  • 1

    Who is responsible for section between signal and first detonator

    signaller

  • 2

    Who is responsible for section between dets and work site marker with red flashing lights

    PICOP

  • 3

    Who is responsible for section between red flashing lights on work site marker board (start) and work site marker board flashing yellow lights(exit)

    engineering supervisor or safe work leader

  • 4

    Who is responsible for section after passing yellow flashing lights and detonators

    PICOP

  • 5

    Once dets have been removed after exiting work site, who’s permission do you need to move

    signaller

  • 6

    Who’s permission do you need to pass yellow flashers to move towards dets

    PICOP

  • 7

    What is speed limit approaching or within possession (not worksite)

    25

  • 8

    What is speed limit within worksite

    5

  • 9

    What colour is armband/badge to identify PICOP

    red letters yellow background

  • 10

    What colour armband/badge for engineering supervisor

    blue letters yellow background

  • 11

    What colour safe work leader armband/badge

    blue letters yellow background

  • 12

    Who must driver PERSONALLY contact to enter or leave possession

    signaller

  • 13

    What does PICOP stand for

    person in charge of possession

  • 14

    What do you get in line with the middle det at each end of possession

    possession limit board

  • routes

    routes

    john collins · 58問 · 1年前

    routes

    routes

    58問 • 1年前
    john collins

    rules dc

    rules dc

    john collins · 5問 · 1年前

    rules dc

    rules dc

    5問 • 1年前
    john collins

    rules ac

    rules ac

    john collins · 11問 · 1年前

    rules ac

    rules ac

    11問 • 1年前
    john collins

    rules g1 pts

    rules g1 pts

    john collins · 9問 · 1年前

    rules g1 pts

    rules g1 pts

    9問 • 1年前
    john collins

    rules m3 managing incidents, floods,snow

    rules m3 managing incidents, floods,snow

    john collins · 9問 · 1年前

    rules m3 managing incidents, floods,snow

    rules m3 managing incidents, floods,snow

    9問 • 1年前
    john collins

    rules p1 single line working

    rules p1 single line working

    john collins · 19問 · 1年前

    rules p1 single line working

    rules p1 single line working

    19問 • 1年前
    john collins

    rules sp speeds

    rules sp speeds

    john collins · 5問 · 1年前

    rules sp speeds

    rules sp speeds

    5問 • 1年前
    john collins

    rules m1 dealing with accident evacuation

    rules m1 dealing with accident evacuation

    john collins · 17問 · 1年前

    rules m1 dealing with accident evacuation

    rules m1 dealing with accident evacuation

    17問 • 1年前
    john collins

    rules m2 train stopped by failure

    rules m2 train stopped by failure

    john collins · 10問 · 1年前

    rules m2 train stopped by failure

    rules m2 train stopped by failure

    10問 • 1年前
    john collins

    rules ss2 shunting

    rules ss2 shunting

    john collins · 6問 · 1年前

    rules ss2 shunting

    rules ss2 shunting

    6問 • 1年前
    john collins

    rules tw5 defective

    rules tw5 defective

    john collins · 10問 · 1年前

    rules tw5 defective

    rules tw5 defective

    10問 • 1年前
    john collins

    rules tw1 prep and movement

    rules tw1 prep and movement

    john collins · 19問 · 1年前

    rules tw1 prep and movement

    rules tw1 prep and movement

    19問 • 1年前
    john collins

    RLU AND FLU TEST

    RLU AND FLU TEST

    john collins · 5問 · 1年前

    RLU AND FLU TEST

    RLU AND FLU TEST

    5問 • 1年前
    john collins

    SHUNTING

    SHUNTING

    john collins · 18問 · 1年前

    SHUNTING

    SHUNTING

    18問 • 1年前
    john collins

    問題一覧

  • 1

    Who is responsible for section between signal and first detonator

    signaller

  • 2

    Who is responsible for section between dets and work site marker with red flashing lights

    PICOP

  • 3

    Who is responsible for section between red flashing lights on work site marker board (start) and work site marker board flashing yellow lights(exit)

    engineering supervisor or safe work leader

  • 4

    Who is responsible for section after passing yellow flashing lights and detonators

    PICOP

  • 5

    Once dets have been removed after exiting work site, who’s permission do you need to move

    signaller

  • 6

    Who’s permission do you need to pass yellow flashers to move towards dets

    PICOP

  • 7

    What is speed limit approaching or within possession (not worksite)

    25

  • 8

    What is speed limit within worksite

    5

  • 9

    What colour is armband/badge to identify PICOP

    red letters yellow background

  • 10

    What colour armband/badge for engineering supervisor

    blue letters yellow background

  • 11

    What colour safe work leader armband/badge

    blue letters yellow background

  • 12

    Who must driver PERSONALLY contact to enter or leave possession

    signaller

  • 13

    What does PICOP stand for

    person in charge of possession

  • 14

    What do you get in line with the middle det at each end of possession

    possession limit board