  • 1

    It means specific duties imposed upon a person to care or to provide for another including liability for personal obligations as granted through a Power of Attorney or Court Order

    Responsibility

  • 2

    Contract Documents

    Agreement General Conditions Special Provisions Specifications Drawings

  • 3

    Is the contract between the owner and the contractor undertaking thr project described in the Contract Documents including all supplemental agreements thereto and all general and special provisions pertaining to the work or materials therefore.

    Agreement

  • 4

    Is additional information on contract documents issued to bidders before date of bidding.

    Bid Bulletin

  • 5

    The list of instructions stipulating the matter on how bids are to be prepared and conditions for the award of contract

    Instruction to Bidders

  • 6

    Are graphical representations of the work involved in the project. They include all supplementary details and shop drawings

    Drawings

  • 7

    As printed documents stipulating the procedural and administrative aspects of the contract.

    General Conditions

  • 8

    Are instructions which may be issues prior to the bidding to supplement and/or modify the drawings, specifications, and/or General Conditions of the contract.

    Special Provisions

  • 9

    Are written or printed descriptions of work to be done describing qualities of material and mode of construction.

    Specifications

  • 10

    Are additional information which may be issued as an addition or amendment to the provisions of the specifications.

    Supplementary Specifications

  • 11

    Is an outline specification enumerating the type or trade names of materials used

    Schedule of Materials and Finishes

  • 12

    Is a listing of the different parts of the work indicating in each part of the corresponding value in materials and labor, including an allowance for profit and overhead.

    Breakdown of Work and Corresponding Value

  • 13

    Means information, advice a notification pertinent to the project delivered in person or sent by registered mail to the individual, firm or corporation at the last known business of such individual, firm or corporation.

    Written Notice

  • 14

    is the duration of time allowed by the contract for the completion of the project in any stipulated portions thereof

    Time Limits

  • 15

    Includes labor or materials or both as well as equipment, transportation, or other facilities necessary to commence and complete the construction called for in the Contract

    Work

  • 16

    Purchase and/or fabricate and deliver to the jobsite or other locations when so designated

    Furnish

  • 17

    shall mean to build in, mount positions, connect or apply any object specified ready for the intended use.

    Install

  • 18

    Shall be understood to mean "Furnish and Install"

    Provide

  • 19

    Shall mean as required or necessary for the complete execution of that portion of the work.

