    問題一覧

  • 1

    which of the ff reasons does not apply as to when the DPWH is authorized the full or partial suspension of work?

    due to ordinary unfavorable weather condition

  • 2

    period of time as to when the contractor or its duly authorized representative is allowed to suspend the work operation on any or all project/activities along the critical path?

    15 cal. days from the date of written notice from the contractor to the DE/RD/consultant or equivalent official

  • 3

    per IRR of RA 9184, suspension of work by the contractor due to delay in progress billing is being authorized for this period under conditions that a written notice from the contractor to the DE/RD/consultant or equivalent official suspending all projects/activities along the critical path and the delay in payment of contractors claim dor progress is being certified to be complete

    45 days

  • 4

    normally, contract time extension is not allowed in one of the following:

    suspension of work along the parallel activities

  • 5

    the event/period in the contract duration when the contractor shall be allowed to adjust the contract time accordingly

    in case of total suspension of activities along the critical path which is not due to the fault of the contractor

  • 6

    what should be done to detect and react appropriately to deviations and changes in plans?

    monitoring

  • 7

    what are the triple constraints that should be controlled?

    time,cost,performance

  • 8

    what is the calibrated action for an on-going proj accumulating a negative slippage of 5%?

    none of the above

  • 9

    ____ serves as the project engineers daily diary.

    construction project logbook

  • 10

    what should be issued in case the contractor is observed to be non-compliant with the contract specifications?

    site instruction-for non-compliance with contract specifications

  • 11

    a document done to keep a written record of the important discussion during meetings

    minutes of meeting

  • 12

    what is/are the basic indicator/s depicting the necessity for project control?

    more resources or less have been used than planned. Activities are taking longer than planned

  • 13

    PCMA stands for ___

    project and contract management application

  • 14

    the construction sched that will give the user information on the inter-relationships of work activities and sub-project groupings is the ____

    pert/cpm network diagram

  • 15

    for purposes of analyzing individual item accomplishment, the best construction sched to view is ____

    none of the above

  • 16

    it means the number of calendar days the project should be completed at prescribed schedule, defined by logic, sequence and duration of activities.

    contract time

  • 17

    illogical accomplishment means ____

    accomplishment done ahead of its predecessor

  • 18

    Given the S-Curve, what is the reason for the revision? See Figure 1

    Variation Order with Time Extension

  • 19

    What is the percent weight distribution in a Normal S-Curve?

    25-50-25

  • 20

    What does the acronym PERT/CPM stand for?

    Program Evaluation Review Technique/Critical Path Method

  • 21

    Who will prepare the complete set of the Construction Schedules prior to the signing of the Contract?

    Contractor

  • 22

    According to Annex "A" of the Revised IRR of RA the program of work shall include, among other things, estimates of work, items, quantities and costs and a PERT/CPM network of the project activities.

    9184

  • 23

    It is the amount of time a scheduled activity may either be delayed or extended from its early start date without delaying the project finish date.

    Float

  • 24

    Which of the following is NOT a use of Construction Schedules in DPWH projects?

    Basis for Billings

  • 25

    Complete the Forward Pass. Duration of Activity C is 30. See Figure 3.

    20 and 50

  • 26

    Complete the Backward Pass. Duration of F is 20. See Figure 4.

    50 and 70

  • 27

    ____ is one of the primary reaponsibilities of the proj inspectors under the supervision of the PE. this includes the measurement of the area, thickness, width and/or other measurements.

    quantity control

  • 28

    which type of chart ia used by the PE to ensure that the contractor is maintaining the min. number of equipment required/commited to the proj?

    equipment utilization schedule

  • 29

    what is the limit of assignment for Regional office PE3 based on DO 95 s. 2021

    5 proj costing above 250m and 15 proj costing 250m and below

  • 30

    the PE shall require the contractor to submit ___ of all permanent works that have been executed under the contract.

    as built plan

  • 31

    once the proj reaches an accomplishment of ___ % the PE shall facilitate the conduct of a pre-final inspection with the contractor

    95%

  • 32

    as applied to various atages of proj implementation is viewed and considered as the contractors responsibility

    quality control

  • 33

    give the overall view of the works to be done or accomplished during the implementation of the proj. these documents also help in the evaluation of the stability and quality of the projs.

    project documents

  • 34

    this doc is a written instruction in a form of memorandum/letter pertaining to the noted discrepancies in project implementation

    site instruction

  • 35

    based on the limits of assignments as stated in DO 95 S. 2021, what is the cost limit assignment for an accredited junior PE - UPMO?

