  • 1

    1. This is the Department Order for the Standard Specification for Public Works and Highways, 2004 Edition, Volume Il for Highways, Bridges and Airports. What is this?

    Department Order No. 24, Series of 2005

  • 2

    2. The Contractor shall provide and maintain field offices and testing laboratories, including all the necessary logistics and facilities for the use of the Engineer and his staff. The offices and laboratories shall have at least the floor area prescribed on the Plans and shall contain the equipment, supplies and furnishings specified in the Contract. Testing equipment supplied in accordance with the Special Provisions shall be located in testing laboratories as required by the Engineer. What are these logistics?

    Electricity, water, drainage and telephone services

  • 3

    3. In the Section A.1.2 Vehicles for the Engineer The Contractor shall provide within ______ calendar days after notice to commence work, the vehicles listed in the Special Provisions for the exclusive use of the Engineer. The vehicles to be provided by the Contractor shall be to the satisfaction of the Engineer. All vehicles shall comply in all respects with all relevant Philippine national or local laws statutes and regulations. All vehicles shall carry or be fitted with the accessories as may be prescribed by laws and have comprehensive insurance. The vehicles on delivery shall be new and shall be driven by a competent qualified and experienced driver who shall be under the direct order of the Engineer. What is the prescribed calendar days?

    30 days

  • 4

    4. In ITEM 100-CLEARING AND GRUBBING - 100.1 Description This item shall consist of various aspects as designated in the Contract, except those objects that are designated to remain in place or are to be removed in consonance with other provisions of this Specification. The work shall also include the preservation from injury or defacement of all objects designated to remain. What are these items ?

    Clearing, grubbing, removing and disposing all vegetation and debris

  • 5

    5. In 100.2.2 Clearing and Grubbing - All surface objects and all trees, stumps, roots and other protruding obstructions, not designated to remain, shall be cleared and/or grubbed, including mowing as required, except as provided below: (1) Removal of undisturbed stumps and roots and nonperishable solid objects with a minimum depth of one (1) meter below subgrade or slope of embankment will not be required. (2) In areas outside of the grading limits of cut and embankment areas, stumps and nonperishable solid objects shall be cut off not more than 150 mm (6 inches) above the ground line or low water level. (3) In areas to be rounded at the top of cut slopes, stumps shall be cut off flush with or below the surface of the final slope line. (4) Grubbing of pits, channel changes and ditches will be required only to the depth necessitated by the proposed excavation within such areas.

    All of the statements are required

  • 6

    6. In Section 100.3 Method of Measurement, the following Alternate Methods can be utilized, except:

    Collective Basis

  • 7

    7. In Section 100.4 Basis of Payment, pay item number 100 (1) for clearing and grubbing - unit of measurement w川 be:

    Hectare

  • 8

    8. In the 102.2.7 Excavation of Roadbed Level Rock shall be excavated to a depth of ________ below subgrade within the limits of the roadbed, and the excavation backfilled with material designated on the Plans or approved by the Engineer and compacted to the required density. When excavation methods employed by the Contractor leave undrained pockets in the rock surface, the Contractor shall at his own expense, properly drain such depressions or when permitted by the Engineer fill the depressions with approved impermeable material. Material below subgrade, other than solid rock shall be thoroughly scarified to a depth of ______ and the moisture content increased or reduced, as necessary, to bring the material throughout this 150 mm layer to the moisture content suitable for maximum compaction. This layer shall then be compacted in accordance with Subsection 104.3.3

    150 mm

  • 9

    9. This is the Department Order for the Guidelines and Criteria for the Design Audit of DPWH Regional and District Engineering Offices 2022 Edition. What is this?

    Department Order No. 82, series 2022

  • 10

    10. In the aforementioned DO, in the pursuit and in order to attain efficiency in the preparation of architectural and engineering plans, and to enhance the capability and further improve the performance of Regional and District Engineering Offices in the delivery of infrastructure projects in terms of cost, time, function, and design life, by incorporating consistency and accuracy in addition to completeness of plan, the proposed Guidelines hereto attached is hereby issued for the regular design audit of DPWH Implementing Offices. What are these terms?

    Cost, time, function, and design life

  • 11

    11. Who is the Overall coordinator in the conduct of Design Audit?

    Design Audit Committee (DAC)

  • 12

    12. The DPWH as the engineering arm of the government is tasked to continuously develop its technology for the purpose of ensuring the safety of all infrastructure facilities and securing all public works and highways with the highest efficiency and quality of construction. This Bureau as the leading support group in providing quality infrastructure through sound engineering design, developed the Design Audit (DA) that covers the evaluation of detailed architectural and engineering design works and processes undertaken in the said offices. What is this Bureau?

    Bureau of Design

  • 13

    13. The main objectives of the design audit are as follows. Select the best answer. 1. To ensure compliance of the design plans prepared by the Planning and Design Division/Section with the standards set by the Department; 2. To identify areas where the design process could be strengthened and improved; and 3. To establish a comparative design performance rating of ROS and DEOS.

    Statements 1, 2 and 3

  • 14

    14. In the areas of assessment for the design audit, in the area of design management - this refers to the Checking on number, appropriateness and ideal ratio of engineering tools (computer hardware/software, references, survey equipment, etc.) to the number of design personnel involved in the actual execution of particular design works. What is this?

    Availability of Design Tools and Software

  • 15

    15. According to this Department Order, or the REVISED CRITERIA FOR RATING OF QUALITY ASSURANCE IN PROJECT IMPLEMENTATION, the Bureau of Quality and Safety (BOS) shall conduct annually the appraisal of quality assurance performance of all Regional/District and Project Management Offices. What is this DO?

    Department Order 102 Series 2016

  • 16

    16. The REVISED CRITERIA FOR RATING OF QUALITY ASSURANCE IN PROJECT IMPLEMENTATION has three (3) responsibility Area Criteria with corresponding weight. What is the correct weight in each criterion?

    Effectiveness of Quality Assurance Implementation 70% |Project Supervision 10% | Laboratory Management 20%

  • 17

    17. REVISED CRITERIA FOR RATING OF QUALITY ASSURANCE IN PROJECT IMPLEMENTATION has the following criteria except:

    The Overall Accumulated Points (OAP) of each Region shall be the median of the total points earned by the Regional Office and the District Offices.

  • 18

    18. In the REVISED CRITERIA FOR RATING OF QUALITY ASSURANCE IN PROJECT IMPLEMENTATION the following documents shall be evaluated and used as bases for rating this parameter. Which does not belong?

    OPCR

  • 19

    19. The ability to implement quality assurance policies (10%, to effect quality control compliance, the DPWH regularly formulates policies through memorandum circulars, department orders and other administrative issuances. These are in addition to other quality assurance policies stipulated in the standard specifications, general conditions, specific provisions and other related documents relative to the project. While all these policies are important, the Bureau of Quality and Safety (BQS) chose eight (8) of the most important ones that should be checked in the field considering time constraints and volume of projects to be appraised. However, other policies observed violated in the field and causing problems in the project implementation shall be considered in the rating. The eight (8) policies are contained in the following issuances, to wit; however which does not belong?

    M.0. No. 100, series of 1978, Accomplishment of Quality Control Logbook

  • 20

    20. This sets forth the Comprehensive Policy Guidelines on the Maintenance of National Roads and Bridges. What is the Department Oder?

    Department Oder No. 189 Series 2022