1
PAES 401 (housing for swine Production: The space requirements per animal m2/animal for adult pigs in groups.
2.5
2
Based on PAES: 401(housing for swine Production: Recommended lighting intensity for swine housing for Inspection areas:
200 lux
3
Based on PAES 411:2000, The slaughterhouse shall be located far from any building used for human habitation, and from any factory, public road or public place ______ and should be free from dust, odor, smoke, and other contaminants.
At least 200 meters
4
PAES 401:2001 (Housing for Swine Production): Artificial lighting shall always be available for use during the night or darkened periods of the day. What shall be the lighting intensity to be provided for Breeding, gestation and farrowing area?
150 lux
5
Based on PAES 419: 2000, Agricultural Structures-Warehouse for bagged storage of Grains, Recommended dimensions of warehouse based on capacity what is the recommended structure dimensions of warehouse based on 10,000 cavan capacity?
10m x 30m
6
In PAES 419 - Warehouse for Bagged Storage of Grains, this system of stackingn provides ventilation space between bags and allows circulation of convective air.
Japanese Method
7
PAES 419:2015 (Warehouse for Bagged Storage of Grains): The standard pallet size should be:
152cm x 61cm
8
In PAES 414-2:2002 - Waste Management Structures, the percent moisture content that should be maintained to nourish the composting bacteria.
50-60%
9
Based on PAES 415:2001 what is the minimum aisle width required for determinate crops on the walkway?
0.30m
10
Based on PAES 415:2001 What is the minimum aisle width required for indeterminate crops on the walkway?
0.80m
11
Based on PABES 289:2019: From farm to market road design requirement as of 2014: for slide slope ratio (H:V) what is the minimum fill slope?
1.5:1
12
Based on PABES 289:2019: The typical width of farm-to-market road for a two-lane roadway.
5m
13
Based on PABES 289:2019(FMR) What is the minimum width of sidewalks designed to allow two people to pass?
1.8m
14
Based on PABES 289:2019(FMR) In lower-speed residential areas, what is the allowable range for sidewalk widths?
1.2m to 2.4m
15
Based on PABES 289:2019(FMR) For sidewalks less than 1.5 m wide, how frequently must a passing section be provided to ensure accessibility?
Every 60m
16
Based on PABES 289:2019(FMR) What is the maximum allowable cross slope for sidewalks to accommodate persons with disabilities?
2%
17
PAES 421:2009 (Farm to Market Roads): For concrete road, the maximum slope of road shoulder from the edge of the road carriageway shall be?
4%
18
PAES 421:2009 (Farm to Market Roads): For earth, gravel and bituminous roads, the minimum slope from the center line towards the ditch shall b
3%
19
PAES 421:2009 (Farm to Market Roads): Culverts and storm drains have ideal slope of 2-4 %. What is the absolute minimum slope for culverts and storm drains?
0.5%
20
Based on PAES 421: 2009 (FMR) in construction requirements of bituminous road the bituminous liquid requirement temperature shall be
180 °C
21
It is a system of grading the performance of a constructor for a specific kind of projects using a set of criteria, approved by the NEDA-INFRACOM.
Constructors' Performance Evaluation System (CPES)
22
A plan of action proposed by the constructor to the concerned agency’s implementing office which is aimed to correct the non-conformance findings on the project based.
Corrective Action Plan (CAP)
23
An individual or group of evaluators accredited by CIAP tasked to undertake performance evaluation of a constructor’s project.
Constructors’ Performance Evaluators (CPE)
24
A request form wherein the CPE records his/her validated finding(s) including corresponding location(s) which do not conform to any of the checklist indicators requiring immediate actions by the constructor.
Corrective Action Request
25
The maximum weight rating for Environmental, Safety and Health criteria during construction.
0.07
26
During the constructions phase, how many projects visits are required regardless of the complexity and size of project in the conduct of CPES?
Min. of 2 visits
27
PERT/CPM: It is a hypothetical activity which takes no resource or time to complete. It is represented by broken arrowed line & is used for either distinguishing activities having common starting & finishing events or to identify & maintain proper precedence relationship between activities that are not connected by events
Dummy Activity
28
According to section 701 of the NBC, all buildings proposed for constructions shall be identified according to their use or character of its occupancy. Based on this, agricultural buildings fall under what group?
Group J
29
Slab that can be constructed as one-way or two-way slabs and it is directly supported by columns or walls. It is easy to construct and requires simple formworks.
Flat plates
30
Concrete is poured first then tendons are tensioned.
Post-tensioned Concrete
31
Why is a newly constructed road covered with straw or paper?
To prevent excessive evaporation
32
Slenderness ratio is defined as
Unsupported length over minimum radius of gyration
33
Which of the following represents the maximum moment M for a simple beam with a uniformly distributed load of W and a clear span of L? assume weight of beam to be negligible.
M=𝑊𝐿^2/8
34
Maximum moment occurs at beam section at which shear diagram passes thru
Zero
35
A term used to describe the shape of the beam having negative bending moment.
Hogging