暗記メーカー
ログイン
4 DE promotional Exam
  • denis cagomoc

  • 問題数 86 • 1/13/2024

    記憶度

    完璧

    12

    覚えた

    32

    うろ覚え

    0

    苦手

    0

    未解答

    0

    アカウント登録して、解答結果を保存しよう

    問題一覧

  • 1

    The Contractor shall deliver a notice to the Implementing Office giving full and detailed particulars of any extra cost, within X calendar days after such work has been commenced pursuant to Item 3.2 Annex E of the Revised IRR;, or, within Y_calendar days after the circumstances or reasons justifying a claim for extra cost shall have occurred. What is the value of X and Y?

    X= 7 and Y = 28

  • 2

    Based on the Standard Form for Itemized Cost of Revised, the signatory to the Verification as to Unit Cost and as to Quantity for projects implemented by the District Engineering office are the _________________ respectively.

    Chief of Construction, Chief of Planning and Design

  • 3

    In justifying the need for Extra Work Order, the Implementing Office shall establish that such need is necessary for any of the following conditions, EXCEPT;

    For the utilization of the savings of the project

  • 4

    Which of the foliowing department policies prescribes the Procedural Flow and Timeline in Processing of Blackiisting of Contractors for Locally-Funded and Foreign-Assisted Infrastructure Projects during Implementation Stage?

    Department Order No. 171, series of 2022

  • 5

    Who among the following is the authorized approving DPWH offcial in Terminating Contracts fror Locally-Funded and Foreign-Assisted Projects?

    Head of Implementng Offce

  • 6

    Identify the missing procedure for contract termination: Verification > Notice to Terminate >___________> Decision

    Show Cause

  • 7

    After the effectivity of contract termination for default, within how many days shall the Head of the Agency issue the Blacklisting Order of the contractor?

    7 calendar days

  • 8

    After the Head of Implementing Office approves the Contract Termination (Executive Summary), what document shall be fomarded to the contractor immediately?

    Notice of Decision to Terminate Contract

  • 9

    Which of the following department policies which prescribes the Guidelines and Procedures for all Price Escalation and Extraordinary Contract-Related Claims Manual?

    Department Order No, 60, serles of 2017

  • 10

    Which of the following shall be satisfled In order to grant a request for Price Escalation?

    Legal Parameters and Technical Parameters

  • 11

    Which of the following statementis CORRECT?

    The total retention money shall be due for release upon final acceptarnce ot the works.

  • 12

    Which of the following statement is CORRECT?

    For road projects with 10 kilometers or more, additional bill board shall also be installed at every 5-kilometer interval.

  • 13

    Which of the following statement is INCORRECT?

    In case the total sum of liquidated damages reaches 10% of the total contract price, the Procuring Entity has the option to allow the contractor to continue the works with prejudice to the continued imposition of liquidated damages until the works have been completed.

  • 14

    Which of the following statement is CORRECT?

    The recommended duration for the preparation and submission of As-Staked Plan incudes, conduct of "As-Staked" survey and geotechnical investigation.

  • 15

    The Warranty Security can be in a form of Surety Bond callable upon demand in an amount equivalent to_______________________.

    30% of the total contract price

  • 16

    What is the validity period of the Performance Security?

    Until acceptance of the project

  • 17

    Which of the following report is being prepared by the Proiect Engineer and Materiais Engineer as an attestation that the materials and works correspond to the quantity accomplished and conform to the approved plans and specifications?

    Certificate of Qualty Control Assurance (CQCA)

  • 18

    In accordance with Department Order No. 21. s. of 2010. Materials Ouality Control Reports of District Engineering Offices shall be submitted to which of the following office?

    Regional Office

  • 19

    In accordance with Department Order No, 85, s. of 2019, this document shall be issued by the concerned implementing office as a last resort when availing the service of accredited private testing laboratories ?

    Waiver

  • 20

    Which document is being prepared by the Contractor and approved by the Project and Materials Engineers of the Implementing Office to ensure that the minimum testing requirements for each item of work are being complied with?

