  • 1

    if any additional drawing issued by the architect during construction involves additional cost due to changes from the original design, is the contractor entitled to charge additional costs to the owner?

    yes, as long as he gives written notice to the architect regarding the extra cost within 15 days of receiving the instruction

  • 2

    wht section in the RA9266 states the integration of the architectural profession

    section 40

  • 3

    a horizontal section 1.2m above the floorline and looking downward seeing the fixtures, walls etc

    floorplan

  • 4

    height of window

    .82-1.82m

  • 5

    wht is the minimum rise of threads for stairs according to the NBC? run:not less than 250mm

    200mm

  • 6

    what is the maximum rise of treads for stairs acc to BP220 run: 200min

    250mm

  • 7

    how much is the minimum basic fee from the PCC for monumental buildings? dads-7.5% daeds-?

    12%

  • 8

    how much is the minimum basic fee from the PCC for simple projects without partitions, such as hangars? daeds-? dads-3%

    5%

  • 9

    for repetitive building designs, how much is the minimum basic fee from the PCC for any succeeding structures after the 3rd repetitive design? 1: 100% 2: 50% 3: 40% 4& succeeding: ?

    30%

  • 10

    malpractice of architecture shall not exceed the amount of how much?

    5 million

  • 11

    the members of the board shall hold office for a term of how many years? section6:term of office

    3

  • 12

    what law protects the architect from the reproduction of copies of the contract? ra8293

    intellectual property

  • 13

    distance of parking for the disabled from building entrance? BP344

    60m

  • 14

    what is not the recommended width for parking slots of PWD?

    2.10

  • 15

    minimum bedroom door opening?

    0.70m

  • 16

    min openings in a room NBCP section 808:window openings

    10% of floor area

  • 17

    what do you call an architect who wishes to practice architecture and is registered with the DTI?

    sole proprietorship

  • 18

    if a family of architects and engineers plans to set-up and architectural company to cater architectural services. what percentage of share should the architect have? section 37

    75%

  • 19

    responsibilities of an architect: when she/he conducts the checking of materials and works done if in adherence with the specification?

    project supervision

  • 20

    a permit secured prior to the occupancy of a building? section 309

    occupancy permit

  • 21

    what is the min floor area for economic and socialized housing?

    all of the choices

  • 22

    what is the minimum width of minor road for Economic and Socialized housing subdivision?

    6.5m

  • 23

    under the NBC, a building permit shall expire if work authorized is commenced within how long from date of such permit?

    12 months/1 year

  • 24

    under the NBC, a bldg permit shall expire if work authorized is abandoned or suspended at any time after a commencement for a period of __. section 305

    120 days

  • 25

    the purposed of the NBC is to provide for all bldgs and structures a framework of standards and requirements which is the __. section 102

    minimum

  • 26

    under the NBC, windows for toilet and bath openings shall equal at least of what percent of the floor area? =1/20 = not less than 240sq mm

    5%

  • 27

    under BP220, the minimum clear width of main door shall be how many meters? main door: ? service/bedroom doors: 0.70m bathroom door: 0.60m

    0.80m

  • 28

    under the NBC, the entry ramp of the driveway connecting the roadway surface to the sidewalk shall have a slope ranging from ___.

    1/3 - 1/4"

  • 29

    design build by maximum cost, how much is the architect remunerated? d kasali ang design build sa rpf unless stated in the pcc

    built in the max cost exclusive of arch reg fee

  • 30

    what shall the architect not ask from sources such as material suppliers given the fact that he already receives a professional fee from the client?

    commissions

  • 31

    a newspaper editor approaches an architect for an interview. which among is not an ethical thing to do.

    endorse a product

  • 32

    you had a project for a client, a residential building. after the construction, you found out that the client used your design for anothet project without your consent. what will you do?

    ask to be paid for the design

  • 33

    b4 submitting sktches to a client, what must the architect first do? acceptance fee- 5%

    sign a service agreement

  • 34

    what stage of the architect's services are site utilization and feasibility studies?

    pre-design services

  • 35

    what architectural service/phase is the part where the architect and client are choosing the contractor?

    bidding / negotiation phase

  • 36

    in a bidding, what is the role of the architect?

    organize the bidding

  • 37

    what is the foremost role of the architect between the client and contractor?

    mediator

  • 38

    role of an architect with regards to his client?

    adviser

  • 39

    who should orient the contractor and make sure that he understands the contract documents?

    architect

  • 40

    who is responsible in asking for a final inspection of a project?

    contractor

  • 41

    who provides continuing professional education (CPE)?

    IAPOA

  • 42

    if the client decide to get you for Design-Build by ADMINISTRATION how much additional fee would you charge in addition to your 10%?

    7%

  • 43

    bid and ___ shall mean the same.

    tender

  • 44

    under pd1096, for R-1 lots, firewalls are not allowed except an abutment or up to ___ in height.

