    An exercise given to the Client for him to review the stipulations of the contract documents within a reasonable time.

    Due Diligence

  • 2

    A principle when drafting the contract, where parties are bound by terms and consequences

    Mutuality

  • 3

    Instructions which may be issued prior to the bidding to supplement and/or modify the drawings, specifications, and/or General conditions of the contract.

    Special Provisions

  • 4

    Article 1723 of the Civil Code

    Civil Liability

  • 5

    Allocated payment value in proportion to the work performed by the contractor

    Prorate

  • 6

    Information, advice a notification or pertinent to the project delivered in person or sent by registered mail to the individual, firm, or corporation at the last known business address of such individual, firm or corporation

    Written Notice

  • 7

    An approved form of security furnished by the contractor as a guarantee to the quality of materials and equipments installed and the workmanship performed by the contractor

    Guarantee Bond

  • 8

    A period wherein the contractor shall execute at his own expense all work necessary for the rectification of imperfections.

    Period of making good of known defect

  • 9

    An approved form of security furnished by the contractor as a guarantee of good faith on his part that he will pay all obligations arising from the contract

    Payment Bond

  • 10

    Labor or Materials, or both as well as equipment, transportation, or other facilities necessary to commence and complete the construction called for in the contract

    Work

  • 11

    Additional information or contract documents issued to bidders before date of bidding

    Bid Bulletin

  • 12

    A listing of the different parts of the work indicating the materials and labor included therein.

    Scope of Work

  • 13

    A listing of the different parts of the work indicating in each part the corresponding value of materials and labor, including an allowance for profit and overhead.

    Breakdown of Work and Corresponding Value

  • 14

    It is an outline description enumerating the type or trade names of materials be used

    Schedule of Material and Finishes

  • 15

    An approved form of security furnished by the contractor as a guarantee of good faith that he will execute the work in accordance with the terms of the contract.

    Performance Bond

  • 16

    A principle when drafting the contract, which binds only those involved and assigns.

    Relativity

  • 17

    Article 1305 of the Civil Code

    Contract

  • 18

    A contractual obligation of one party to compensate the loss incurred to the other party or as security against legal liability for one's actions.

    Indemnity

  • 19

    A contract, represented by a policy, in which the client receives financial protection or reimbursement against losses in case of claims on damages on lives and properties lost or affected.

    Insurance

  • 20

    The drawings are supplementary

    False/Complementary

  • 21

    Should the contractor fail to remove, unsatisfactory workmen or fail to furnish suitable and sufficient equipment or personnel for the proper prosecution of the work, thr CONSTRUCTION MANAGER may withhold payment which are or may become or may suspend the work until such orders are compiled with.

    False/Owner

  • 22

    The CLIENT shall prepare at his own expense and submit with such promptness as to cause no delay in his own work or i. that of any other contractor doing work on the same building, teo copies of all shop or setting drWings, templates, patterns and models as well as schedule required for the work of the various trades

    False/Contractor

  • 23

    The CLIENT shall make all necessary arrangements with the local utility companies in order that temporary facilities for water, power, and telephone are sufficiently provided till the completion to of the work. All expenses incurred in connections therewith shall be paid by the CLIENT.

    False/Contractor

  • 24

    Responsibility for the adequacy of the design and for suffiency of the drawings and specifications shall be borne by the CONTRACTOR

    False/Client

  • 25

    The complete requirements of the work to be performed under the contract shall be set forth in drawings and specifications to be supplied by the CONTRACTOR

    False/client

  • 26

    The CONTRACTOR shall furnish from time to time all additional detail drawings and instructions essential to the proper execution of the work.

