1
alteration
2
moving
3
renovation
4
true
5
true
6
true
7
NON-COMPLIANCE with work STOPPAGE ORDER for construction or demolition without permit
8
building official's duty
9
8 meters
10
building permit
11
all of the above are included under civil/structural documents
12
1.50m
13
the highest point if the lot
14
3.60 x 12.00 m
15
TOSL
16
PSO max
17
GFA
18
6.00 sqm
19
14 cum
20
3.00 m
21
2.70 m
22
20 m
23
R-4
24
certificate of occupancy
25
licensed architect
26
addition
27
type 2
28
aesthetic deficiency
29
highly fire restrictive zones
30
1200mm
31
15mm
32
38 meters/minute
33
0.90m
34
TLA x PSOmax x BHLmeters
35
4 m
36
1:12
37
0.90m
38
3.70m
39
1.70m x 1.80m
40
30m from entrance
41
800mm
42
800mm
43
class C
44
250mm
45
200mm
46
class A
47
2.00m
48
FSMR
49
72 sqm
50
8.00m
51
1.50m
52
42 sqm
53
96sqm
54
6 inches
55
22 sqm
56
occupant load
57
FSEC
58
an architects duty to the public
59
architect in charge of construction
60
all of the choices
61
a partnership
62
direct selection
63
value management
64
reimbursibles
65
professional fee plus expenses
66
site development
67
design revisions
68
physical planning
69
specialized architectural service
70
SPP-204B
71
1.5-2.5
72
all of the choices
73
mall
74
all of the choices
75
net amount
76
cost of acquiring the lot
77
PDC
78
280mm
79
100mm
80
870mm
81
3 exits
82
6.00m
83
230mm
84
1120mm
85
600mm
86
0.28sqm
87
300mm
88
18sqm
89
3.00m
90
1.20m
91
3.50m
92
1200mm from the floor
93
0.90m
94
300mm
95
1:20
96
1:100
97
6.5mm
98
40mm
99
50mm
100
0.90m/sec
Architect Dictums and Philosophies
Architect Dictums and Philosophies
LazyXKing · 90問 · 1年前Architect Dictums and Philosophies
Architect Dictums and Philosophies
90問 • 1年前FIRE PROTECTION 1
FIRE PROTECTION 1
LazyXKing · 100問 · 1年前FIRE PROTECTION 1
FIRE PROTECTION 1
100問 • 1年前FIRE PROTECTION 2
FIRE PROTECTION 2
LazyXKing · 46問 · 1年前FIRE PROTECTION 2
FIRE PROTECTION 2
46問 • 1年前DAY 01am-part1
DAY 01am-part1
LazyXKing · 53問 · 1年前DAY 01am-part1
DAY 01am-part1
53問 • 1年前DAY 01 pm-part1
DAY 01 pm-part1
LazyXKing · 100問 · 1年前DAY 01 pm-part1
DAY 01 pm-part1
100問 • 1年前DAY 01 pm-part2
DAY 01 pm-part2
LazyXKing · 100問 · 1年前DAY 01 pm-part2
DAY 01 pm-part2
100問 • 1年前DAY 01 pm-part3
DAY 01 pm-part3
LazyXKing · 99問 · 1年前DAY 01 pm-part3
DAY 01 pm-part3
99問 • 1年前RA 9266
RA 9266
LazyXKing · 30問 · 1年前RA 9266
RA 9266
30問 • 1年前BLDG LAWS & PROFPRAC PREBOARD 2
BLDG LAWS & PROFPRAC PREBOARD 2
LazyXKing · 100問 · 1年前BLDG LAWS & PROFPRAC PREBOARD 2
BLDG LAWS & PROFPRAC PREBOARD 2
100問 • 1年前BLDG LAWS & PROFPRAC PREBOARD 3
BLDG LAWS & PROFPRAC PREBOARD 3
LazyXKing · 45問 · 1年前BLDG LAWS & PROFPRAC PREBOARD 3