    3.20m

  • 45

    under bp344, what is the inside dimensions of an elevator car?

    1.10m x 1.40m

  • Architect Dictums and Philosophies

    Architect Dictums and Philosophies

    LazyXKing · 90問 · 1年前

    Architect Dictums and Philosophies

    Architect Dictums and Philosophies

    90問 • 1年前
    LazyXKing

    FIRE PROTECTION 1

    FIRE PROTECTION 1

    LazyXKing · 100問 · 1年前

    FIRE PROTECTION 1

    FIRE PROTECTION 1

    100問 • 1年前
    LazyXKing

    FIRE PROTECTION 2

    FIRE PROTECTION 2

    LazyXKing · 46問 · 1年前

    FIRE PROTECTION 2

    FIRE PROTECTION 2

    46問 • 1年前
    LazyXKing

    DAY 01am-part1

    DAY 01am-part1

    LazyXKing · 53問 · 1年前

    DAY 01am-part1

    DAY 01am-part1

    53問 • 1年前
    LazyXKing

    DAY 01 pm-part1

    DAY 01 pm-part1

    LazyXKing · 100問 · 1年前

    DAY 01 pm-part1

    DAY 01 pm-part1

    100問 • 1年前
    LazyXKing

    DAY 01 pm-part2

    DAY 01 pm-part2

    LazyXKing · 100問 · 1年前

    DAY 01 pm-part2

    DAY 01 pm-part2

    100問 • 1年前
    LazyXKing

    DAY 01 pm-part3

    DAY 01 pm-part3

    LazyXKing · 99問 · 1年前

    DAY 01 pm-part3

    DAY 01 pm-part3

    99問 • 1年前
    LazyXKing

    RA 9266

    RA 9266

    LazyXKing · 30問 · 1年前

    RA 9266

    RA 9266

    30問 • 1年前
    LazyXKing

    BLDG LAWS & PROFPRAC PREBOARD 1

    BLDG LAWS & PROFPRAC PREBOARD 1

    LazyXKing · 100問 · 1年前

    BLDG LAWS & PROFPRAC PREBOARD 1

    BLDG LAWS & PROFPRAC PREBOARD 1

    100問 • 1年前
    LazyXKing

    BLDG LAWS & PROFPRAC PREBOARD 2

    BLDG LAWS & PROFPRAC PREBOARD 2

    LazyXKing · 100問 · 1年前

    BLDG LAWS & PROFPRAC PREBOARD 2

    BLDG LAWS & PROFPRAC PREBOARD 2

    100問 • 1年前
    LazyXKing

    BLDG LAWS & PROFPRAC PREBOARD 4

    BLDG LAWS & PROFPRAC PREBOARD 4

    LazyXKing · 97問 · 1年前

    BLDG LAWS & PROFPRAC PREBOARD 4

    BLDG LAWS & PROFPRAC PREBOARD 4

    97問 • 1年前
    LazyXKing

    VERNACULAR TERMS o1

    VERNACULAR TERMS o1

    LazyXKing · 86問 · 1年前

    VERNACULAR TERMS o1

    VERNACULAR TERMS o1

    86問 • 1年前
    LazyXKing

    VERNACULAR TERMS o2

    VERNACULAR TERMS o2

    LazyXKing · 98問 · 1年前

    VERNACULAR TERMS o2

    VERNACULAR TERMS o2

    98問 • 1年前
    LazyXKing

    VERNACULAR TERMS o3

    VERNACULAR TERMS o3

    LazyXKing · 100問 · 1年前

    VERNACULAR TERMS o3

    VERNACULAR TERMS o3

    100問 • 1年前
    LazyXKing

    VERNACULAR TERMS o4

    VERNACULAR TERMS o4

    LazyXKing · 53問 · 1年前

    VERNACULAR TERMS o4

    VERNACULAR TERMS o4

    53問 • 1年前
    LazyXKing

    HOA RANDOMS MST 01

    HOA RANDOMS MST 01

    LazyXKing · 100問 · 1年前

    HOA RANDOMS MST 01

    HOA RANDOMS MST 01

    100問 • 1年前
    LazyXKing

    HOA RANDOMS MST 02

    HOA RANDOMS MST 02

    LazyXKing · 100問 · 1年前

    HOA RANDOMS MST 02

    HOA RANDOMS MST 02

    100問 • 1年前
    LazyXKing

    HOA MST RANDOMS 03

    HOA MST RANDOMS 03

    LazyXKing · 7問 · 1年前

    HOA MST RANDOMS 03

    HOA MST RANDOMS 03

    7問 • 1年前
    LazyXKing

    DESIGN DAY 2

    DESIGN DAY 2

    LazyXKing · 97問 · 1年前

    DESIGN DAY 2

    DESIGN DAY 2

    97問 • 1年前
    LazyXKing

    問題一覧

  • 1

    if any additional drawing issued by the architect during construction involves additional cost due to changes from the original design, is the contractor entitled to charge additional costs to the owner?

    yes, as long as he gives written notice to the architect regarding the extra cost within 15 days of receiving the instruction

  • 2

    wht section in the RA9266 states the integration of the architectural profession

    section 40

  • 3

    a horizontal section 1.2m above the floorline and looking downward seeing the fixtures, walls etc

    floorplan

  • 4

    height of window

    .82-1.82m

  • 5

    wht is the minimum rise of threads for stairs according to the NBC? run:not less than 250mm

    200mm

  • 6

    what is the maximum rise of treads for stairs acc to BP220 run: 200min

    250mm

  • 7

    how much is the minimum basic fee from the PCC for monumental buildings? dads-7.5% daeds-?

