ログイン

project management
331問 • 8ヶ月前
  • ユーザ名非公開
  • 通報

    問題一覧

  • 1

    Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

    Risk

  • 2

    A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

    10 days and $3,200

  • 3

    While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

    Have a meeting with the project sponsor and main stakeholders.

  • 4

    Which of the following tools is best to use for storing lessons learned?

    Wiki knowledge base

  • 5

    During a executive call , A project sponsor found out about issues with the project but could not provide next steps. What needs to be revised?

    Communication plan

  • 6

    During project initiation, a PM is drafting a document with high-level goals and requirements. What is this document?

    Preliminary scope statement

  • 7

    Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

    Validating the deliverables

  • 8

    A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps. Which of the following is the current status of the process?

    The process is out of control and should be revised

  • 9

    A project manager provided details regarding the completion of the following tasks: Vendor selection took less time than planned. Equipment procurement took less time than estimated. Equipment installation went according to schedule. Which of the following should the project manager update?

    Project Gantt

  • 10

    During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

    Gantt chart

  • 11

    A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

    Scope creep

  • 12

    A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?

    Project sponsor

  • 13

    A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

    Time and materials contract

  • 14

    Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?

    Multitiered architecture project

  • 15

    A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

    RFP

  • 16

    During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

    Change log

  • 17

    Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

    Sprint review

  • 18

    Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

    Rollback plan

  • 19

    An enhancement is set to be released into production, and availability issues need to be avoided. Before the release, which of the following should be the most important consideration?

    risk assessnent

  • 20

    A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

    Focus group

  • 21

    A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

    Monthly feedback and training sessions

  • 22

    Which of the following is a quantitative key performance indicator?

    The workers complete tasks on average 25% faster using a new application.

  • 23

    Which of the following software programs would be best to use to store information related to business transactions?

    Enterprise resource planning

  • 24

    Which of the following tools is best to use when conducting project meetings across time zones?

    Videoconference

  • 25

    During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

    defect log

  • 26

    A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

    Defect log

  • 27

    By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

    establish baselines

  • 28

    During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

    Pareto chart

  • 29

    How does data discovery assist with data classification'?

    It shows where specific data is stored

  • 30

    A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

    Agile

  • 31

    During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

    SOW

  • 32

    A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

    A transition plan

  • 33

    During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

    option A

  • 34

    A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

    Proposal

  • 35

    A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

    Project network diagram

  • 36

    Which of the following is a potential challenge that may arise from language barriers among a project team?A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

    A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

  • 37

    A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

    Revise the communication plan.

  • 38

    A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

    Project quality assurance

  • 39

    A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

    Update the issue log.

  • 40

    Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

    Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution

  • 41

    After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

    Smoke test

  • 42

    During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

    Work with the project scheduler to update the project timeline

  • 43

    A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

    Closing contracts

  • 44

    Which of the following are primary features provided by a standard laaS solution? (Select two).

    Storage, Networking

  • 45

    A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

    Pareto

  • 46

    Which of the following best describes the difference between the current state and the desired future state in project management?

    The current state is where the business is now, and the desired state is where the project is going to take the business.

  • 47

    A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

    Smoke

  • 48

    A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

    Data management, Document management

  • 49

    Which of the following is the best example of a breach of physical security?

    Project documentation that is only kept on a removable device

  • 50

    After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

    Have a meeting with the project sponsor to discuss the situation.

  • 51

    A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

    Identify business needs and product descriptions.

  • 52

    A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

    Acceptable communication channels

  • 53

    Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

    Avoiding

  • 54

    During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

    Schedule a call with the vendor PM and vendor executive to review the statement of work

  • 55

    After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

    Customer notification

  • 56

    The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

    Complete the project sign-off.

  • 57

    A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

    Country legal regulations

  • 58

    Which of the following is a consideration when determining a project's ESG factors?

    Corporate values compliance

  • 59

    Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

    Confronting

  • 60

    A project coordinator has started a new project and is reviewing the following characteristics provided by the customer: • Two developers • High uncertainty about existing systems • Risk of frequent requirement changes • Tight deadlines Which of the following project methodologies would be best to use in this situation?

    Scrum

  • 61

    A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

    Time and materials contract

  • 62

    Which of the following software programs would be BEST to use lo store information related to business transactions?

    Customer relationship management

  • 63

    Which of the following aspects are true of waterfall as compared to agile? (Select two).

    In waterfall, solution validation occurs later in the development cycle, Waterfall is less tolerant to changes in scope.

  • 64

    While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

    Contact the PMO for assistance.

