問題一覧
1
What is the maximum gradient for curb cut-outs?
1:12
2
What is the maximum gradient for sidewalk as per BP344?
1:20
3
As per BP344 requirement, what is walking speed design on the crossings?
0.90m/sec
4
What is the length of tangent between reverse curves for both Tourism and FMR?
30m
5
For roadway obstructions, such as bridge piers, what is the width of the black and white stripes on the object markings?
300mm
6
For roadway obstructions, what is the minimum width of the black and white stripes on the object markings?
100mm
7
For raised median island, planting trees should not be permitted on high-speed multi-lane divided highway and the surface of the soil fill shall be lower than the top of island - 50mm for island height less than or equal to _____ and 10mm for island height greater than _____.
0.45m
8
The pavement thickness of turnout, unloading and loading bays shall in no case be less than ____ for asphalt and 230mm for concrete with supporting base layers.
100mm
9
During road reblocking works, holes of ____ diameter and spaced at 300mm shall be drilled at 1/2 of the existing concrete pavement thickness to permit load transfer transverse construction joints.
260mm
10
What Department Order is the Project and Contract Management Procedures and Application Policy Update?
D.O. 15 series of 2018
11
To correct the original contract duration in the PCMA, the ___________ should request for Data Change Request.
Procuring Unit
12
Which office is authorized to approve project/ contract revisions in PCMA?
Bureau of Construction
13
Which module in PCMA is used to generate summaries and reports?
Civil Works Monitoring
14
Which module in PCMA is used to package a contract?
Construction Program Management
15
Which module in PCMA is used to access pay item library?
PCMA Administration
16
Which module in PCMA is used to input actual work accomplishments?
Contract Management
17
The Head of Implementing Office shall submit within ___ calendar days upon the approval of CTE, a certified true copy of the approved CTE and corresponding revised construction schedule together with all supporting documents as per DOTS, to the Bureau of Construction for the eventual approval of the revised schedule in the PCMA.
30
18
Which tab under Contract Management module is used to record cause/s of delay?
Monthly Reviews
19
The PCMA is the official monitoring system for ____ projects and onwards.
2016
20
Regional Director Jovel G. Mendoza’s network ID should be _____.
mendozajg
21
Who is accountable in assigning Department Authorities in the PCMA?
Monitoring Engineer
22
See encircled part with label “2”
Module
23
See encircled part with label “3”
Tab
24
See encircled part with label “4”
Folder
25
Refers to an increase in the contract price during contract implementation on the basis of the existence of extraordinary circumstances as determined by NEDA and upon prior approval of GPPB.
Price Escalation
26
What does GPPB mean?
Government Procurement Policy Board
27
This form of VO may be issued by the implementing official to cover any increase / decrease in quantities of original work items in the contract.
Change Order
28
Who is the approving authority for extension of contract time due tonthe Variation Order?
Head of Implementing Office
29
Any cumulative positive Variation Order beyond how many percent of the original contract price shall be subject of another contract to be bid out of the works are separable from the original contract?
10%
30
It is considered to be the preliminary stage of the procedure in the preparation of the variation order proper. It consists of tentative information as to cost (if possible to be included) and contains the technical justification to which the reasons the variation order is proposed.
Preclearance
31
It is a project document that may be issued by the procuring entity to the contractor to cover such as but nit limited to reclassification of work items that are duebto change of plans, design or alignment to suit the actual field conditions.
Variation Order
32
The term used to describe the period through which a contract is effective.
Contract Duration
33
It is a written order issued by the DPWH Project Engineer/ Engineer's Representative and approved by the concerned Head of the I.O. to the contractor to resume construction operations covered by a previous Work Suspension Order, after the cause of or reason for the work suspension has been resolved.
Work Resumption Order
34
It is a written order to the contractor issued by the DPWH Project Engineer/ Engineer's Representative and approved by the authorized DPWH officials to suspend the contract work wholly or partly for such period as may be deemed necessary.
Work Suspension Order
35
It is a written authority, issued by the DPWH Project Engineer and approved by the duly authorized DPWH Officials, prior to the contract expiration, granting the contractor additional time beyond the approved completion in order to carry out remaining works or any additional works, on account of other special circumstances that warrant such additional contract time.
Contract Time Extension
36
The cumulative inclusive period the District Engineer is authorized to approved WSO and CTE as per D.O. 39, series of 2024.
90 calendar days
37
This immediately disqualifies the erring contractor from participating in the bidding of all government projects upon issuance.
Blacklisting Order
38
What is the maximum percentage the contractor can request for an Advance Payment?
15%
39
What is the Department Order for the Implementation of the DoTS for Civil Works?
D.O. 11 series of 2021
40
What is the maximum period for the contractor to rectify the Notice of Defects/ Deficiencies after the receipt of Completion Inspection Report?
90 days
41
How many years is the period covered for the warranty against Structural Defects and Failures for Semi-Permanent Structures?
5 years
42
Liquidated damages should be computed equivalent to _____ of the cost of the unperformed portion of the works for every day of delay.
1/10 of 1%
43
Retention Money to be deducted is equivalent to __% of the _____ this billing amount before the contract had reached 50% accomplishment.
10% gross amount
44
________ is the first official meeting between the contractor, the assigned DPWH field engineers in the project, and the end-user of the project (if any) and other concerned stakeholders.
Pre-construction meeting
45
________ is best described as the deployment of resources at the project site. This also involves any work that is necessary to provide access to the site.
Mobilization
46
_________ is an activity necessary to verify the actual field condition and to identify modifications and other deviations in the project.
As-Stake Survey
47
Involves watching the progress of a project against time, resources and performance schedules during the execution of the project and identifying lagging areas requiring timely attention and action.
Project Monitoring
48
Process and activities needed to correct deviations.
Project Control
49
It is the delays by the contractor in the implementation of contract.
Slippage
50
The calibrated action where the contractor incurred a negative slippage of 5% and shall be given a warning and require to submit a detailed "catch-up" program on a fortnightly (2 weeks) basis to eliminate the slippage.
Early Warning Stage
51
The calibrated action where the contractor incurred a negative slippage of 10% and directed to submit a more detailed program of activities with weekly physical targets, together with the required additional input resources to accelerate work accomplishment and reduce the slippage over a defined time period.
ICU Stage
52
In project component IDs, the suffix used for Visayas is __.
VS
53
PCMA stands for _________________________.
Project and Contract Management Application
54
Who is accountable in updating actual work activities and revised construction schedules?
Project Engineer
55
Whose account should be used in “Contract Packaging”?
Monitoring Engineer
56
To protect the interests of government whenever disputes occur, it is imperative that the construction records documenting day-by-day events and project activities be properly established and maintained.
Project Records
57
A single work step with a definable scope of work, an identifiable start and finish requiring time and typically resources to complete.
Activity
58
Suggested design flood protection level for Principal and Major Rivers
100-year for areas 40sq.km. and above
59
What is the minimum freeboard for dike and revetment structures?
0.60m
60
Sabo is a Japanese word of origin which means “Sa” = ____ and “Bo” = _____.
Sediment, Prevention
61
Minimum size of pipe in order to allow passage of debris and also for maintenance purposes.
910mm
62
RIDF means
Rainfall Intensity Duration Frequency
63
It is the start of the census survey for PAPs and tagging of structures and other improvement. Structures built after this day is not eligible for compensation.
Date of filing for compensation