    Required or Necessary

  • Geotech Quiz 1

    Geotech Quiz 1

    John Rotrix Tumaneng · 38問 · 2年前

    Geotech Quiz 1

    Geotech Quiz 1

    38問 • 2年前
    John Rotrix Tumaneng

    IE First LE

    IE First LE

    John Rotrix Tumaneng · 26問 · 2年前

    IE First LE

    IE First LE

    26問 • 2年前
    John Rotrix Tumaneng

    Laws

    Laws

    John Rotrix Tumaneng · 15問 · 2年前

    Laws

    Laws

    15問 • 2年前
    John Rotrix Tumaneng

    Hydro LE 1

    Hydro LE 1

    John Rotrix Tumaneng · 20問 · 2年前

    Hydro LE 1

    Hydro LE 1

    20問 • 2年前
    John Rotrix Tumaneng

    SOCSC MIDTERMS

    SOCSC MIDTERMS

    John Rotrix Tumaneng · 30問 · 2年前

    SOCSC MIDTERMS

    SOCSC MIDTERMS

    30問 • 2年前
    John Rotrix Tumaneng

    GEOTECH FORMULAS

    GEOTECH FORMULAS

    John Rotrix Tumaneng · 19問 · 2年前

    GEOTECH FORMULAS

    GEOTECH FORMULAS

    19問 • 2年前
    John Rotrix Tumaneng

    SOCSC LE1

    SOCSC LE1

    John Rotrix Tumaneng · 57問 · 2年前

    SOCSC LE1

    SOCSC LE1

    57問 • 2年前
    John Rotrix Tumaneng

    CE101 LE2 CHAP3

    CE101 LE2 CHAP3

    John Rotrix Tumaneng · 17問 · 2年前

    CE101 LE2 CHAP3

    CE101 LE2 CHAP3

    17問 • 2年前
    John Rotrix Tumaneng

    CE101 LE2CHAP4

    CE101 LE2CHAP4

    John Rotrix Tumaneng · 7問 · 2年前

    CE101 LE2CHAP4

    CE101 LE2CHAP4

    7問 • 2年前
    John Rotrix Tumaneng

    SOCSCI FE

    SOCSCI FE

    John Rotrix Tumaneng · 36問 · 2年前

    SOCSCI FE

    SOCSCI FE

    36問 • 2年前
    John Rotrix Tumaneng

    Hum01 FE

    Hum01 FE

    John Rotrix Tumaneng · 21問 · 2年前

    Hum01 FE

    Hum01 FE

    21問 • 2年前
    John Rotrix Tumaneng

    IE FINAL EXAM

    IE FINAL EXAM

    John Rotrix Tumaneng · 10問 · 2年前

    IE FINAL EXAM

    IE FINAL EXAM

    10問 • 2年前
    John Rotrix Tumaneng

    GEOTECH FE

    GEOTECH FE

    John Rotrix Tumaneng · 18問 · 2年前

    GEOTECH FE

    GEOTECH FE

    18問 • 2年前
    John Rotrix Tumaneng

    CE 161 FIRST LE

    CE 161 FIRST LE

    John Rotrix Tumaneng · 29問 · 1年前

    CE 161 FIRST LE

    CE 161 FIRST LE

    29問 • 1年前
    John Rotrix Tumaneng

    CE 190

    CE 190

    John Rotrix Tumaneng · 25問 · 1年前

    CE 190

    CE 190

    25問 • 1年前
    John Rotrix Tumaneng

    CE 161 2ND LE

    CE 161 2ND LE

    John Rotrix Tumaneng · 64問 · 1年前

    CE 161 2ND LE

    CE 161 2ND LE

    64問 • 1年前
    John Rotrix Tumaneng

    ENGG101 SECOND LE

    ENGG101 SECOND LE

    John Rotrix Tumaneng · 55問 · 1年前

    ENGG101 SECOND LE

    ENGG101 SECOND LE

    55問 • 1年前
    John Rotrix Tumaneng

    Quiz 3

    Quiz 3

    John Rotrix Tumaneng · 14問 · 1年前

    Quiz 3

    Quiz 3

    14問 • 1年前
    John Rotrix Tumaneng

    問題一覧

  • 1

    It means specific duties imposed upon a person to care or to provide for another including liability for personal obligations as granted through a Power of Attorney or Court Order

    Responsibility

  • 2

    Contract Documents

    Agreement General Conditions Special Provisions Specifications Drawings

  • 3

    Is the contract between the owner and the contractor undertaking thr project described in the Contract Documents including all supplemental agreements thereto and all general and special provisions pertaining to the work or materials therefore.

    Agreement

  • 4

    Is additional information on contract documents issued to bidders before date of bidding.

    Bid Bulletin

  • 5

    The list of instructions stipulating the matter on how bids are to be prepared and conditions for the award of contract

    Instruction to Bidders

  • 6

    Are graphical representations of the work involved in the project. They include all supplementary details and shop drawings

    Drawings

  • 7

    As printed documents stipulating the procedural and administrative aspects of the contract.

    General Conditions

  • 8

    Are instructions which may be issues prior to the bidding to supplement and/or modify the drawings, specifications, and/or General Conditions of the contract.

    Special Provisions

  • 9

    Are written or printed descriptions of work to be done describing qualities of material and mode of construction.

    Specifications

  • 10

    Are additional information which may be issued as an addition or amendment to the provisions of the specifications.

    Supplementary Specifications

  • 11

    Is an outline specification enumerating the type or trade names of materials used

    Schedule of Materials and Finishes

  • 12

    Is a listing of the different parts of the work indicating in each part of the corresponding value in materials and labor, including an allowance for profit and overhead.

    Breakdown of Work and Corresponding Value

  • 13

    Means information, advice a notification pertinent to the project delivered in person or sent by registered mail to the individual, firm or corporation at the last known business of such individual, firm or corporation.

    Written Notice

  • 14

    is the duration of time allowed by the contract for the completion of the project in any stipulated portions thereof

    Time Limits

  • 15

    Includes labor or materials or both as well as equipment, transportation, or other facilities necessary to commence and complete the construction called for in the Contract

    Work

  • 16

    Purchase and/or fabricate and deliver to the jobsite or other locations when so designated

    Furnish

  • 17

    shall mean to build in, mount positions, connect or apply any object specified ready for the intended use.

    Install

  • 18

    Shall be understood to mean "Furnish and Install"

    Provide

  • 19

    Shall mean as required or necessary for the complete execution of that portion of the work.

    Required or Necessary