  • 65

    During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

    Traceability matrix

  • 66

    A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

    RACI

  • 67

    A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

    Subscription

  • 68

    While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

    Encourage the use of the chat and use plain language when speaking

  • 69

    A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

    Removing access

  • 70

    A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

    Limit access to members of the project team.

  • 71

    During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

    Issue log

  • 72

    Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?

    To ensure that all stakeholders have a shared understanding of the project's objectives

  • 73

    A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?

    The project is ahead of schedule and over budget.

  • 74

    A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

    Meeting minutes

  • 75

    A meeting agenda included the following items: . Review the goals of the project. . Review the progress of the project. . Discuss if the project is ready to move forward. Which of the following best describes this type of meeting?

    Gate review

  • 76

    A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

    Assign additional resources to prevent overwork.

  • 77

    A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

    Informative

  • 78

    A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

    Finish-to-start

  • 79

    Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

    Distribute an agenda.

  • 80

    A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

    SaaS

  • 81

    An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

    The system is lacking proper access controls.

  • 82

    A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

    Ticketing system

  • 83

    A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

    Waterfall

  • 84

    A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

    Stress testing

  • 85

    Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

    Operational security

  • 86

    A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

    laaS

  • 87

    A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

    Use only full-time employees even if the project is delayed

  • 88

    Which of the following best represents an intellectual property breach?

    A service provider that worked on a project uses the developed software on a project for a new customer.

  • 89

    A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

    Perform a gap analysis.

  • 90

    During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

    Quality assurance

  • 91

    Which of the following is an intended outcome of a stand-up meeting?

    To identify blocking tasks

  • 92

    Which of the following pieces of data are examples of Pll?

    IP address and email address

  • 93

    Which of the following is the most important activity for the project manager during the closure of a project?

    Obtain project sign-off.

  • 94

    A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

    Risk, issue

  • 95

    A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

    Decision tree

  • 96

    A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

    Downtime window schedule

  • 97

    A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

    Revise the communication plan.

  • 98

    Which of the following requires the MOST availability from the business team?

    Scrum

  • 99

    For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

    RACI chart

  • 100

    A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

    Backlog

  • cryptogrophy

    cryptogrophy

    ユーザ名非公開 · 50問 · 1年前

    cryptogrophy

    cryptogrophy

    50問 • 1年前
    ユーザ名非公開

    crypto pretest

    crypto pretest

    ユーザ名非公開 · 51問 · 8ヶ月前

    crypto pretest

    crypto pretest

    51問 • 8ヶ月前
    ユーザ名非公開

    crypto2

    crypto2

    ユーザ名非公開 · 42問 · 8ヶ月前

    crypto2

    crypto2

    42問 • 8ヶ月前
    ユーザ名非公開

    問題一覧

  • 1

    Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

    Risk

  • 2

    A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

    10 days and $3,200

  • 3

    While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

    Have a meeting with the project sponsor and main stakeholders.

  • 4

    Which of the following tools is best to use for storing lessons learned?

    Wiki knowledge base

  • 5

    During a executive call , A project sponsor found out about issues with the project but could not provide next steps. What needs to be revised?

    Communication plan

  • 6

    During project initiation, a PM is drafting a document with high-level goals and requirements. What is this document?

    Preliminary scope statement

  • 7

    Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

    Validating the deliverables

  • 8

    A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps. Which of the following is the current status of the process?

    The process is out of control and should be revised

  • 9

    A project manager provided details regarding the completion of the following tasks: Vendor selection took less time than planned. Equipment procurement took less time than estimated. Equipment installation went according to schedule. Which of the following should the project manager update?

    Project Gantt

  • 10

    During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

    Gantt chart

  • 11

    A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

    Scope creep

  • 12

    A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?

    Project sponsor

  • 13

    A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

    Time and materials contract

  • 14

    Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?

    Multitiered architecture project

  • 15

    A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

    RFP

  • 16

    During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

    Change log

  • 17

    Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

    Sprint review

  • 18

    Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

    Rollback plan

  • 19

    An enhancement is set to be released into production, and availability issues need to be avoided. Before the release, which of the following should be the most important consideration?

    risk assessnent

  • 20

    A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

    Focus group

  • 21

    A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

    Monthly feedback and training sessions

  • 22

    Which of the following is a quantitative key performance indicator?

    The workers complete tasks on average 25% faster using a new application.

  • 23

    Which of the following software programs would be best to use to store information related to business transactions?

    Enterprise resource planning

  • 24

    Which of the following tools is best to use when conducting project meetings across time zones?

    Videoconference

  • 25

    During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

    defect log

  • 26

    A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

    Defect log

  • 27

    By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

    establish baselines

  • 28

    During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

    Pareto chart

  • 29

    How does data discovery assist with data classification'?

