    True or false, crew members should hold inside of munition skids when aligning cannister with align pins?

    True for PAC2, false for PAC3

  • 2

    TM _______ covers M9834A

    9-2320-340-10

  • 3

    True or false, patriot launchers can only be emplaced in two distance envelopes to courier the threat.

    False

  • 4

    True or false, communications line of sight is required for remote launchers.

    False

  • 5

    True or false, if the GMT is out of level more than 10 degrees, unloved indicator light (GREEN) and buzzer will sound.

    True

  • 6

    Solid rocket motors produce toxic gases. Remain at least ___ ft upwind of a launcher for a min of 5 minutes following a missile launch.

    500

  • 7

    True or false, perform launching station stray/no voltage check must be conducted as a part of missile stability check.

    True

  • 8

    A class ____ leak is a leakage great enough to form drops, but not great enough to form drops from items being checked.

    2

  • 9

    Stay out of the area within ____ meters from in front of the RS and within maximum angular

    120m (front) 2m (sides) 2m (back)

  • 10

    True or false, before lowering the LS platform, ensure the quadrail is not installed around the generator unless quadrail has been modified.

    True

  • 11

    True or false, the LS can have a mix of up to 2 PAC3 canisters on one side of the launcher and 3 ATM/MSE kitted

    True

  • 12

    The paper humidity indicator on the canister instrument panel should show blue in sectors 30, 40 and 50 or digital humidity indicator should read ___ % or less when button is pressed

    30

  • 13

    Table VI is the certification that delineates ____ levels of proficiency.

    Basic

  • 14

    DAGR stands for? Used for?

    Defense Advanced Global Positioning System Reciever. Provides position, elevation and time data.

  • 15

    Drill _____ covers emplacing PAC3 LS

    44-CW-D0190

  • 16

    PM&E is a subtask of table ____ training and should be conducted ____ IAW TC3-01.86.

    1, twice weekly

  • 17

    RL1 refers to any LS emplaced more than 1.3km radius from the radar, but not exceeding a ____km radius.

    10

  • 18

    True or false, a canister that has been dropped 12 inches or more and remains in the canister shall be considered UNARMED.

    False

  • 19

    When performing the missile selectability, a warm up time of up to ____min for PAC3 missiles is necessary.

    10

  • 20

    ____ ground guides are required at all times to safely move GMs with the forklift.

    2

  • 21

    The LS is lowered by a M983 10ton tractor and can be placed on a slope of ____ degrees.

    10

  • 22

    A class ____ leak is a seepage of fluid not great enough to form drops.

    Class 1

  • 23

    True or false, ensure tires are off the ground when deploying outriggers and leveling the GMT.

    False

  • 24

    RL-3 refers to any LS more than a _____km radius from the RS, but not exceeding a _____km radius and using a CRG or an ECS as an LCS.

    6, 30

  • 25

    True or false, the ATM-3/MSE interceptor comes in a one pack canister consisting of a single launch tube, which serves as a shipping/storage/launch container for one missile. The ATM3 interceptor one pack must be knitted to create a two-pack configuration, which is required for loading and unloading.

    True

  • 26

    True or false, when a live missile is dropped more than 12inches, all personnel should evacuate at least 381 meters/1250 feet away.

    True

  • 27

    At what frequency are basic system skills trained IAW TC3-01.85?

    Twice weekly

  • 28

    True or false, one canister must be empty to lift a two stack. Hoisting equipment and equipment tie-downs will not stand the weight if both canisters are loaded.

    True

  • 29

    True or false, patriot launchers can only be emplaced in 2 distance envelopes to counter the threat, local and RL-3.

    False

  • 30

    RL-1 refers to any LS emplaced more than 1.3km radius from the radar, but not exceeding a ____km radius.

    10

  • 31

    The LS is towed by a M983 10-ton tractor and can emplaced on a slope of ____ degrees or less.

    10

  • 32

    If top corner of canister are painted with 4 inch yellow square missile is _____.

    Live

  • 33

    During the forklift missile reload crew member ___ is responsible for powering down LEM/ELES

    1

  • 34

    True or false, when performing GMT reload do not stack off-loaded canisters on top of each other.

    True

  • 35

    Wood runners with cracks over _____ inches long that extend completely through runners are unserviceable.

    5

  • 36

    Local LS must be located within ____km of radar coordinates and within sector of 80 degrees the radar PTL.