    The method of mining for surface Highwall or out recovery of coal by boring or excavation openings

    Auger mining

  • 2

    The amount of oxygen in underground mines required under the revised mind safety rules and regulation is

    20% by volume

  • 3

    In planning and development, what is the main factor for determining the bench height and an open pit?

    Equipment specification

  • 4

    Occurs when an obstruction to the flow is encountered, and the velocity of the medium is great enough

    Impingement

  • 5

    What is the importance of defining the pit limit?

    to determine the amount of mineable ore

  • 6

    It is the underground mind gas otherwise called as white dump

    Carbon monoxide

  • 7

    Refers to the timbering or concrete around the mass or top of the shaft

    Collar

  • 8

    cut and fill stoping, shrinkage stoping VCR stoping And long wall mining our methods that are

    Artificially supported

  • 9

    How many drivers are required for mining company that operates 10 dump trucks running 24 hours a day in a shift of two shift schedule considering 85% mechanical availability and 10% manpower availability

    19

  • 10

    The condition of the surrounding rock in in situ Mining

    Impermeable

  • 11

    Underground mining method used to extract mineral deposits that are roughly tabular, strong flat or simply dipping and generally in contact with strong wall rock

    Unsupported

  • 12

    A type of anemometer suitable for measuring very high velocities than special anemometer

    Pitot tube apparatus

  • 13

    All unit operations involve in extracting or excavating or moving bulk materials or minerals during mining

    Materials handling

  • 14

    Mine gas produce as a result of poor blasting

    Nitrous oxide

  • 15

    An overhand mining in which the ore is mine in horizontal slices and remains in the slope as a temporary support for the walls and to provide a working platform

    Shrinkage stoping

  • 16

    The concept of replacing the intermittent operations of rock, breakage, and material handling in mining with system of continuous extraction

    Rapid excavation

  • 17

    The underwater excavation deposit usually carry out the floating vessel, which may and corporate processing and was posting facilities

    None of these

  • 18

    Open excavation from which ore is removed from by gravity through a race or connecting to underground, haulageways

    Glory hole

  • 19

    The mixture of gases which remains in a mind after a mind, fire or an explosion of fire, dump or cool dust

    After Dump

  • 20

    During the first shift for 24 hour operation with a two shifting schedule a deal machine was in operation for 10.5 hours and under what you prepared for 3.5 hours within this timeframe, the drill machine achieve the production of 251 m calculate the percentage utilization of the drill machine during the first shift

    88%

  • 21

    The practice of removing the gas contained in the coal seam and adjoining strata through wellbores, drill holes, and pipeline

    Methane drainage

  • 22

    the process wherein large quantities of hot water are introduced to wells drilled into buried deposit of native sulfur

    Frasch process

  • 23

    A method of caving that utilizes the weight of an ore column that is being given to crash itself into sizes, small enough to pass through drop points that have been prepared beforehand

    Block caving

  • 24

    It is a vertical or horizontal opening to the surface where air enters and circulate inside the mine with the aid of different fans

    Intake

  • 25

    In borehole extraction or aqueous extraction rock should be

    Competent and impermeable

  • 26

    produces pressure by importing a Tangential acceleration to air as it proceeds to the impeller

    Axial flow fan

  • 27

    A surface mining method where the overburden is stripped first and dumped at the same time then the body is mine horizontally in a single bench

    Strip mining

  • 28

    It is timbered stope but classified as a self-supporting opening because the timbers are not used as support, but to provide working platforms for miners the method is applicable to very narrow veins so that the timber to be used or normally 5 to 6 feet

    Stull stope

  • 29

    It is called the back ‘pressure results’ from the inside of the vent tube or drift not being perfectly smooth. The air cannot move along the tube or drift as fast as the fan would like to blow more air into the airway does producing friction.

    Static head

  • 30

    It is a type of ventilation which is efficient and generally dependable

    Mechanical ventilation

  • 31

    The most expensive among the placer mining methods

    Dredging

  • 32

    A term applied the carbon monoxide or atmosphere containing lethal quantities of carbon monoxide

    White damp

  • 33

    The threshold limits value of hydrogen sulfide as per Revised mine, safety rules, and regulation

    0.10% by volume

  • 34

    An effective way to operate a mine with conventional haulage methods in an inclined seam or bed is to drive all openings cross pitch that is

    At an angle to the strike of the deposit

  • 35

    It is the underground mine gas otherwise called a marsh gas

    Methane

  • 36

    A surface or near surface deposit usually tabular, and maybe of considered durable aerial extend containing a mineral particles in detritus

    Detrital deposit

  • 37

    It is the underground mine gas otherwise called choke or black damp

    Carbon dioxide

  • 38

    The total area around an airway is called

    Rubbing surface

  • 39

    Underground mining method used by small scale miners

    Gophering

  • 40

    The unexcavated face of exposed over burden and coal or an ore In an open cast mining or the face or bank on the uphill side of a contour strip mine excavation

