暗記メーカー
ログイン
CE 161 LE 2
  • John Rotrix Tumaneng

  • 問題数 84 • 4/20/2024

    記憶度

    完璧

    12

    覚えた

    31

    うろ覚え

    0

    苦手

    0

    未解答

    0

    アカウント登録して、解答結果を保存しよう

    問題一覧

  • 1

    The act of missing deadlines when managing a task or series of tasks in other words delay

    Slippage

  • 2

    5 pillars of construction ( 5M's)

    Manpower Methods Machinery Material Management

  • 3

    The driving force behind every organization

    Management team

  • 4

    Administration ( defined as the process or activity of running a business, organization, etc.) of the construction procedure is most often times difficult

    Construction Management by Max B. Fajardo

  • 5

    In order to repair the damage incurred on either party, there must be a __________

    Liability for damages

  • 6

    Bid/Tender

    Pre-bid Bid Awarding (Notice to Proceed)

  • 7

    Liabilities in the context of disputes and arbitrations

    Fraud Negligence Delay

  • 8

    Construction Project Phasing (a.)

    Art, Science, Business of a Building

  • 9

    Intangible Elements

    Goodwill Brand Recognition Public Promotion Reputation

  • 10

    How many months for litigation

    6 Months

  • 11

    EO 1008

    to establish an arbitration machinery in the construction industry to resolve disputes arising from construction contracts.

  • 12

    Actual losses or unrealized profit (Liability for Damages)

    Actual

  • 13

    Involvement of Mediator

    A third party, the mediator facilitates the process but parties are in control of content and outcome.

  • 14

    Submission of disputes by consensual agreement to a third party for a binding decision

    Arbitration

  • 15

    Construction Milestones

    1. Establishment of References 2. Ground Breaking (Checking Dimensions of Footing) (Laying Cornerstone) 3. Construction Pouring 4. Topping (Off/Out) 5. Water Tightness 6. Energization 7. Close Out (Testing and Commissioning)

  • 16

    Kaslang functional organization nga based on specialty yem agpapada da ubraen each division for project

    Project organization

  • 17

    Key Professionals(Management Team)

    Client/Developer/Owner Design Operations Manager Contractor

  • 18

    to establish an arbitration machinery in the construction industry to resolve disputes arising from construction contracts.

    EO 1008

  • 19

    Contruction Project Phasing (b)

    the process of building

  • 20

    GENSITCOMAMEWOTHEDOFINSEFSCOMSELEC

    nigga

  • 21

    Involvement of Arbitrator

    A third party, the arbitrator, controls content and outcome of proceedings but parties control choice of arbitrator, language, time, venue applicable law and procedural rules.

  • 22

    PCAB

    Philippine Contractors Accreditation Board

  • 23

    How are construction conflicts settled?

    Exemplary Nominal Temperate Liquidated

  • 24

    It is defined as the process of translating the arrow diagram into time table of calendar days

    Scheduling

  • 25

    CIAC

    Construction Industry Arbitration Commission

  • 26

    A group of professionals working together to balance, cost, quality and schedule

    Management Team

  • 27

    Administration service which are over and beyond the normal service of all project phases

    Project Management

  • 28

    Alternative Dispute Resolution(Law)

    RA 9285

  • 29

    What is a project

    A project is a temporary endevour undertaken to create a unique product, service or result.

  • 30

    Construction

    Preliminaries Temporary Facilities/Utilities Establish References Excavation(Siteworks) Construction Sequence Project Management Meeting Turnover

  • 31

    Alternative Dispute Resolution act of _____

    2004

  • 32

    What is Liquidated (method of repair)

    By agreement of both parties as predetermined by the contract/service agreement stipulations

  • 33

    The General Conditions

    CIAP Document 102

  • 34

    Tangible elements

    Monetary Assets Stocks or Market Sales Fixtures

  • 35

    Is an individual or organization specializing in construction management or practicing it on a particular project as part of a project management team that also includes an owner and a design organization.

    Construction Manager

  • 36

    Is the process of devising of workable scheme of operations that, when, put into action, will accomplish an established objective.

    Planning

  • 37

    How many Days...File Case (CIAC)

    0

  • 38

    Organization nga naka divide da iti based on specialty yem agpapada da ti specialty naidivide lang

    Division Organization

  • 39

    The construction Phase according to the 2012 MasterFormat Version

    General Requirements Site Works/Civil Works Concrete Masonry Metals Woods and Plastics Thermal and Moisture Protection Doors and Windows Finishes Specialties Equipment Furnishes Special Construction Conveying Systems Mechanical Electrical

  • 40

    Nominal (settlement of construction conflicts)

    Can be assessed

  • 41

    Main sources of dispute in Construction(2)

    2. Delays(whether excusable or inexcusable)

  • 42

    Culpa

    Negligence

  • 43

    Negotiation with assistance of a third party

    Mediation

  • 44

    Contruction Industry Authority of the Philippines (CIAP) (LAW)

    PD 1746

  • 45

    What is CIAP for?

    a juridical executive department similar function as to the DTI, that is specially tasked for the construction industry.