    10 proj implemented simultaneously do not exceed 100m php

  • 36

    it is the legally executed aggrement bet. the contractor and the govt for the performance of the works covered by the contract

    contract docs

  • 37

    choose the correct statement among the choices below

    none of the above

  • 38

    choose the correct statement among the choices

    none of the above

  • 39

    which of the ff statement is correct

    as staked survey/site layout survey is an activity necessary to verify the actual field condition and to identify modifications and other deviations in the project

  • 40

    choose the correct statement among the choices below

    none of the above

  • 41

    in the process of issuance of COC, the contractor is advised to xomplete the works under the issued notice of defects/deficiencies within ___ days

    30

  • 42

    if the contractor fails to submit the as staked plan on time for processing, the contractor shall submit to the IO a request for 1 time extension of ___ days depending on the proj cost

    none of the above

  • 43

    the approving authority for the as staked plan is the head of IO

    none of the above

  • 44

    what is the calibrated action for an ongoing proj accumulating a negative slippage of 5%

    none of the above

  • 45

    the contractor shall submit a ___ to the head of implementing office through the PE for the final inspection of the proj

    written request for inspection

  • 46

    the______ shall monitor the conduct of joint as take survey which includes the establishment of project limits

    Dpwh PE

  • 47

    the_____shall prepare and submit to the PE monthly materials report containing test conducted and results

    dpwh me

  • 48

    it is done to ensure that the materials and workmanship provide by the contractor comply with the requirements of the project

    inspection

  • 49

    it shall be taken on the same location at the same time at the same angle before during and after the completion of each major component of the project

    photographs for progress billing

  • 50

    what DO prescribes the guidelines on the issuance of COC and COA?

    99 s. 2016

  • 51

    It is the Department Order instructing the adoption of the PDM as the project scheduling technique to be utilized in DPWH infrastructure projects.

    D.O. no. 133, series of 2015

  • 52

    what DO gives emphasis on the significance and requirement of construction records documentation for all DPWH implemented projects considering its vulnerability to litigation?

    216 s. 2000

  • 53

    DO for procesural flow and timeline in the processing of blacklisting of contractors for locally funded and foreign assisted infrastructure projects during implementation stage

    do 171 s. 2022

  • 54

    DO for time variance

    do42s2020

  • 55

    DO delegating usecs for approval/signing the procurement and Contract management

    do192s2016

  • 56

    DO guidelines for price escalation

    do60s2017

  • 57

    DO for preparation of as stake

    do55s2020

  • 58

    DO for termination of contract

    do90s2020

  • 59

    DO for standard forms for project implementation

    do46s2022

  • module 2

    module 2

    Wilson Angelo Oraza · 259問 · 2年前

    module 2

    module 2

    259問 • 2年前
    Wilson Angelo Oraza

    module 3

    module 3

    Wilson Angelo Oraza · 107問 · 2年前

    module 3

    module 3

    107問 • 2年前
    Wilson Angelo Oraza

    item #

    item #

    Wilson Angelo Oraza · 25問 · 2年前

    item #

    item #

    25問 • 2年前
    Wilson Angelo Oraza

    compre set 1

    compre set 1

    Wilson Angelo Oraza · 100問 · 2年前

    compre set 1

    compre set 1

    100問 • 2年前
    Wilson Angelo Oraza

    compre set 3

    compre set 3

    Wilson Angelo Oraza · 100問 · 2年前

    compre set 3

    compre set 3

    100問 • 2年前
    Wilson Angelo Oraza

    compre set 4

    compre set 4

    Wilson Angelo Oraza · 50問 · 2年前

    compre set 4

    compre set 4

    50問 • 2年前
    Wilson Angelo Oraza

    問題一覧

  • 1

    which of the ff reasons does not apply as to when the DPWH is authorized the full or partial suspension of work?

    due to ordinary unfavorable weather condition

  • 2

    period of time as to when the contractor or its duly authorized representative is allowed to suspend the work operation on any or all project/activities along the critical path?

    15 cal. days from the date of written notice from the contractor to the DE/RD/consultant or equivalent official

  • 3

    per IRR of RA 9184, suspension of work by the contractor due to delay in progress billing is being authorized for this period under conditions that a written notice from the contractor to the DE/RD/consultant or equivalent official suspending all projects/activities along the critical path and the delay in payment of contractors claim dor progress is being certified to be complete

    45 days

  • 4

    normally, contract time extension is not allowed in one of the following:

    suspension of work along the parallel activities

  • 5

    the event/period in the contract duration when the contractor shall be allowed to adjust the contract time accordingly

    in case of total suspension of activities along the critical path which is not due to the fault of the contractor

  • 6

    what should be done to detect and react appropriately to deviations and changes in plans?

    monitoring

  • 7

    what are the triple constraints that should be controlled?

    time,cost,performance

  • 8

    what is the calibrated action for an on-going proj accumulating a negative slippage of 5%?

    none of the above

  • 9

    ____ serves as the project engineers daily diary.

    construction project logbook

  • 10

    what should be issued in case the contractor is observed to be non-compliant with the contract specifications?

    site instruction-for non-compliance with contract specifications

  • 11

    a document done to keep a written record of the important discussion during meetings

    minutes of meeting

  • 12

    what is/are the basic indicator/s depicting the necessity for project control?

    more resources or less have been used than planned. Activities are taking longer than planned

  • 13

    PCMA stands for ___

    project and contract management application

  • 14

    the construction sched that will give the user information on the inter-relationships of work activities and sub-project groupings is the ____

    pert/cpm network diagram

  • 15

    for purposes of analyzing individual item accomplishment, the best construction sched to view is ____

    none of the above

  • 16

    it means the number of calendar days the project should be completed at prescribed schedule, defined by logic, sequence and duration of activities.

    contract time

  • 17

    illogical accomplishment means ____

    accomplishment done ahead of its predecessor

  • 18

    Given the S-Curve, what is the reason for the revision? See Figure 1

    Variation Order with Time Extension

  • 19

    What is the percent weight distribution in a Normal S-Curve?

