weld 20 mod 5-8-10 weld 24 midterm
問題一覧
1
Using a properly tinted lens
2
0.30 percent to 0.50 percent
3
weathering steel
4
Needle scaler
5
Twisting the metal in opposite directions
6
edge
7
Fillet welds
8
More preparation time but use less weld material than a V-groove weld
9
Cast iron
10
A feather edge
11
Rotational speed
12
Cut square and beveled
13
Pipe-end prep lathes
14
Pipe-end prep lathes.
15
Air-carbon arc citting
16
Air-carbon cutting
17
Wire core of the electrode
18
Intense heat of the arc
19
Welding consumables
20
Year the specification was last revised
21
The client requirements and job specification
22
F3 fast-freeze
23
F4 low-hydrogen
24
1/2 hour to 4 hours
25
40 degrees F (4.5 degrees C)
26
F4 low hydrogen
27
Straightedge
28
Combination square
29
Pipe joint misalignment
30
A structural member
31
One side of the strongback
32
Strongbacks
33
Four-legged jack stands
34
Allow welds to be made under the clamp
35
Chain clamps
36
Residual stress
37
Shrinkage
38
Pipe sizes 5" (DN125) or smaller
39
Welding code
40
Welding Procedure Specifications (WPS)
41
Applicable code
weld 20 test 6-11-12
weld 20 test 6-11-12
ユーザ名非公開 · 39問 · 1年前weld 20 test 6-11-12
weld 20 test 6-11-12
39問 • 1年前weld 21 test 1,2,7
weld 21 test 1,2,7
ユーザ名非公開 · 57問 · 1年前weld 21 test 1,2,7
weld 21 test 1,2,7
57問 • 1年前weld 21 test 1,2,7 / wld 24 midterm
weld 21 test 1,2,7 / wld 24 midterm
ユーザ名非公開 · 57問 · 11ヶ月前weld 21 test 1,2,7 / wld 24 midterm
weld 21 test 1,2,7 / wld 24 midterm
57問 • 11ヶ月前問題一覧
1
Using a properly tinted lens
2
0.30 percent to 0.50 percent
3
weathering steel
4
Needle scaler
5
Twisting the metal in opposite directions
6
edge
7
Fillet welds
8
More preparation time but use less weld material than a V-groove weld
9
Cast iron
10
A feather edge
11
Rotational speed
12
Cut square and beveled
13
Pipe-end prep lathes
14
Pipe-end prep lathes.
15
Air-carbon arc citting
16
Air-carbon cutting
17
Wire core of the electrode
18
Intense heat of the arc
19
Welding consumables
20
Year the specification was last revised
21
The client requirements and job specification
22
F3 fast-freeze
23
F4 low-hydrogen
24
1/2 hour to 4 hours
25
40 degrees F (4.5 degrees C)
26
F4 low hydrogen
27
Straightedge
28
Combination square
29
Pipe joint misalignment
30
A structural member
31
One side of the strongback
32
Strongbacks
33
Four-legged jack stands
34
Allow welds to be made under the clamp
35
Chain clamps
36
Residual stress
37
Shrinkage
38
Pipe sizes 5" (DN125) or smaller
39
Welding code
40
Welding Procedure Specifications (WPS)
41
Applicable code