    It shows where specific data is stored

  • 30

    A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

    Agile

  • 31

    During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

    SOW

  • 32

    A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

    A transition plan

  • 33

    During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

    option A

  • 34

    A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

    Proposal

  • 35

    A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

    Project network diagram

  • 36

    Which of the following is a potential challenge that may arise from language barriers among a project team?A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

    A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

  • 37

    A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

    Revise the communication plan.

  • 38

    A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

    Project quality assurance

  • 39

    A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

    Update the issue log.

  • 40

    Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

    Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution

  • 41

    After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

    Smoke test

  • 42

    During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

    Work with the project scheduler to update the project timeline

  • 43

    A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

    Closing contracts

  • 44

    Which of the following are primary features provided by a standard laaS solution? (Select two).

    Storage, Networking

  • 45

    A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

    Pareto

  • 46

    Which of the following best describes the difference between the current state and the desired future state in project management?

    The current state is where the business is now, and the desired state is where the project is going to take the business.

  • 47

    A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

    Smoke

  • 48

    A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

    Data management, Document management

  • 49

    Which of the following is the best example of a breach of physical security?

    Project documentation that is only kept on a removable device

  • 50

    After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

    Have a meeting with the project sponsor to discuss the situation.

  • 51

    A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

    Identify business needs and product descriptions.

  • 52

    A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

    Acceptable communication channels

  • 53

    Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

    Avoiding

  • 54

    During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

    Schedule a call with the vendor PM and vendor executive to review the statement of work

  • 55

    After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

    Customer notification

  • 56

    The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

    Complete the project sign-off.

  • 57

    A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

    Country legal regulations

  • 58

    Which of the following is a consideration when determining a project's ESG factors?

    Corporate values compliance

  • 59

    Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

    Confronting

  • 60

    A project coordinator has started a new project and is reviewing the following characteristics provided by the customer: • Two developers • High uncertainty about existing systems • Risk of frequent requirement changes • Tight deadlines Which of the following project methodologies would be best to use in this situation?

    Scrum

  • 61

    A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

    Time and materials contract

  • 62

    Which of the following software programs would be BEST to use lo store information related to business transactions?

    Customer relationship management

  • 63

    Which of the following aspects are true of waterfall as compared to agile? (Select two).

    In waterfall, solution validation occurs later in the development cycle, Waterfall is less tolerant to changes in scope.

  • 64

    While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

    Contact the PMO for assistance.

  • 65

    During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

    Traceability matrix

  • 66

    A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

    RACI

  • 67

    A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

    Subscription

  • 68

    While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

    Encourage the use of the chat and use plain language when speaking

  • 69

    A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

    Removing access

  • 70

    A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

    Limit access to members of the project team.

  • 71

    During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

    Issue log

  • 72

    Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?

    To ensure that all stakeholders have a shared understanding of the project's objectives

  • 73

    A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?

    The project is ahead of schedule and over budget.

  • 74

    A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

    Meeting minutes

  • 75

    A meeting agenda included the following items: . Review the goals of the project. . Review the progress of the project. . Discuss if the project is ready to move forward. Which of the following best describes this type of meeting?

    Gate review

  • 76

    A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

    Assign additional resources to prevent overwork.

  • 77

    A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

    Informative

  • 78

    A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

    Finish-to-start

  • 79

    Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

    Distribute an agenda.

  • 80

    A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

    SaaS

  • 81

    An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

    The system is lacking proper access controls.

  • 82

    A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

    Ticketing system

  • 83

    A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

    Waterfall

  • 84

    A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

    Stress testing

  • 85

    Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

    Operational security

  • 86

    A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

    laaS

  • 87

    A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

    Use only full-time employees even if the project is delayed

  • 88

    Which of the following best represents an intellectual property breach?

    A service provider that worked on a project uses the developed software on a project for a new customer.

  • 89

    A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

    Perform a gap analysis.

  • 90

    During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

    Quality assurance

  • 91

    Which of the following is an intended outcome of a stand-up meeting?

    To identify blocking tasks

  • 92

    Which of the following pieces of data are examples of Pll?

    IP address and email address

  • 93

    Which of the following is the most important activity for the project manager during the closure of a project?

    Obtain project sign-off.

  • 94

    A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

    Risk, issue

  • 95

    A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

    Decision tree

  • 96

    A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

    Downtime window schedule

  • 97

    A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

    Revise the communication plan.

  • 98

    Which of the following requires the MOST availability from the business team?

    Scrum

  • 99

    For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

    RACI chart

  • 100

    A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

    Backlog