bldtc

29 questions • 2024-09-18
KRYZL CHARYNE MICU
Report

Question

provides a visual identification of the soil strata underlying the area by literally penetrating into the earth.

Answer

Question

process of establishing the point of building outlines or perimeters on the ground or site where the building is to be constructed

Answer

Question

are wooden sticks used as posts sharpened at one end and driven into the ground to serve as boundaries or support of the horizontal batter boards.are wooden sticks used as posts sharpened at one end and driven into the ground to serve as boundaries or support of the horizontal batter boards.

Answer

Question

are wood stick nailed horizontally to the stake to serve as the horizontal plane where the building technical measurements are established. It is installed horizontally to an elevation parallel with the ground floor line

Answer

Question

process of providing temporary supports to the structure or ground during the excavation

Answer

Question

horizontal displacement of vein or stratum

Answer

Question

sinking down, or sink to lower level

Answer

Question

the sinking or lowering of materials or structure.

Answer

Question

the operation of providing a permanent foundation in place of an inadequate footing

Answer

Question

Made from materials which must contain the proper proportions of lime, silica, alumina and iron components.

Answer

bldtc

TestMaker

Score

0 / 10

Correct rate

0%

Correct: 0

Incorrect: 0

Unanswered: 10

 
ankimaker.com

Question list

  • 1

    provides a visual identification of the soil strata underlying the area by literally penetrating into the earth.

    boring test

  • 2

    process of establishing the point of building outlines or perimeters on the ground or site where the building is to be constructed

    layout and staking

  • 3

    are wooden sticks used as posts sharpened at one end and driven into the ground to serve as boundaries or support of the horizontal batter boards.are wooden sticks used as posts sharpened at one end and driven into the ground to serve as boundaries or support of the horizontal batter boards.

    stake

  • 4

    are wood stick nailed horizontally to the stake to serve as the horizontal plane where the building technical measurements are established. It is installed horizontally to an elevation parallel with the ground floor line

    batter boards

  • 5

    process of providing temporary supports to the structure or ground during the excavation

    shoring

  • 6

    horizontal displacement of vein or stratum

    heave

  • 7

    sinking down, or sink to lower level

    subsidence

  • 8

    the sinking or lowering of materials or structure.

    settlement

  • 9

    the operation of providing a permanent foundation in place of an inadequate footing

    underpinning

  • 10

    Made from materials which must contain the proper proportions of lime, silica, alumina and iron components.

    portland cement

  • 11

    Same materials as normal Portland except in color

    white portland cement

  • 12

    been specially designed to produce better mortar than that made with normal Portland cement

    masonry cement

  • 13

    stable soil of adequate bearing capacity

    shallow foundation

  • 14

    plain or reinforced concrete

    spread footing

  • 15

    Is classified as a large footing extending over a wide area or the entire ground floor area of the building itsel

    mat

  • 16

    structural member of small cross-sectional area with reasonable length down into the ground by means of hammer or vibratory generators

    pile

  • 17

    refers to a large cross- sectional dimension,

    pier

  • 18

    reinforced concrete pile minus the metal casing or shell thereby reducing the cost of construction.

    uncased pile

  • 19

    is a concrete cased inside a metal shell form left underground.

    cased pile

  • 20

    – are reinforced to resist high impact pressure from a driving hammer.

    precast pile

  • 21

    excellent in penetrating into hard rocks

    h pile

  • 22

    suitable materials for piles on sliding banks or in deep water

    box pile

  • 23

    grouped into 3 rails and welding together at the head and base form a unit pile.

    rail pile

  • 24

    is a structural box or chamber that is sunk in place or built in place by excavating systematically below the bottom of the unit that descends to the final depth.

    caisson

  • 25

    maybe the box of the pile type. The top and bottom are open during installation.

    open caisson

  • 26

    has the top and side sealed and used compressed air to prevent water and soil from entering the lower chamber.

    pneumatic caisson

  • 27

    special type of foundation applied in location where deep deposits of compressible cohesive soil exist and the use of pile is impractical

    floating foundation

  • 28

    Wall footings is a strip of reinforced concrete wider than the wall which distributes the load to the soil

    wall footing

  • 29

    kind of footing represents the simplest and most economical type usually in the form of: a

    isolated footing