    Steel posts must be at least __ in diameter and protected against rust such as with rust resistant paint

    3”

  • 2

    how do you tell the dimensions of a steel beam I.e. W12 X 45#

    The first number is the width of the beam, The second number is how many pounds per foot

  • 3

    pertaining to steel beams an S instead of a W means that the beam will be

    an I-beam

  • 4

    when installing stiffeners on I-joist, The stiffeners should be ___ shorter than the expected portion of the web so that they do not force the upper flange out of position

    1/8”

  • 5

    bridging is not generally required by code unless Joyce exceed ___ in depth

    2x12

  • 6

    blocking should be spaced no more than ___

    4”

  • 7

    for framing a stair well the rough opening must be at least ___ wide

    37”

  • 8

    A soffit is usually about ___ deeper (protruding into the room) than the cabinets so that the molding can be installed at the cabinet top

    2”

  • 9

    what is the most economical way to roof a house to weatherproof

    shed roof

  • 10

    What are the advantages of using roof truss instead of using traditional roofing rafters

    save money on materials, save on on-site labor

  • 11

    what is the most common roofing truss

    fink truss a.k.a. W truss

  • 12

    A standard interior jam is ___ wide

    4-9/16”

  • 13

    a rough door opening should be ___ wider and ___ higher than the door

    2”/2”

  • 14

    when talking about vertical intersections (roofing around stuff like chimney) The cap flashing is inserted ___ into the joints between bricks the joints are then filled with mortar

    1-1/2”

  • 15

    if gutter is over 60 foot in length what is required

    expansion joint/slip joint connector

  • 16

    in a gutter system a splash block should be at least blank long

    3’

  • 17

    suspension systems for gutters should be spaced ___ to ___ on center

    3’-4’

  • 18

    Three types of siding nails are

    Galvanize steel, Stainless steel, High tensile strength aluminum

  • 19

    The standard brick sizes are the same except for the width which are

    4”/3-1/4”

  • 20

    To permit acclamation floor and should always be stored in the building in which it will be installed for at least ___ or ___ days before being laid

    4/5

  • 21

    under laminate should be at least ___ thick and have a sanded of the surface

    1/4”

  • 22

    What type of fasteners are used in exterior basement or crawlspace walls such as knee walls construction

    type 304 or 316 stainless steel

  • 23

    which fasteners should not be used in below grade exterior basement/crawl space wall studs or fasteners used in knee wall construction

    Electro galvanized steel nails, Galvanized zinc coated steel staples

  • 24

    concrete shall be air entrained. call Eric content (percent by volume of concrete) shall be not less than ___ or more than ___

    5%/7%

  • 25

    What is the minimal thickness of crushed stone or coarse sand under a basement floor

    4”

  • 26

    A sump shall be not less than __ in diameter

    24”

  • 27

    in a crawlspace one ventilation open child be within ___ feet of each corner of the building

    3

  • 28

    veneer ties (sheet metal) shall support no more than ___ square feet pre tie

    2.67

  • 29

    additional veneer ties shall be provided around wall openings greater than ___ inches in either dimension

    16

  • 30

    What is the minimum thickness of a fireplace hearth?