    Quality Control Program

  • 21

    Which of the following is a legally executed agreement between the contractor and the government for the performance of the works covered by the contract?

    Contract Documents

  • 22

    Every material should be subjected to testing, inspection and verification before_________________.

    Acceptance

  • 23

    In accordance with Department Order No 97,S. 2022, all DPWH Star-Rated Laboratory shall have at least how many certifed DPWH Laboratory Technician in order to maintain their Star Rating?

    One (1)

  • 24

    Which of the following specifies,the kind and number of tests for each pay item of works?

    Minimum Testing Requirements

  • 25

    Which of the following department issuances aims to strengthen the Quality Assurance Program of the Department and to ensure that only qualified and competent Materials Engineers shall be assigned in the implementation of DPWH projects?

    Department Order No. 12, series of 2013

  • 26

    Which of the following work elements carried out by the manager or by those in the organization contributes to the quality of the output?

    Quality Control Work

  • 27

    If the soil to be used as Item 200 - Subbase Course fails to meet grading requirement, what should be the best measure to be done?

    Blend the material with either finer or Coarser material

  • 28

    Which of the following laboratory tests in geotechnical engineering is used to evaluate the mechanical strength and load-bearing capacity of subgrade soils and base course materials for pavement design?

    California Bearing Ratio (CBR) Test

  • 29

    Which of the following tests determines the right amount of mixing water in compacting a soil fill in order to obtain the maximum density under the applied energy?

    Moisture Density Relation

  • 30

    What type of an asohalt mxture is designed to have a large volume of air voids (typicaly18% to 229) so that water will readily drain through the pavement layer and used to provide a skid-resistant pavement surface and as a porous base layer to provide for positive drainage under either Asphalt or Portland cement concrete pavement surface?

    Open-Graded Asphalt Mixes

  • 31

    Concrete in the area represented by the cores will be considered adequate if the average strength of the cores is equal to atleast what value?

    85% of specified strength, and if no single core is less than 75% of specified strength

  • 32

    If the strength of control specimens does not meet the reauirements, and it is not feasible or not advisable to obtain cores from the structure due to structural considerations, what is the best action that should be done?

    payment will be made at an adjusted price due to strength defciency of specimens

  • 33

    The completed pavement shall be accepted on a lot basis. A lot shall be considered as?

    1000 linear meters of pavement when a single traffic lane is poured or 500 linear meters when two lanes are poured concurrently.

  • 34

    If no core samples were taken during the day's operation, core samples shall be taken from the completed pavement for every___________.

    100 L. M. per lane

  • 35

    Based on ASTM E-950, what is the required longitudinal sampling for a Class 1 Profiling Device?

    less than or equal to 25 mm (1 in.)

  • 36

    Based on ASTM E-950, what is the required vertical measurement resolution for a Class 1 Profiling Device?

    less than or equal to 0.1 mm (0.005 in.)

  • 37

    As per Department Order No. 21, series of 2019, what percentage of the Item Cost is allowed for the payment for concrete pavement with an International Roughness Index (1RR) value of 6.31 m/km?

    Fifty percent (50%)

  • 38

    Intermational Roughness Index (IRI) measurement for acceptance for projects constructed along what type of road?

    Natonal primary road

  • 39

    Which of the following issuances directs the adoption of the Cash Budgeting System in the beginning of FY 2019?

    ExecUtive Order No. 91

  • 40

    Which of the following is a set of detailed rules to that covers the processes and practices that shall be utilized in a specific construction proiect site in conformity with the Occupational Safety and Health Standards (OSHS)?

    Construction Safety and Health Program

  • 41

    Which of the folowing is NOT a compensable property?

    Water Utility

  • 42

    What provisions in the 1987 Philippine Constitution limit the Government's exercise of the Power of Eminent Domain? I. Section 1. No person shall be deprived of life, liberty, or property without due process of law II. Section 7. The right of the people to information on matters of public concern shall be recognized III、Secion 9. Privete property shall not be taken for public use without just compensation.

    I and III only

  • 43

    It is considered as the means of last resort of ROW acquisition usually undertaken when negotiation has falled or is not feasible.

