問題一覧
1
Provisions for SpeciaI lnspection program shall be submitted to the Building Official:
Prior to issuance of a building permit
2
The statement of Special Inspections must include:
all of the above
3
Periodic Special Inspection is:
part-time or intermittent observation of the work (intermittently present where the work to be inspected has been or is being performed)
4
Continuous Special Inspection means:
The inspector is on site observing the work requiring Special Inspection (present when and where the work is to be inspected is being performed)
5
The Special Inspector is be employed by:
either “a” or “b”
6
The Special Inspector must be qualified and demonstrate competence to the satisfaction of:
the Building Official
7
Special Inspections may be waived by the Building Official if:
construction is of a minor nature
8
A fabricated item is:
structural, load-bearing assemblies of materials assembled prior to installation in the building
9
To be an approved agency:
all of the above
10
The Special Inspector is to:
all of the above
11
To become an approved Fabricator, the Fabricator must have:
all of the above
12
Special Inspection of work performed at a Fabricator’s shop is waived provided:
both “a” and “b”
13
If no welding, cutting or heating is performed as a part of steel fabrication:
no Special Inspection of fabrication is required, but the Fabricator must submit and implement a procedure for material control
14
The tops of anchor bolts must be:
at least flush with the top of the nut
15
Except for certain types and sizes of welds, inspection of structural welding is to be done:
during the welding operations
16
Welds eligible for periodic inspection include:
all of the above
17
Welding of stairs and railing systems:
may be inspected on a periodic basis
18
The Special Inspector shall perform an inspection of the steel frame to verify proper construction of:
all of the above
19
For bolted connections, the Special Inspector must check:
all of the above
20
For pretentioned bolted joints, the Special Inspector must:
both “a” and “b”
21
Periodic monitoring of bolt installation for pretentioned bolts is permitted:
any of the above
22
Continuous monitoring of bolt installation of pretensioned joints is required:
either “a” or “b”
23
Special Inspections for seismic resistance of structural steel shall be in accordance with:
the quality assurance provisions of AISC 341
24
Special Inspection of structual steel shall be in accordance with:
the quality assurance provisions of AISC 360
25
Special Inspection for seismic resistance of structural steel shall be in accordance with:
the quality assurance provisions of AISC 341