1
What size is UPS 2A and B?
400 Kw
2
What size are the Critical Chillers (Air cooled)
770 Kw
3
What number Risers are Life safety Electrical risers?
26,27
4
What size are the sprinkler tanks?
130000 L
5
What size are the Drinking tanks?
4000 L
6
What AHU’s have extracts?
1,2,3,4
7
What does UPS 1A and B feed?
Data centre
8
What do level 8 Calorifiers feed?
Kitchen
9
What does AHU 5 supply?
Basement
10
What size are the kitchen water tanks?
200 L
11
What size are the Blended tanks?
84000 L
12
What does AHU 9 supply
Kitchen
13
what riser are the Calorifiers in?
31
14
What should the sprinkler pumps be on low?
6.2
15
What AHU’s supply the North side of the building?
3 & 4
16
What size are the Sprinkler pumps?
55Kw
17
How are the level 8 Calorifiers heated?
Heating element (electrical)
18
How is level 9 calorifier heated?
Gas
19
What does AHU 6 supply
LG Changing rooms
20
Where are the BMS Outstations
Risers 17/18
21
What risers are the Calorifiers in?
31
22
What should the sprinkler pumps be on high?
12.5
23
What size are the Chillers (Water cooled)
800 Kw
24
What KVA are the Generators?
1000 KVA
25
What Riser numbers are Tenant electrical risers?
17,18,19
26
How many extract fans are there in the building? (Excluding smoke extracts and AHU extracts)
3
27
What does AHU 7 supply?
Entrance
28
What does UPS 2A and B feed?
Traders Floor and IDF rooms on all floors
29
After the first smoke head damper activation how many fans will be running?
2
30
What floors ALWAYS evacuate in a fire alarm (real)?
Roof, Basement floor where call point or smoke head was activated, and 1 above and below
31
What size is UPS 1a and b?
300 Kw
32
How many ACU’s are there?
4
33
What size are the generators
800 Kw
34
What AHU’s supply the South side of the building
1 & 2
35
What does level 9 calorifier feed?
All showers and WHB
36
What is the CRAH code?
1490
37
What does AHU 8 supply?
Building management suite