm
97
793. This was placed on the edges of landing for the purpose of preventing the vessels or ship from getting direct contact with the pier.
Timber Walling
98
840. Admixtures which help incorporate a controlled amount of air in the form of minute bubbles in concrete during mixing, without significantly altering the setting or rate of hardening characteristic of concrete
Air Entraining Admixtures
99
861. The minimum index of retained strength of asphalt ?
70
100
1066. The moisture density relation test determines the.
Maximum dry density