    Expropriation

  • 44

    What shouid be done if the Writ of Possession (WOP) Is NOT İssued within 7 days?

    Seek from the court immedlate Issuance of the WOP

  • 45

    Upon the execution of a deed of sale, the Implementing Agency (IA) shall pay the property owner by how many initial percentage of the negotiated price of the affected crops and trees?

    Seventy percent (70%)

  • 46

    Which of the following notice issued by the Procuring Entity (PE) to prospective bidders with respect to any clarification or modifications in the bidding documents, including those affecting the technical specifications, procurement schedules, contract requirements and other similar matters?

    Supplemental Bid Bulletin

  • 47

    What is the maximum allowable period for the procurement of consulting services pursuant to 2016 Revised IRR of RA 9184?

    180 calendar days

  • 48

    What is the lowest possible weight/percentage of financial proposal based on 2016 Revised IRR of RA9184?

    Fifteen percent (15%)

  • 49

    Which of the following process verifies whether the bidder with the Highest Rated Bid (HRB) complies with and is responsive to all the requirement of eligibility bidding?

    Post-Qualification

  • 50

    Which of the foliowing is a method of evaluating proposals for consulting services based on both the quality of the proposals and the cost of the services offered?

    Quality-Cost Based Evaluation

  • 51

    Which of the following is a method of procurement of goods that involves direct invitation to bid by the Procuring Entity from the list of pre-selected supplyers with known experience and proven capability to perform the contract?

    Limited Source Bidding

  • 52

    What is the maximum allowable percentage of the quantity of each item in the original contract under repeat orders?

    Twenty-five percent (25%)

  • 53

    The timeframe for the processing of Variation Orders from the preparation up to the approval by the Head of Implementing Office concerned shalI NOT exceed___________________.

    30 calendar days

  • 54

    Which of the following department policy provides the guidelines for the Approval of Work Suspension Order, Work Resumption Order, and Contract Time Extension for Civil Works?

    Department Order No, 42, series of 2020

  • 55

    Who delegates the authority to approve request for Work Resumption Order?

    Head of Implementing Office

  • 56

    Under D.O. 42 Series of 2020, the District Engineer has the authority to approve the following documents, EXCEPT:

    Continuance of Work Suspension Order

  • 57

    Who among the following shall approve the Monthly Time Suspension Report (MTSR)?

    Head of Implementing Office

  • 58

    Which of the following is the proper timeframe that needs to be complied by the Contractor in requesting for Contract Time Extension?

    Prior or before expiry date and within thirty (30) calendar days after such work has been commenced or after the circumstances leading to such claim have arisen

  • 59

    Which of the following department policies prescribes as the Guidelines and Procedures in Terminating Contracts Due to the Fault of the Contractor for Locally Funded Infrastructure Projects?

    Department Order No. 90, series of 2020

  • 60

    Which of the following statement is CORRECT?

    As-staked survey/ site layout suvey is an activity necessary to verify the actual field condition and to identify modifications and other deviations in the project.

  • 61

    Which of the following statements about "As-Bult" plans is FALSE?

    As-built plans have a certification in the cover sheet stating that all material testing requirements were undertaken and that all materials used complied with the required specification, signed by the DPWH Project Engineer.

  • 62

    In the process of issuance of Certificate of Completion, within how many days is the contractor is advised to complete the works under the issued Notice of Defects/Deficiencies?

    Thirty (30) days

  • 63

    In accordance with Department Order No. 11, series of 2021, which of the following is NOT a requirement for the processing of Final Billing?

    Certification that necessary scheduled equipment for the first two months were mobilized after issuance of Notice to Proceed (NTP) with geotagged pictures

  • 64

    What is the calibrated action for an on-going project accumulating a negative slippage of 5%?

    The contrator shall be qiven a warning and required to submit a detailed "catch-up'" program on a fortnightly basis

  • 65

    Which of the following statement is CORRECT?

    None of the above

  • 66

    Which of the following statement is CORRECT?

    None of the above

  • 67

    Based on the limits of assignment as stated in Department Order No. 95, series of 2021, what is the cost limit assignment for an accredited Project Engineer III in the District Engineering Office?