    High wall

  • 41

    According to the fan law twice the volume develops, how many times the pressure

    Four times the pressure

  • 42

    Methane is explosive with this range of concentration

    5% to 15% by volume

  • 43

    The oldest method of my name, both coal And most metallic ores

    Room and Pillar

  • 44

    Basically, a continuous large volume digging machine attached to gravity concentrating facility with waste removal systems contained on floating platform

    Dredge

  • 45

    Prolonged exposure of miners to coal dust causes

    Anthracosis

  • 46

    During the First shift of 24 hour operation with a two shifting schedule a drill machine was an operation for 10.5 hours and underwent repairs for 0.5 hours within this timeframe, the drill machine achieved a production of 251 m calculate the percentage utilization of the drill machine during the first chef

    88%

  • 47

    In the layering of gases after an underground explosion, which of these gases slice on top

    Methane

  • 48

    it is the underground mine gas otherwise called as “ laughing gas”

    Nitrogen dioxide

  • 49

    Hydrogen gas is exclusive with this range of concentration

    4% to 74% by volume

  • 50

    The most predominant method of mining worldwide

    Open pit mining

  • 51

    In a mind with 2000 employees where 100 were on sickleave and another were on vacation leave for a particular month. There were 18 last time accident assuming the employees worked for 25 days and no one worked overtime. What was the accident Frequency per million hours

    50

  • 52

    The Costliest method in underground mining

    Square set stoping

  • 53

    Any source of potential damage harm or adverse Health effects on something or someone

    Hazard

  • 54

    Used to measure moderate velocity airflow

    Vane anemometer

  • 55

    The losses and energy due to the roughness of the wall

    Frictional pressure losses

  • 56

    Sublevel block caving is a hybrid between sublevel caving and block caving introduced to counter

    Problems in block, caving regarding stability reinforcement and secondary blasting problems

  • 57

    A system of Transporting ore Consisting essentially of head frame head, winding machine, and winding ropes

    Hoisting

  • 58

    In class be mine, the safety engineer required should be

    One full-time

  • 59

    The threshold limits Value of carbon dioxide as per revised mines safety rules, and regulation

    0.50% by volume

  • 60

    Pressure exerted By the air on the walls of the containing vessel

    Static pressure

  • 61

    The unsupported and underground mining methods can be used in any type except in

    Placer deposits

  • 62

    tailings and slurries Maybe ask backfill in a subsidence area

    False

  • 63

    A product of mine explosion and is given off by gasoline motors during the donation of negating, oxygen balance explosives

    Carbon monoxide

  • 64

    The percentage of Time the equipment is available to perform its intended function over a defined period of time when it is required by operation

    Mechanical availability

  • 65

    Investigation reports discussing this severity of an accident in case of fatal or serious accident shall be made

    Within 15 calendar days from the date of accident

  • 66

    Mine gas that supports combustion

    Oxygen

  • 67

    An excavator loads dump trucks in a mining operation. The excavator has a cycle time of two minutes each dump trucks have a capacity of 80 tons and requires eight buckets to fill determine the number of dump trucks that can be loaded per hour, assuming an 80% utilization rate.

    Three units

  • 68

    The ideal number of members of a miner rescue team should be

    Five

  • 69

    In the context of mine production optimization, which of the following factors can contribute to increase operational, efficiency, and productivity

    Adequate Maintenance and minimized equipment breakdown

  • 70

    Validity of all safety, engineer, or safety inspector permits

    Three years

  • 71

    At what temperature are Celsius and Fahrenheit equal

    -40 Fahrenheit and -40°C

  • 72

    The faster, the air moves the lower pressure

    Bernoulli’s principal

  • 73

    Sublevel keeping method requires to be called so due to the fact that

    The country rock are hanging wall and football caves

  • 74

    A large scale or bulk mining method that is highly productive low in cost and use primarily on massive deposits that must be underground

    Block caving

  • 75

    The temporary saves, the inspector should renew its temporary license every

    Every year

  • 76

    Sublevel caving layout depends primarily on the size and shape of the ore body for steeply dipping and narrow ore bodies, the appropriate layout is

    Longitude layout

  • 77

    It is any division or branch of ventilation circuit

    Air split

  • 78

    Lung ailment caused by for belonged exposure to tin dust

    Stanosis

  • 79

    During the first shift of a 24 hour operation with a two shifting schedule a drill machine was an operation for 10.5 hours and under one repairs for 0.5 hours within this timeframe, digital machine achieved a production of 251 m calculate the penetration rate of the drill machine

    24 m/h

  • 80

    The class A mine underground has at least of number ____ Workers