    False/client

  • 27

    Testing of all samples shall comply with the specifications and government standards and shall be performed by competent, entity or testing laboratory. All cost for shipment, delivery, handling and testing of samples are to be paid by the OWNER

    False/Contractor

  • 28

    The Architect MAY at anytime order extra work or make changes by altering, adding to or deducting from the work

    False/May Not

  • 29

    The contract shall be assigned in whole or in part by the contractor or shall any part of the work be SUBLET by the contractor

    False

  • Geotech Quiz 1

    Geotech Quiz 1

    John Rotrix Tumaneng · 38問 · 2年前

    Geotech Quiz 1

    Geotech Quiz 1

    38問 • 2年前
    John Rotrix Tumaneng

    IE First LE

    IE First LE

    John Rotrix Tumaneng · 26問 · 2年前

    IE First LE

    IE First LE

    26問 • 2年前
    John Rotrix Tumaneng

    Laws

    Laws

    John Rotrix Tumaneng · 15問 · 2年前

    Laws

    Laws

    15問 • 2年前
    John Rotrix Tumaneng

    Hydro LE 1

    Hydro LE 1

    John Rotrix Tumaneng · 20問 · 2年前

    Hydro LE 1

    Hydro LE 1

    20問 • 2年前
    John Rotrix Tumaneng

    SOCSC MIDTERMS

    SOCSC MIDTERMS

    John Rotrix Tumaneng · 30問 · 2年前

    SOCSC MIDTERMS

    SOCSC MIDTERMS

    30問 • 2年前
    John Rotrix Tumaneng

    GEOTECH FORMULAS

    GEOTECH FORMULAS

    John Rotrix Tumaneng · 19問 · 2年前

    GEOTECH FORMULAS

    GEOTECH FORMULAS

    19問 • 2年前
    John Rotrix Tumaneng

    SOCSC LE1

    SOCSC LE1

    John Rotrix Tumaneng · 57問 · 2年前

    SOCSC LE1

    SOCSC LE1

    57問 • 2年前
    John Rotrix Tumaneng

    CE101 LE2 CHAP3

    CE101 LE2 CHAP3

    John Rotrix Tumaneng · 17問 · 2年前

    CE101 LE2 CHAP3

    CE101 LE2 CHAP3

    17問 • 2年前
    John Rotrix Tumaneng

    CE101 LE2CHAP4

    CE101 LE2CHAP4

    John Rotrix Tumaneng · 7問 · 2年前

    CE101 LE2CHAP4

    CE101 LE2CHAP4

    7問 • 2年前
    John Rotrix Tumaneng

    SOCSCI FE

    SOCSCI FE

    John Rotrix Tumaneng · 36問 · 2年前

    SOCSCI FE

    SOCSCI FE

    36問 • 2年前
    John Rotrix Tumaneng

    Hum01 FE

    Hum01 FE

    John Rotrix Tumaneng · 21問 · 2年前

    Hum01 FE

    Hum01 FE

    21問 • 2年前
    John Rotrix Tumaneng

    IE FINAL EXAM

    IE FINAL EXAM

    John Rotrix Tumaneng · 10問 · 2年前

    IE FINAL EXAM

    IE FINAL EXAM

    10問 • 2年前
    John Rotrix Tumaneng

    GEOTECH FE

    GEOTECH FE

    John Rotrix Tumaneng · 18問 · 2年前

    GEOTECH FE

    GEOTECH FE

    18問 • 2年前
    John Rotrix Tumaneng

    CE 161 CHAP 1

    CE 161 CHAP 1

    John Rotrix Tumaneng · 19問 · 1年前

    CE 161 CHAP 1

    CE 161 CHAP 1

    19問 • 1年前
    John Rotrix Tumaneng

    CE 190

    CE 190

    John Rotrix Tumaneng · 25問 · 1年前

    CE 190

    CE 190

    25問 • 1年前
    John Rotrix Tumaneng

    CE 161 2ND LE

    CE 161 2ND LE

    John Rotrix Tumaneng · 64問 · 1年前

    CE 161 2ND LE

    CE 161 2ND LE

    64問 • 1年前
    John Rotrix Tumaneng

    ENGG101 SECOND LE

    ENGG101 SECOND LE

    John Rotrix Tumaneng · 55問 · 1年前

    ENGG101 SECOND LE

    ENGG101 SECOND LE

    55問 • 1年前
    John Rotrix Tumaneng

    Quiz 3

    Quiz 3

    John Rotrix Tumaneng · 14問 · 1年前

    Quiz 3

    Quiz 3

    14問 • 1年前
    John Rotrix Tumaneng

    問題一覧

  • 1

    An exercise given to the Client for him to review the stipulations of the contract documents within a reasonable time.

