問題一覧
1
Resources can’t be storable or nonstorable
false
2
When you are making a project your goal is to have the lowest return with the highest possible cost
false
3
The plan that ensures that the project will meet the requirements of the person that has asked you to do the project is the
quality plan
4
A Project has a .
start and end point
5
Resources can include people, equipment and facilities
true
6
The plan which keeps all stakeholders informed about the progress of the project is the
communication plan
7
Means one activity must finish before another can start
finish to start relationship
8
Setting a deadline is important because it can provide a tremendous sense of accomplishment besides it can prevent an overhead work schedule
true
9
The plan that makes a detailed assessment of the required resources is the
Resources plan
10
In a Gantt chart
you can insert as many tasks as you want
11
The plan that list the cost of the resources on a project is the
financial plan
12
It’s important for a Project to have a
defined set of objectives
13
The project manager has equal responsibilities to all members
true
14
Each Project has
its own schedule.
15
A deadline is a set date that you have to deliver your work by
true
16
You are able to make changes in a chart that
you have already created.
17
With a Gantt chart you can present tasks and their relationships and also add priority levels.
true
18
Some tasks
can be done at the same time.
19
Planning a project is listing tasks, Scheduling and assigning tasks to people.
true
20
The plan that breaks the project down into smaller activities is the
project plan