PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Road, Bridge and Flood Control Projects 100M up to 150M
45 days
2
747. Minimum shoulder width?
1.0 Meter
3
764. Maximum value of e: (Super elevation) in Downtown Arterial?
6%
4
Minimum calendar days ( Earliest Possible Time ) for Consulting Services
34 CD
5
766. Minimum Diameter of storm pipes?
18"
6
755. What is the density of Bentonite to 1 cu.m. of water?
30 - 100 kilos/cu.m.
7
740. The procurement process from the opening of bids up to the award of contract shall not exceed:
3 months
8
744. Minimum width of paved sidewalk?
1.5 Meter
9
770. Minimum time needed on the removal of forms for beams, girders, frames or arches
14 days or 80% of design Strength
10
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Bridge Projects Above 200M
75 days
11
735. Which of the following scheduling features does not describe the bar chart?
ldentifies activity relationship
12
CONSTRUCTION OF STONE MASONRY FOR CATCH BASIN/HEADWALLS OF CULVERTS SHALL BE IN CONFORMITY WITH THE LINES, GRADES, SECTIONS AND DIMENSIONS SHOWN ON THE PLANS OR AS ORDERED IN WRITING BY THE PROJECT ENGINEER. THE STONE SHALL BE CLEAN, HARD AND DURABLE AND SHALL BE SUBJECT FOR ENGINEERS APPROVAL. THE STONES SHALL HAVE A THICKNESS NOT LESS THAN _____ MM. AND WIDTH OF NOT LESS THAN _____ TIMES THEIR RESPECTIVE THICKNESS AND LENGTHS OF NOT LESS THAN ______ TIMES THEIR RESPECTIVE WIDTHS.
150mm ,1/2 & 1 1/2
13
762. Maximum value of e: (Super elevation) in Rural Highway?
10%
14
743. The Plasticity Index requirement for Aggregate Base Course should not be greater than:
6
15
761. A 3 dimensional view of the road
Sight Distance
16
717. What do you call the limit of drainage of a river system?
Drainage area
17
745. Guardrails spacing?
3.81 meters
18
Livestreaming of DPWH Procurement Activities from Facebook Pages to YouTube Channels
Department Order No. 6, series of 2024
19
731. Rock used in gabions shall consists of hard, durable rock pieces that will not deteriorate when submerged in water or exposed to severe weather condition, and should be uniformly graded in sizes ranging from:
101 mm to 200 mm
20
757. A kind of drilling using a combination of steel casing and stabilizing mud. A temporary casing is penetrated up to an extractable length of not more than 3.0 meters
Protected Drilling
21
724. If 95% of a soil passes the No. 200 mm sieve, its particle size distribution is best determined by:
c. Hydrometer Analysis
22
The Contractor or its duly authorized representative shall have the right to suspend work operation on any or all projects/activities along the critical path of activities after fifteen (15) calendar days from date of receipt of written notice from the Contractor to the district engineer/regional director/consultant or equivalent official, as the case may be, on any of the following grounds:
f. All of the above
23
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Road, Bridges and Flood Control Projects Below 50M
15 days
24
725.In tem 200ーAggregate Subbase Course, the fraction passing the 0.425 mm (No. 40) sieve should have a liquid limit not greater than:
35 %
25
729. What class of structural concrete is generally used for reinforced sections, railings, pre-cast piles, cribbing and for filler in steel grid floors?