    Maximum of eighteen (18) Projects implemented simultaneously, each proiect costing 250 million Pesos and below

  • 68

    What is the highest STAR rating that can be given to DPWH Laboratories based on Department Order No. 126, series ef 2016?

    Three Star

  • 69

    What is the acceptable International Roughness Index (IRI) Value for completed concrete and asphalt projects along National Primary Roads as per Department Order No. 21, Series of 2019?

    3.0 m/km

  • 70

    Which of the following refers to the responsibility/obligation of DPWH to ensure strict compliance to existing standards/specifications and other pertinent DPWH Issuances relative to project implementation?

    Quality Assurance

  • 71

    In accordance with Department Order No. 102, S. of 2016, which of the following office is concerned in the conduct of annual appraisal of quality assurance performance of all Regional/District and Project Management Office?

    Bureau of Research and Standards

  • 72

    Which of the following provides the overall view of the works to be done or accomplished during the implementation of the project and helps in the evaluation of the stability and quality of the projects?

    Project Documents

  • 73

    In accordance with Department Order No. 99, series of 2015, the Certificate of Completion shall be issued by the________________.

    Head of Implementing Office

  • 74

    Due to the limited facilities and manpower in the Regional and District laboratories as against the number of projects which will require the testing of materials, which of the following department issuances was issued authorizing Private TestingLaboratories (PTLS) undertake materials testinq for and in behalf of the DPWH?

    Department Order No. 100, series of 2018

  • 75

    In accordance with Department Order No. 126, series of 2016, which of the following is the required laboratory to comply with the provision for laboratory space in District Materials Testing space of Two-Star Rating Category?

    60- 81 sg. m.

  • 76

    Which of the following number of Accredited Materials Engineer/s is/are required for Two-Star Rated District Materials Testing Laboratories in accordance with Department Order No, 126, series of 2016?

    At least one (2) Material Engineers

  • 77

    As per Item 900.3.9 of DPWH Standard Specifcations for Public Works Structures, in the mixing of concrete, volumetric measurement shall be used only if by weight batching plant is located _________________travel from the project site.

    More than one (1) hour

  • 78

    Which of the following is the minimum thickness of Portland Cement Concrete Pavement (PCCP) in all Arterial and Secondary National Roads and Access Roads Leading to Ports as per Department Order No.40, Series of 2014?

    280 mm

  • 79

    Which of the following joint constructed is used when there is an interruption of more than 30 minutes in the concreting operations?

    Construction Joint

  • 80

    When the average thickness of the pavement per lot is more than 25mm, the payment for the lot shall be adjusted to_______________.

    No payment or remove and replace

  • 81

    Concrete mix that is NOT within the specified slump limits at the time of placement shall____________________.

    Not be used

  • 82

    What method is used in determining the strength of concrete pipes?

    Three-edged bearing method

  • 83

    Which of the following favorably alters oxidation kinetics and interacts with products of oxidation to reduce their deleterious effects that alters the plastic properties of clay fines, improves moisture stability and durability, andincreases pavement life and performance through mutiple mechanisms?

    Hydrated Lime

  • 84

    31. Based on the Project Fact sheet, what type of Environmental Impact Assessment report will the proponent prepare in line with DENR EMB MC 005-2014?

    Environmental Impact Statement (EIS)

  • 85

    29. Based from the MCA above, which is the BEST alignment option?

    Alignment option 2

  • 86

    30. The DPWH will propose the Bataan-Cavite Interlink Bridge (BCIB), which will connect the provinces of Cavite and Bataan. It will be a four-lane, median-separated roadway with a total length of 32.15 km, of which 26 km will be over the waters of Manila Bay. The BCIB will connect to the Roman Superhighway at an interchange in Mariveles, Bataan, and to the Antero Soriano Highway at an interchange in Nalc, Cavite. Based on the revised guideline coverage screening and standardized requirements of the Philippine EIS System (DENR-EMB MC 005-2014), what type of EIA category does the project below fall into?

    Category A- Environmentally Critical Projects (ECP)