  • 1

    When installing a steel door frame, how many anchors should be installed on each side of the door?

    2

  • 2

    Spreaders are used to maintain____ when the door frame is installed on a block wall

    width

  • 3

    And interior wall with casings is most commonly used with ?

    demountable partitions

  • 4

    compression anchors are used at the top of knockdown frames, and they can keep the miters

    tight and adjust an out of square frame

  • 5

    What gauge steel is used for steel door frames?

    16

  • 6

    The shims should be placed closer to the barrel side of the hinge if you want to

    throw the door

  • 7

    The best type of wood for exterior finishes would be ?

    cedar

  • 8

    The building code says that when installing vertical wood siding we must have a ___mm clearance above the ground

    200

  • 9

    Long, tall walls, where the brick is the cladding require the addition of ?

    expansion joints into the walls

  • 10

    A curtain wall is a non-load bearing wall that supports itself and ?

    exterior finishes

  • 11

    The rain screen principle is a method of cladding that

    Leaves a space behind the cladding for moisture to drain away

  • 12

    Three coats of stucco are supplied. What are the three different coats?

    scratch brown and finish

  • 13

    stucco requires us to install an ___________ as a sheathing membrane over wood frame walls

    asphalt impregnated fibreboard

  • 14

    Final siding has a high expansion and contraction factor due to

    temperature change

  • 15

    Clapboard or bevel sliding can have the

    exposure adjusted

  • 16

    Corrosion resistant nails must be used for

    wood siding

  • 17

    In a built up roof system if that insulation is installed below the roof deck we would be required to incorporate an

    airspace to allow for airflow

  • 18

    The main purpose of a built up roof is to contain the

    roofing materials

  • 19

    A can’t strip is used to create

    A bevelled inside corner between the horizontal roof and a vertical transition

  • 20

    Scupper is an opening in a roof at the

    perimeter to allow water to drain

  • 21

    Steel stud framing can be

    Loadbearing or nonload bearing

  • 22

    Tracks must be the same gauge, or heavier than

    the studs

  • 23

    Lightweight steel stud gauge is ?

    20,22,25

  • 24

    Heavyweight steel stud is ?

    14,16,18,20

  • 25

    Tracks installed for interior walls must be fasten with a minimum of ?

    600mm o.c

  • 26

    Tracks installed on exterior walls must be fastened with a minimum of ?

    300mm o.c

  • 27

    Studs can be secured by

    crimping,screwing,welding

  • 28

    Leading edge of a panel is fastened to the

    open side of the stud first

  • 29

    Corner consisting of two studs is called a ?

    pass through corner

  • 30

    The maximum spacing, when installing resilient channel is ?

    600mm o.c

  • 31

    Steel stud wall studs in a fire, rated assembly are cut how much shorter than the actual wall height ?

    1/2”

  • 32

    The shoe on a lintel must extend a minimum of

    150mm down the trimmer

  • 33

    Panel edges must not be placed in line with the

    edges of an opening

  • 34

    When installing drywall in a house, we always start boarding the

    ceilings first

  • 35

    Type X gypsum board is used to protect framing from

    fires

  • 36

    When using a Spiral saw the correct direction of operation is

    Counter clockwise

  • 37

    Aviation snips would be best suited for cutting ?

    Metal T-bar ceiling tees

  • 38

    Screws should be spaced how far from the edge of the panel ?

    10mm

  • 39

    Taping compounds or adhesives can be used for

    laminating drywall

  • 40

    For an inside curve, the drywall is ?

    wetted on the backside

  • 41

    Plaster grounds are used to control the

    plaster depth

  • 42

    Expansion joint is incorporated into main teas for fire rated assemblies, what what else is installed?

    hold down clips

  • 43

    When chalking a line for a wall angle, where do you mark?

    Mark the top side of the angle

  • 44

    Main tees are installed running the

    length of the room

  • 45

    Border tile should be a minimum of

    1/2 a tile

  • 46

    Suspended ceilings can be

    exposed,semi-concealed or concealed

  • 47

    A suspended drywall ceiling system require

    furring channel to be fastened too

  • 48

    The maximum spacing of furring channel is?

    600mm

  • 49

    If installing hangers for an expose suspended ceiling system, the maximum spacing is ?

    1200mm

  • 50

    How many attachment points are needed for each side of an interior knock down frame ?

    2

  • 51

    when constructing a bulkhead with suspended ceiling Components, what would you fasten it with?

    rivets

  • 52

    The screws for fasting drywall should penetrate how far through the steel stud ?

    10mm

  • 53

    Two types of demountable partition systems are?

    progressive and non-progressive