BLDG LAWS & PROFPRAC PREBOARD 3
45問 • 1年前BLDG LAWS & PROFPRAC PREBOARD 4
BLDG LAWS & PROFPRAC PREBOARD 4
LazyXKing · 97問 · 1年前BLDG LAWS & PROFPRAC PREBOARD 4
BLDG LAWS & PROFPRAC PREBOARD 4
97問 • 1年前VERNACULAR TERMS o1
VERNACULAR TERMS o1
LazyXKing · 86問 · 1年前VERNACULAR TERMS o1
VERNACULAR TERMS o1
86問 • 1年前VERNACULAR TERMS o2
VERNACULAR TERMS o2
LazyXKing · 98問 · 1年前VERNACULAR TERMS o2
VERNACULAR TERMS o2
98問 • 1年前VERNACULAR TERMS o3
VERNACULAR TERMS o3
LazyXKing · 100問 · 1年前VERNACULAR TERMS o3
VERNACULAR TERMS o3
100問 • 1年前VERNACULAR TERMS o4
VERNACULAR TERMS o4
LazyXKing · 53問 · 1年前VERNACULAR TERMS o4
VERNACULAR TERMS o4
53問 • 1年前HOA RANDOMS MST 01
HOA RANDOMS MST 01
LazyXKing · 100問 · 1年前HOA RANDOMS MST 01
HOA RANDOMS MST 01
100問 • 1年前HOA RANDOMS MST 02
HOA RANDOMS MST 02
LazyXKing · 100問 · 1年前HOA RANDOMS MST 02
HOA RANDOMS MST 02
100問 • 1年前HOA MST RANDOMS 03
HOA MST RANDOMS 03
LazyXKing · 7問 · 1年前HOA MST RANDOMS 03
HOA MST RANDOMS 03
7問 • 1年前DESIGN DAY 2
DESIGN DAY 2
LazyXKing · 97問 · 1年前DESIGN DAY 2
DESIGN DAY 2
97問 • 1年前問題一覧
1
alteration
2
moving
3
renovation
4
true
5
true
6
true
7
NON-COMPLIANCE with work STOPPAGE ORDER for construction or demolition without permit
8
building official's duty
9
8 meters
10
building permit
11
all of the above are included under civil/structural documents
12
1.50m
13
the highest point if the lot
14
3.60 x 12.00 m
15
TOSL
16
PSO max
17
GFA
18
6.00 sqm
19
14 cum
20
3.00 m
21
2.70 m
22
20 m
23
R-4
24
certificate of occupancy
25
licensed architect
26
addition
27
type 2
28
aesthetic deficiency
29
highly fire restrictive zones
30
1200mm
31
15mm
32
38 meters/minute
33
0.90m
34
TLA x PSOmax x BHLmeters
35
4 m
36
1:12
37
0.90m
38
3.70m
39
1.70m x 1.80m
40
30m from entrance
41
800mm
42
800mm
43
class C
44
250mm
45
200mm
46
class A
47
2.00m
48
FSMR
49
72 sqm
50
8.00m
51
1.50m
52
42 sqm
53
96sqm
54
6 inches
55
22 sqm
56
occupant load
57
FSEC
58
an architects duty to the public
59
architect in charge of construction
60
all of the choices
61
a partnership
62
direct selection
63
value management
64
reimbursibles
65
professional fee plus expenses
66
site development
67
design revisions
68
physical planning
69
specialized architectural service
70
SPP-204B
71
1.5-2.5
72
all of the choices
73
mall
74
all of the choices
75
net amount
76
cost of acquiring the lot
77
PDC
78
280mm
79
100mm
80
870mm
81
3 exits
82
6.00m
83
230mm
84
1120mm
85
600mm
86
0.28sqm
87
300mm
88
18sqm
89
3.00m
90
1.20m
91
3.50m
92
1200mm from the floor
93
0.90m
94
300mm
95
1:20
96
1:100
97
6.5mm
98
40mm
99
50mm
100
0.90m/sec