construction 1.5
  • Sterling Thomas

  • 問題数 20 • 2/18/2024

    記憶度

    完璧

    3

    覚えた

    7

    うろ覚え

    0

    苦手

    0

    未解答

    0

    アカウント登録して、解答結果を保存しよう

    問題一覧

  • 1

    What type of contract requires the owner/architect to compile a list of total quantities as well as the contractor to provide the cost per unit to supply and install?

    unit price contract

  • 2

    What type of contract is used when the scope of work is poorly defined and/or to cover emergency repairs and renovations to occupied facilities?

    cost plus percentage of cost contract (Time and Materials)

  • 3

    What is true in regard to a cost plus/fee contract (Construction Management)?

    all the of above

  • 4

    What should you be sure to include in your contracts?

    all of the above

  • 5

    What is the most common type of contract used in residential construction?

    lump sum contract

  • 6

    What act requires prevailing wages to be paid out?

    The Davis-Bacon Act

  • 7

    Within how many days of being on the jobsite must the lg form be completed?

    3 days

  • 8

    A contract is not required if the job is under

    $1000

  • 9

    What STATE law regulates discrimination on the jobsite?

    The Elliott-Larsen Civil Rights Act

  • 10

    Homes built prior to what year require at least 1 smoke detector?

    1974

  • 11

    In reference of the lien law, what is the FIRST document that has to be filled out to continue the lien process?

    the notice of commencement

  • 12

    The findings/penalty of the Administrative Law Hearing Examiner are reported to

    all of the above

  • 13

    If the dispute cannot be resolved at the informal conference, where does it go next?

    the administrative law hearing examiner (also known as hearing officer/presiding officer)

  • 14

    Once the investigative unit receives a complaint, who do they verify the legitimacy of the complaint with?

    the building inspector of the local jurisdiction (city building department)

  • 15

    How many days after notification of a complaint does the respondent have to respond?

    15 days

  • 16

    What is it called when several business members come together to form a new business entity larger and financially stronger than if they acted alone?

    joint venture

  • 17

    What allows an individual to invest in a general partnership but have no input to how the partnership is operated?

    limited partnership

  • 18

    Which is NOT an advantage of a general partnership?

    each partner is liable for the business debts of the other partner

  • 19

    Which is NOT an advantage of sole proprietorship?

    owner is liable for all debts

  • 20

    Which of the following is true in regard to employing minors?

    D: both A and B