    Due Diligence

  • 2

    A principle when drafting the contract, where parties are bound by terms and consequences

    Mutuality

  • 3

    Instructions which may be issued prior to the bidding to supplement and/or modify the drawings, specifications, and/or General conditions of the contract.

    Special Provisions

  • 4

    Article 1723 of the Civil Code

    Civil Liability

  • 5

    Allocated payment value in proportion to the work performed by the contractor

    Prorate

  • 6

    Information, advice a notification or pertinent to the project delivered in person or sent by registered mail to the individual, firm, or corporation at the last known business address of such individual, firm or corporation

    Written Notice

  • 7

    An approved form of security furnished by the contractor as a guarantee to the quality of materials and equipments installed and the workmanship performed by the contractor

    Guarantee Bond

  • 8

    A period wherein the contractor shall execute at his own expense all work necessary for the rectification of imperfections.

    Period of making good of known defect

  • 9

    An approved form of security furnished by the contractor as a guarantee of good faith on his part that he will pay all obligations arising from the contract

    Payment Bond

  • 10

    Labor or Materials, or both as well as equipment, transportation, or other facilities necessary to commence and complete the construction called for in the contract

    Work

  • 11

    Additional information or contract documents issued to bidders before date of bidding

    Bid Bulletin

  • 12

    A listing of the different parts of the work indicating the materials and labor included therein.

    Scope of Work

  • 13

    A listing of the different parts of the work indicating in each part the corresponding value of materials and labor, including an allowance for profit and overhead.

    Breakdown of Work and Corresponding Value

  • 14

    It is an outline description enumerating the type or trade names of materials be used

    Schedule of Material and Finishes

  • 15

    An approved form of security furnished by the contractor as a guarantee of good faith that he will execute the work in accordance with the terms of the contract.

    Performance Bond

  • 16

    A principle when drafting the contract, which binds only those involved and assigns.

    Relativity

  • 17

    Article 1305 of the Civil Code

    Contract

  • 18

    A contractual obligation of one party to compensate the loss incurred to the other party or as security against legal liability for one's actions.

    Indemnity

  • 19

    A contract, represented by a policy, in which the client receives financial protection or reimbursement against losses in case of claims on damages on lives and properties lost or affected.

    Insurance

  • 20

    The drawings are supplementary

    False/Complementary

  • 21

    Should the contractor fail to remove, unsatisfactory workmen or fail to furnish suitable and sufficient equipment or personnel for the proper prosecution of the work, thr CONSTRUCTION MANAGER may withhold payment which are or may become or may suspend the work until such orders are compiled with.

    False/Owner

  • 22

    The CLIENT shall prepare at his own expense and submit with such promptness as to cause no delay in his own work or i. that of any other contractor doing work on the same building, teo copies of all shop or setting drWings, templates, patterns and models as well as schedule required for the work of the various trades

    False/Contractor

  • 23

    The CLIENT shall make all necessary arrangements with the local utility companies in order that temporary facilities for water, power, and telephone are sufficiently provided till the completion to of the work. All expenses incurred in connections therewith shall be paid by the CLIENT.

    False/Contractor

  • 24

    Responsibility for the adequacy of the design and for suffiency of the drawings and specifications shall be borne by the CONTRACTOR

    False/Client

  • 25

    The complete requirements of the work to be performed under the contract shall be set forth in drawings and specifications to be supplied by the CONTRACTOR

    False/client

  • 26

    The CONTRACTOR shall furnish from time to time all additional detail drawings and instructions essential to the proper execution of the work.

    False/client

  • 27

    Testing of all samples shall comply with the specifications and government standards and shall be performed by competent, entity or testing laboratory. All cost for shipment, delivery, handling and testing of samples are to be paid by the OWNER

    False/Contractor

  • 28

    The Architect MAY at anytime order extra work or make changes by altering, adding to or deducting from the work

    False/May Not

  • 29

    The contract shall be assigned in whole or in part by the contractor or shall any part of the work be SUBLET by the contractor

    False