    4 inches

  • construction

    construction

    Sterling Thomas · 40問 · 2年前

    construction

    construction

    40問 • 2年前
    Sterling Thomas

    construction 1.25

    construction 1.25

    Sterling Thomas · 20問 · 2年前

    construction 1.25

    construction 1.25

    20問 • 2年前
    Sterling Thomas

    construction 1.5

    construction 1.5

    Sterling Thomas · 20問 · 2年前

    construction 1.5

    construction 1.5

    20問 • 2年前
    Sterling Thomas

    construction 1.75

    construction 1.75

    Sterling Thomas · 20問 · 2年前

    construction 1.75

    construction 1.75

    20問 • 2年前
    Sterling Thomas

    construction 2

    construction 2

    Sterling Thomas · 34問 · 2年前

    construction 2

    construction 2

    34問 • 2年前
    Sterling Thomas

    construction 2.25

    construction 2.25

    Sterling Thomas · 30問 · 2年前

    construction 2.25

    construction 2.25

    30問 • 2年前
    Sterling Thomas

    construction 2.5

    construction 2.5

    Sterling Thomas · 30問 · 2年前

    construction 2.5

    construction 2.5

    30問 • 2年前
    Sterling Thomas

    construction 3

    construction 3

    Sterling Thomas · 29問 · 2年前

    construction 3

    construction 3

    29問 • 2年前
    Sterling Thomas

    construction 4

    construction 4

    Sterling Thomas · 25問 · 2年前

    construction 4

    construction 4

    25問 • 2年前
    Sterling Thomas

    construction 4.5

    construction 4.5

    Sterling Thomas · 24問 · 2年前

    construction 4.5

    construction 4.5

    24問 • 2年前
    Sterling Thomas

    construction 5

    construction 5

    Sterling Thomas · 34問 · 2年前

    construction 5

    construction 5

    34問 • 2年前
    Sterling Thomas

    construction 5.25

    construction 5.25

    Sterling Thomas · 33問 · 2年前

    construction 5.25

    construction 5.25

    33問 • 2年前
    Sterling Thomas

    construction 5.5

    construction 5.5

    Sterling Thomas · 33問 · 2年前

    construction 5.5

    construction 5.5

    33問 • 2年前
    Sterling Thomas

    Identify

    Identify

    Sterling Thomas · 32問 · 2年前

    Identify

    Identify

    32問 • 2年前
    Sterling Thomas

    construction 6

    construction 6

    Sterling Thomas · 28問 · 2年前

    construction 6

    construction 6

    28問 • 2年前
    Sterling Thomas

    construction 7

    construction 7

    Sterling Thomas · 30問 · 2年前

    construction 7

    construction 7

    30問 • 2年前
    Sterling Thomas

    construction 8

    construction 8

    Sterling Thomas · 30問 · 2年前

    construction 8

    construction 8

    30問 • 2年前
    Sterling Thomas

    construction 9

    construction 9

    Sterling Thomas · 29問 · 2年前

    construction 9

    construction 9

    29問 • 2年前
    Sterling Thomas

    construction 10

    construction 10

    Sterling Thomas · 35問 · 2年前

    construction 10

    construction 10

    35問 • 2年前
    Sterling Thomas

    construction 11

    construction 11

    Sterling Thomas · 30問 · 2年前

    construction 11

    construction 11

    30問 • 2年前
    Sterling Thomas

    construction 12

    construction 12

    Sterling Thomas · 30問 · 2年前

    construction 12

    construction 12

    30問 • 2年前
    Sterling Thomas

    Identify 2

    Identify 2

    Sterling Thomas · 22問 · 1年前

    Identify 2

    Identify 2

    22問 • 1年前
    Sterling Thomas

    construction 13

    construction 13

    Sterling Thomas · 30問 · 1年前

    construction 13

    construction 13

    30問 • 1年前
    Sterling Thomas

    Identify 3

    Identify 3

    Sterling Thomas · 35問 · 1年前

    Identify 3

    Identify 3

    35問 • 1年前
    Sterling Thomas

    問題一覧

  • 1

    Steel posts must be at least __ in diameter and protected against rust such as with rust resistant paint

    3”

  • 2

    how do you tell the dimensions of a steel beam I.e. W12 X 45#

    The first number is the width of the beam, The second number is how many pounds per foot

  • 3

    pertaining to steel beams an S instead of a W means that the beam will be

    an I-beam

  • 4

    when installing stiffeners on I-joist, The stiffeners should be ___ shorter than the expected portion of the web so that they do not force the upper flange out of position

    1/8”

  • 5

    bridging is not generally required by code unless Joyce exceed ___ in depth

    2x12

  • 6

    blocking should be spaced no more than ___

    4”

  • 7

    for framing a stair well the rough opening must be at least ___ wide

    37”

  • 8

    A soffit is usually about ___ deeper (protruding into the room) than the cabinets so that the molding can be installed at the cabinet top

    2”

  • 9

    what is the most economical way to roof a house to weatherproof

    shed roof

  • 10

    What are the advantages of using roof truss instead of using traditional roofing rafters

    save money on materials, save on on-site labor

  • 11

    what is the most common roofing truss

    fink truss a.k.a. W truss

  • 12

    A standard interior jam is ___ wide

    4-9/16”

  • 13

    a rough door opening should be ___ wider and ___ higher than the door

    2”/2”

  • 14

    when talking about vertical intersections (roofing around stuff like chimney) The cap flashing is inserted ___ into the joints between bricks the joints are then filled with mortar

    1-1/2”

  • 15

    if gutter is over 60 foot in length what is required

    expansion joint/slip joint connector

  • 16

    in a gutter system a splash block should be at least blank long

    3’

  • 17

    suspension systems for gutters should be spaced ___ to ___ on center

    3’-4’

  • 18

    Three types of siding nails are

    Galvanize steel, Stainless steel, High tensile strength aluminum

  • 19

    The standard brick sizes are the same except for the width which are

    4”/3-1/4”

  • 20

    To permit acclamation floor and should always be stored in the building in which it will be installed for at least ___ or ___ days before being laid

    4/5

  • 21

    under laminate should be at least ___ thick and have a sanded of the surface

    1/4”

  • 22

    What type of fasteners are used in exterior basement or crawlspace walls such as knee walls construction

    type 304 or 316 stainless steel

  • 23

    which fasteners should not be used in below grade exterior basement/crawl space wall studs or fasteners used in knee wall construction

    Electro galvanized steel nails, Galvanized zinc coated steel staples

  • 24

    concrete shall be air entrained. call Eric content (percent by volume of concrete) shall be not less than ___ or more than ___

    5%/7%

  • 25

    What is the minimal thickness of crushed stone or coarse sand under a basement floor

    4”

  • 26

    A sump shall be not less than __ in diameter

    24”

  • 27

    in a crawlspace one ventilation open child be within ___ feet of each corner of the building

    3

  • 28

    veneer ties (sheet metal) shall support no more than ___ square feet pre tie

    2.67

  • 29

    additional veneer ties shall be provided around wall openings greater than ___ inches in either dimension

    16

  • 30

    What is the minimum thickness of a fireplace hearth?

    4 inches