    25-50-25

  • 20

    What does the acronym PERT/CPM stand for?

    Program Evaluation Review Technique/Critical Path Method

  • 21

    Who will prepare the complete set of the Construction Schedules prior to the signing of the Contract?

    Contractor

  • 22

    According to Annex "A" of the Revised IRR of RA the program of work shall include, among other things, estimates of work, items, quantities and costs and a PERT/CPM network of the project activities.

    9184

  • 23

    It is the amount of time a scheduled activity may either be delayed or extended from its early start date without delaying the project finish date.

    Float

  • 24

    Which of the following is NOT a use of Construction Schedules in DPWH projects?

    Basis for Billings

  • 25

    Complete the Forward Pass. Duration of Activity C is 30. See Figure 3.

    20 and 50

  • 26

    Complete the Backward Pass. Duration of F is 20. See Figure 4.

    50 and 70

  • 27

    ____ is one of the primary reaponsibilities of the proj inspectors under the supervision of the PE. this includes the measurement of the area, thickness, width and/or other measurements.

    quantity control

  • 28

    which type of chart ia used by the PE to ensure that the contractor is maintaining the min. number of equipment required/commited to the proj?

    equipment utilization schedule

  • 29

    what is the limit of assignment for Regional office PE3 based on DO 95 s. 2021

    5 proj costing above 250m and 15 proj costing 250m and below

  • 30

    the PE shall require the contractor to submit ___ of all permanent works that have been executed under the contract.

    as built plan

  • 31

    once the proj reaches an accomplishment of ___ % the PE shall facilitate the conduct of a pre-final inspection with the contractor

    95%

  • 32

    as applied to various atages of proj implementation is viewed and considered as the contractors responsibility

    quality control

  • 33

    give the overall view of the works to be done or accomplished during the implementation of the proj. these documents also help in the evaluation of the stability and quality of the projs.

    project documents

  • 34

    this doc is a written instruction in a form of memorandum/letter pertaining to the noted discrepancies in project implementation

    site instruction

  • 35

    based on the limits of assignments as stated in DO 95 S. 2021, what is the cost limit assignment for an accredited junior PE - UPMO?

    10 proj implemented simultaneously do not exceed 100m php

  • 36

    it is the legally executed aggrement bet. the contractor and the govt for the performance of the works covered by the contract

    contract docs

  • 37

    choose the correct statement among the choices below

    none of the above

  • 38

    choose the correct statement among the choices

    none of the above

  • 39

    which of the ff statement is correct

    as staked survey/site layout survey is an activity necessary to verify the actual field condition and to identify modifications and other deviations in the project

  • 40

    choose the correct statement among the choices below

    none of the above

  • 41

    in the process of issuance of COC, the contractor is advised to xomplete the works under the issued notice of defects/deficiencies within ___ days

    30

  • 42

    if the contractor fails to submit the as staked plan on time for processing, the contractor shall submit to the IO a request for 1 time extension of ___ days depending on the proj cost

    none of the above

  • 43

    the approving authority for the as staked plan is the head of IO

    none of the above

  • 44

    what is the calibrated action for an ongoing proj accumulating a negative slippage of 5%

    none of the above

  • 45

    the contractor shall submit a ___ to the head of implementing office through the PE for the final inspection of the proj

    written request for inspection

  • 46

    the______ shall monitor the conduct of joint as take survey which includes the establishment of project limits

    Dpwh PE

  • 47

    the_____shall prepare and submit to the PE monthly materials report containing test conducted and results

    dpwh me

  • 48

    it is done to ensure that the materials and workmanship provide by the contractor comply with the requirements of the project

    inspection

  • 49

    it shall be taken on the same location at the same time at the same angle before during and after the completion of each major component of the project

    photographs for progress billing

  • 50

    what DO prescribes the guidelines on the issuance of COC and COA?

    99 s. 2016

  • 51

    It is the Department Order instructing the adoption of the PDM as the project scheduling technique to be utilized in DPWH infrastructure projects.

    D.O. no. 133, series of 2015

  • 52

    what DO gives emphasis on the significance and requirement of construction records documentation for all DPWH implemented projects considering its vulnerability to litigation?

    216 s. 2000

  • 53

    DO for procesural flow and timeline in the processing of blacklisting of contractors for locally funded and foreign assisted infrastructure projects during implementation stage

    do 171 s. 2022

  • 54

    DO for time variance

    do42s2020

  • 55

    DO delegating usecs for approval/signing the procurement and Contract management

    do192s2016

  • 56

    DO guidelines for price escalation

    do60s2017

  • 57

    DO for preparation of as stake

    do55s2020

  • 58

    DO for termination of contract

    do90s2020

  • 59

    DO for standard forms for project implementation

    do46s2022