Class C
26
749. When the outside diameter of unfilled tubular pile is less than 355 mm, what is the required minimum thickness of the wall
6.5 mm
27
751. The minimum interval of concrete pouring to avoid cold joint
30 minutes
28
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Building 50M up to 100M
25 days
29
752. Required revolution of concrete mixer
4 - 6 RPM
30
754. Must be within the limit of water cement ratio for concrete
0.50 -0.60
31
720. When the average thickness of the concrete pavement per lot is deficient by 5 mm, payment for the lot should be:
100 %
32
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Road, Bridge and Flood Control Projects 50M up to 100M
30 days
33
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Building Projects 150M up to 200M
45 days
34
769. Undertaken on the highway with a cycle span of 1-5 years such as re-scaling bituminous pavement, bridge re-decking, re-gravelling, etc
Periodic Maintenance
35
Maximum calendar days ( Procurement Latest Allowable Time ) for Consulting Services
170 CD
36
722. Clay can be made plastic by:
adjusting its water content
37
765. Drainage is an extremely important element of good highway development
Sidewalk Design
38
760. Admixtures used to speed up the initial set of concrete
Accelerator
39
726. A rehabilitation of asphalt pavement is undertaken by a District Office. Per approved program of work, Item 201 was included in the pay items. However, during construction, the Materials Engineer certified that the existing base course material is still of good quality. As project/resident engineer, what is the best recommendation?
c. Deduct from payment due to the contractor the corresponding amount equivalent to the total volume of Item 201 that was not incorporated into the works
40
756. A type of drilling without the use of steel casing or stabilizing mud
Unprotected Drilling
41
Minimum calendar days ( Procurement Earliest Possible Time ) for Goods
28 CD
42
STONE MASONRY, THE FINISH FOR EXPOSED FACE STONES SHALL BE PITCHED TO THE LINE ALONG THE BEDS AND JOINTS. THE MAXIMUM PROJECTION OF ROCK FACES BEYOND THE PITCH LINES SHALL BE MORE THAN _____ MM.
50 mm
43
Maximum calendar days ( Procurement Latest Allowable Time ) for Infrastructure Projects for ABC above 50M
144 CD
44
768. Only undertaken when routine and periodic maintenance have been satisfied and there are still balance on the appropriation. Activities are slope protection, installation of guardrail
Special Maintenance
45
771. Minimum separation of splices when staggered?
40 bar dia.
46
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Road Projects Above 200M
90 days
47
718. What do you call the total covering area of a river system?
River basin
48
716. Which of the following is not a result of river mouth inmprovement works?
Fast river bed deposition
49
723. Ordinarily, what is the absolute volume of cement in a concrete mix?
7 to 14 percent
50
750. Part of the bridge which support the load of the extreme spans and retain the approach fill
Abutment
51
753. The minimum spacing of steel bars on bored piles to ensure that concrete would still flow outwards to the walls of the bored piles
100 mm
52
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Building Projects Above 200M
60 days
53
K63. Maximum value of e: (Super elevation) in Urban?
8%
54
Minimum calendar days ( Earliest Possible Time ) for Infrastructure Projects
28 CD
55
A32. In laying the stone components of Item 506 (Stone Masonry), the exposed faces of the individual stones should be:
Parallel to the faces of the walls
56
739. The best aid in locating and identifying areas of discussion in an inspection report are:
Photographs
57
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Flood Control Projects Above 200M
90 days
58
767. Drainage structures which collect run-off from curb and gutter and convey it to the underground corners or culvert
Inlets
59
719. Which of the following factors does not affect the stability of an embankment?
Wind load
60
741. A variation orders may be in the form of the following except:
Supplemental Agreement
61
748. The main objective of this design is to determine the proportion of the ingredients that will produce concrete of the proper workability when fresh and the desired stability and strength after it has hardened.
Design of Concrete Mix
62
Maximum calendar days ( Procurement Latest Allowable Time ) for Infrastructure Projects for ABC 50M and below
113 CD
63
746. The specimen for thickness determination shall have a diameter of:
4"
64
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Building Projects 100M up to 150M
35 days
65
758. When concrete pipe cast in-place formed by first removing the soil by drilling and filling the void by concrete
Bored Pile
66
Zi59. New type of water reducing admixtures that are used to produce flowing concrete
Super Plasticizers
67
PREPARATION AND SUBMISSION OF "AS-STAKED" PLAN (Time Duration in Calendar Days) Road, Bridge and Flood Control Projects 150M up to 200M
60 days
68
Maximum calendar days ( Procurement Latest Allowable Time ) for Goods
124 CD
69
737. Which of the following is the main purpose of the first advance payment to a contractor?
mobilization costs