  • 46

    CIAP

    Construction Industry Authority of the Philippines

  • 47

    different kinds of organization

    Organic Functional Divisional Matrix Project Virtual Line Line and Staff

  • 48

    Failure to satisfy or meet the ends of the contract by either of the parties is a ground for _____.

    Liabilities

  • 49

    Means to fast tract or expedite; cure for Slippage

    Crash

  • 50

    dolo

    Fraud

  • 51

    Litigation

    Process of making a civil claim in a court of Law

  • 52

    How many days for Mediation

    14 Days

  • 53

    How many days for Arbitration

    14 Days

  • 54

    Main sources of dispute in construction(1)

    1. Variations without written agreement or consent of both or concerned parties. a.) Alteration to the Design(plan) b.) Alterations to the Quantities c.) Alteration to the Quality of Materials d.) Alterations in Working Conditions e.) Alterations to the sequence of work

  • 55

    The terms of references

    CIAP Document 101

  • 56

    Involvement of Attorney(The Judge) Litigation

    A third party, the judge controls outcome of proceedings, parties have no control over choice of Judge, language, time, venue of processing and procedural rules.

  • 57

    Mora

    Delay

  • 58

    As seen in a sample contract DISPUTE AND ARBITRATIONS

    All questions in dispute under this Agreement shall be submitted in accordance with the provisions of R.A. No. 9285, otherwise known as the Alternative Dispute Resolution(ADR) Act of 2004 and as provided for under E.O. No.1000, governing Construction(and consulting) Industry Arbitration, as well as Art. 2042 of the New Civil Code

  • 59

    Contruction Project Phasing (c)

    Manner in which materials are assembled(Assembly)

  • 60

    Refers to a collection of projects, group of related projects, and other groups of activites that are organized together to meet strategic business objectives ( PMI, 2014)

    Portfolio

  • 61

    Mediation

    Negotiation with assistance of a third party(the mediator)

  • 62

    Definite Beginning and End

    Temporary Endeavor

  • 63

    Projects drive change. From a business perspective, a project is aimed at moving an organization from one state to another to achieve a specific objective.

    Undertaking

  • 64

    Is a disagreement, argument, or controversy-often one that gives rise to a legal proceeding(such as arbritation, mediation, or a lawsuit). The opposing parties are said to be averse to one another(see also adverse party).

    Dispute

  • 65

    Projects enable business creation Tangible element and Intangible Elements

    Creation

  • 66

    PD 1746

    Construction Industry Authority of the Philippines(CIAP)

  • 67

    Amount of free time for an activity when all other preceding activities starts on early start

    Free Float

  • 68

    What is Construction Management? by Max b. Fajardo

    Administration ( defined as the process or activity of running a business, organization, etc.) of the construction procedure is most often times difficult

  • 69

    Post-Construction

    Repair Maintenance Renovation

  • 70

    Organization nga divided iti members na focusing on their different specialty

    Functional Organization

  • 71

    Construction Project Phasing (4)

    1. Predesign 2. Bid/Tender 3. Construction 4. Post-Construction

  • 72

    Process of making a civil claim in a court of Law

    Litigation

  • 73

    Predesign

    Prefeasibility Feasibility Schematic Conseptual Design Development Contract Document

  • 74

    Arbitration

    Submission of disputes by consensual agreement to a third party(the arbitrator) for a binding decision

  • 75

    Philippines Licensing Board for Contractors(PCAB)(Law)

    RA 4566

  • 76

    Exemplary (settlement of construction conflicts)

    Corrective

  • 77

    is defined as the formal arrangement that is established to coordinate all activities in order to implement a given strategy.

    Construction Organization

  • 78

    Identify the provision of the civil code that stipulates the liability of the engineer or architect who drew up the plans and specifications for a building is liable for damages if within 15 years from the completion of structure, it collapses by reason of defect in plans and specification

    article 1723

  • 79

    What is a Dispute?

    A dispute is a disagreement, argument, or controversy-often one that gives rise to a legal proceeding(such as arbitration,mediation, or a lawsuit). The opposing parties are said to be averse to one another(see also adverse party).

  • 80

    Defined as a group of related projects managed in a coordinated manner to obtain benefits and control not available from managing them individually (PMI, 2014)

    Program

  • 81

    By agreement of both parties as predetermined by the contract/service agreement stipulations

    Liquidated

  • 82

    Administrative service with the objective of achieving high project quality at a minimum cost

    Construction Management

  • 83

    mental and physical anguish(reputation and sleepless nights, stress, anxiety, etc) (Liability for Damages)

    Moral

  • 84

    A group of individuals who are cooperating willingly and effectively to achieve a common goal

    Organization