    12%

  • 8

    how much is the minimum basic fee from the PCC for simple projects without partitions, such as hangars? daeds-? dads-3%

    5%

  • 9

    for repetitive building designs, how much is the minimum basic fee from the PCC for any succeeding structures after the 3rd repetitive design? 1: 100% 2: 50% 3: 40% 4& succeeding: ?

    30%

  • 10

    malpractice of architecture shall not exceed the amount of how much?

    5 million

  • 11

    the members of the board shall hold office for a term of how many years? section6:term of office

    3

  • 12

    what law protects the architect from the reproduction of copies of the contract? ra8293

    intellectual property

  • 13

    distance of parking for the disabled from building entrance? BP344

    60m

  • 14

    what is not the recommended width for parking slots of PWD?

    2.10

  • 15

    minimum bedroom door opening?

    0.70m

  • 16

    min openings in a room NBCP section 808:window openings

    10% of floor area

  • 17

    what do you call an architect who wishes to practice architecture and is registered with the DTI?

    sole proprietorship

  • 18

    if a family of architects and engineers plans to set-up and architectural company to cater architectural services. what percentage of share should the architect have? section 37

    75%

  • 19

    responsibilities of an architect: when she/he conducts the checking of materials and works done if in adherence with the specification?

    project supervision

  • 20

    a permit secured prior to the occupancy of a building? section 309

    occupancy permit

  • 21

    what is the min floor area for economic and socialized housing?

    all of the choices

  • 22

    what is the minimum width of minor road for Economic and Socialized housing subdivision?

    6.5m

  • 23

    under the NBC, a building permit shall expire if work authorized is commenced within how long from date of such permit?

    12 months/1 year

  • 24

    under the NBC, a bldg permit shall expire if work authorized is abandoned or suspended at any time after a commencement for a period of __. section 305

    120 days

  • 25

    the purposed of the NBC is to provide for all bldgs and structures a framework of standards and requirements which is the __. section 102

    minimum

  • 26

    under the NBC, windows for toilet and bath openings shall equal at least of what percent of the floor area? =1/20 = not less than 240sq mm

    5%

  • 27

    under BP220, the minimum clear width of main door shall be how many meters? main door: ? service/bedroom doors: 0.70m bathroom door: 0.60m

    0.80m

  • 28

    under the NBC, the entry ramp of the driveway connecting the roadway surface to the sidewalk shall have a slope ranging from ___.

    1/3 - 1/4"

  • 29

    design build by maximum cost, how much is the architect remunerated? d kasali ang design build sa rpf unless stated in the pcc

    built in the max cost exclusive of arch reg fee

  • 30

    what shall the architect not ask from sources such as material suppliers given the fact that he already receives a professional fee from the client?

    commissions

  • 31

    a newspaper editor approaches an architect for an interview. which among is not an ethical thing to do.

    endorse a product

  • 32

    you had a project for a client, a residential building. after the construction, you found out that the client used your design for anothet project without your consent. what will you do?

    ask to be paid for the design

  • 33

    b4 submitting sktches to a client, what must the architect first do? acceptance fee- 5%

    sign a service agreement

  • 34

    what stage of the architect's services are site utilization and feasibility studies?

    pre-design services

  • 35

    what architectural service/phase is the part where the architect and client are choosing the contractor?

    bidding / negotiation phase

  • 36

    in a bidding, what is the role of the architect?

    organize the bidding

  • 37

    what is the foremost role of the architect between the client and contractor?

    mediator

  • 38

    role of an architect with regards to his client?

    adviser

  • 39

    who should orient the contractor and make sure that he understands the contract documents?

    architect

  • 40

    who is responsible in asking for a final inspection of a project?

    contractor

  • 41

    who provides continuing professional education (CPE)?

    IAPOA

  • 42

    if the client decide to get you for Design-Build by ADMINISTRATION how much additional fee would you charge in addition to your 10%?

    7%

  • 43

    bid and ___ shall mean the same.

    tender

  • 44

    under pd1096, for R-1 lots, firewalls are not allowed except an abutment or up to ___ in height.

    3.20m

  • 45

    under bp344, what is the inside dimensions of an elevator car?

    1.10m x 1.40m