    問題一覧

  • 1

    a disagreement that give rise to a legal proceeding

    Dispute

  • 2

    The driving force behind every organization

    Management Team

  • 3

    dispute resolution facilitated by a 3rd party who controls the outcome with a binding decision

    Arbitration

  • 4

    the professional practice of leading people and managing processes as applied to the planning design and exucution of construction projects for the purpose of successful completion of the project

    Construction Management

  • 5

    additional legal obligations such as reparation for consequential damages that arise from the contract

    Liabilities

  • 6

    the provision of the civil code that stipulates that liability of an engineer or architect who drew the plans and specifications for a bldg is liable for damages if within 15 years from the completion of the structure, it collapses by a reason of defect in plans and specifications

    Article 1723

  • 7

    two main sources of construction disputes

    Variation without written agreement, Delay

  • 8

    an amount spelled out in advance in the contract paid to one of the parties for intangible losses

    Liquidated Damages

  • 9

    A corrective method for repair of liabilities arising from conflicts in any contract

    Exemplary

  • 10

    A group of professionals that was established to coordinate all activities in order to implement a given strategy in a construction project

    Construction Management Group

  • 11

    Alternative Dispute Resolution Law

    Republic Act 9285

  • 12

    the law that established the Construction Industry Arbitration of the Philippines (CIAP)

    Presidential Decree 1746

  • 13

    The law that established the Construction Industry Arbitration Commission

    Executive Order 1008

  • 14

    the law that created the Philippine Construction Licensing Board (PCAB)

    Republic Act 4566

  • 15

    the provision of the Civil Code that stipulates the liablity of the contractor for the damages if the efidice falls, with the same period, on account of defects in the construction or the sue of materials of inferior quality by him, or due to any violation of the terms of the contract

    Article 1723

  • 16

    A method of repair for liabilities arising from conflicts in which the damage can be assessed or quantified

    Nominal

  • 17

    Refers to the collection of projects, groups of related projects and other groups of activities that are organized together to meet strategic business activities (PMI, 2014)

    Portfolio Management

  • 18

    Scoping of Work packages to various labor sublets, material suppliers, etc.

    Contract Admin

  • 19

    Define as a group of related projects managed in a coordinated manner to obtain benefits and control not available from managing the individually (PMI, 2014)

    Program Management

  • 20

    A group of individuals who are cooperating willingly and effectively to achieve a common goal

    Organization

  • 21

    Negotations with the assistance of a third party whi facilitates the process but has no control over the outcome of the dispute resolution

    Mediation

  • 22

    A group of professionals working together to balance cost, quality, and schedule

    Management Team

  • 23

    Administration Service with the objdctive of achieving high project quality at a minimum cost

    Construction Management

  • 24

    Administration Service which are over and beyond the normal services of all project phases

    Project Management

  • 25

    A temporary endeavor undertaken to create a unique product, service or result

    Project

  • 26

    The objectives are met

    Success

  • 27

    The objectives will not or cannot be met

    Change in Direction

  • 28

    Funding is exhausted or no longer available for allocation to the project

    Bankruptcy

  • 29

    The need for the project no longer exists

    Change in Priority

  • 30

    The human or physical respurces are no longer available

    Lack of Manpower

  • 31

    The project is terminated for legal cause or convenience

    Legal Termination or End-o

  • 32

    The net quantifiable benefit derived from a business endeavor

    Business Value

  • 33

    The process of devising of workable scheme of operations

    Planning

  • 34

    translating the arrow diagram into time table of calendar days

    Scheduling

  • 35

    flexibility and update re-computations brought about hy changing conditions

    Controlling and Monitoring

  • 36

    The work operations required to complete a task

    Activity

  • 37

    A point in time signifying the beginning or end of one or more activities

    Events

  • 38

    Arrow on a network showing the dependent relationship between 2 activities

    Dummy Activity

  • 39

    The time it takes an activity to be finished

    Duration of an Activity

  • 40

    The sequence of activities the leads from the starting node to the finishing node

    Path